Van Doren Roofing & Cornice Co. v. Guardian Casualty & Guaranty Co.

168 P. 1124, 99 Wash. 68, 1917 Wash. LEXIS 1023
CourtWashington Supreme Court
DecidedNovember 22, 1917
DocketNo. 14094
StatusPublished
Cited by14 cases

This text of 168 P. 1124 (Van Doren Roofing & Cornice Co. v. Guardian Casualty & Guaranty Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Doren Roofing & Cornice Co. v. Guardian Casualty & Guaranty Co., 168 P. 1124, 99 Wash. 68, 1917 Wash. LEXIS 1023 (Wash. 1917).

Opinion

Ellis, C. J.

Defendant Manhattan Contracting Company, as contractor, erected a transit shed for the port of Seattle at a contract price of $34,760, of which sum twenty-[70]*70five per cent was to be withheld until all claims for labor and material had been satisfied. To secure payment of such claims, two statutory bonds complying with the provisions of Rem. Code, § 1159 were given, one for $30,000, with the Guardian Casualty & Guaranty Company as surety, the other for $4,760, with Reeves Aylmore, Jr.? and A. V. Smith as sureties. The contract and bonds were executed on December 29, 1915. During the progress of the work, a number of materialmen’s claims were filed with the Port of Seattle. The validity of some of these being disputed, the Port of Seattle refused to complete payment of the contract price and withheld a balance of $13,853.27, which was more than $5,000 in excess of the twenty-five per cent. The sum so withheld was finally paid into the registry of the court to await the court’s order. Van Doren Roofing & Cornice Company, a material claimant, brought an action in interpleader to determine the respective rights of the various claimants to this fund. The Canal Lumber Company brought a separate action to enforce its claims for materials. These actions were ordered consolidated for the purpose of trial. By stipulation they were actually tried separately, but are treated as consolidated on this appeal. A number of other claimants, including Dalk & Lindberg, Seattle Construction & Dry Dock Company, and American Savings Bank & Trust Company were made parties defendant or intervened and cross-complained to establish their respective rights to the fund and against the .statutory bonds. After trial, judgment was entered in favor of various claimants against the contractor and its surety, the Guardian Casualty & Guaranty Company. Both of these defendants gave notice of appeal, but the latter alone has perfected its appeal, and in this court contests only the claims of Dalk & Lindberg, Seattle Construction & Dry Dock Company, Canal Lumber Company, and American Savings Bank & Trust Company. We shall discuss the errors assigned generally as they apply to the facts connected with the respective claims.

[71]*71I. Dalk & Lindberg were awarded judgment against Manhattan Contracting Company and Guardian Casualty & Guaranty Company for materials furnished in the sum of $1,062.20, with interest, and an attorney’s fee of $150. Their notice of claim filed with the Port of Seattle was as follows:

January 5tb, 1916.
Port of Seattle, Port Commission,
Gentlemen: You are hereby notified that the Manhattan Contracting Co. still owes us $1,062.20 for materials furnished East Water Building Transit Shed on Wharf No. 2. Wish yon would hold out that amount from their contract or make some arrangement to pay our claim. Yours truly,
(Signed) Dalk & Lindb.erg.
Appellants contend that* this claim was insufficient, in that it gave no notice of any intention to assert a claim against the statutory bonds, hence did not comply with Rem. Code, § 1161, which prescribes that the notice in such cases shall state that the claimant “has a claim in the sum of...... dollars......against the bond......”
It is true that this notice is a mere statement of the balance due and a request that the Port of Seattle hold out the amount or make some arrangement to pay it. It contains no statement of an intention to hold the surety on the bond. In Rodgers v. Fidelity & Deposit Co., 89 Wash. 316, 154 Pac. 444, cited by appellant, touching a similar notice, we said:
“The sureties upon such bonds have a right to know what claims are being made against them, by timely filing of the required notice. It is not enough that the claimant makes some claim against the contractor, his debtor, or against the funds which may be due the contractor.”

In Robinson Mfg. Co. v. Bradley, 71 Wash. 611, 129 Pac. 382, a similar notice was held insufficient. In the case here, however, appellant received actual notice of the filing of the claim and thereafter treated it as sufficient. The Port of Seattle at once sent to the contractor and to appellant a written notice as follows:

[72]*72“There has been this day filed with the Port of Seattle a claim against you and your bondsmen in amount $1,062.20, by Dalk & Lindberg.”

But appellant, relying upon the decision in Robinson Mfg. Co. v. Bradley, supra, asserts that actual notice cannot take the place of the filing of a notice with the municipality specifically asserting a claim against the bond. In the Bradley case, however, the actual notice went no further than the written notice filed with the library board, which was merely notice that the claim was due and unpaid. In the case here, the port commission evidently construed the notice filed with it as a claim against the bond, and so interpreted it in its notice to the contractor and bondsmen. We think that the doctrine in the Bradley case should not be extended, especially where, as in this case, the pleading shows that the surety was not misled, but at all times prior to trial treated the notice as a sufficient claim against the bond. The Manhattan Contracting Company and the Guardian Casualty & Guaranty Company, its bondsman, answered the cross-complaint of Dalk & Lindberg, denying generally the paragraph thereof in which was alleged the filing of the claim with the Port of Seattle, and denying specifically that $250 was a reasonable attorney’s fee as therein alleged, but these answers further affirmatively averred that the contractor nor its bondsman “has never disputed the claim of said cross-complainant and has never refused to pay the same,” and set up, as an excuse for the failure to pay this claim, the fact that other claimants had filed fraudulent claims, because of which the Port of Seattle was withholding money due on the contract.. These answers close as follows:

“A tender is hereby made by this defendant to this cross-complainant out of said money in the registry of the court of the amount of its claim.”

Dalk & Lindberg demurred to this affirmative matter in each answer, on the ground that it constituted no defense in law. The demurrers were sustained, but the affirmative mat[73]*73ter was not stricken from either of the answers, and though held on demurrer insufficient in law as a defense, it still stood as an admitted fact. Nowhere in appellant’s pleading is the sufficiency of the claim specifically assailed. There is a mere denial that the claim was filed. There is no claim, even here, that appellant was misled by the notice given. On the contrary, the admission above quoted shows affirmatively that it was not misled. Notwithstanding this admission, the court permitted full evidence to be taken as to the amount of the claim and as to the character of the claim filed. He concluded, however, that “so long as the bonding company received any notice and was not misled that is sufficient.” While the court’s statement is somewhat broader than is warranted by our decisions, we are satisfied that it is warranted in the light of the evidence coupled with the admission in the pleading. As to the probative effect of such admissions, see:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutson v. Wenatchee Federal Savings & Loan Ass'n
588 P.2d 1192 (Court of Appeals of Washington, 1978)
Grant County Constructors v. E. v. Lane Corp.
459 P.2d 947 (Washington Supreme Court, 1969)
Gwinn v. Cleaver
354 P.2d 913 (Washington Supreme Court, 1960)
Smith v. Smith
351 P.2d 142 (Washington Supreme Court, 1960)
Washington Fish & Oyster Co. v. G. P. Halferty & Co.
269 P.2d 806 (Washington Supreme Court, 1954)
City of Seattle v. Northern Pacific Railway Co.
121 P.2d 382 (Washington Supreme Court, 1942)
Champlin v. Transport Motor Co.
33 P.2d 82 (Washington Supreme Court, 1934)
Standard Accident Insurance v. Interlocking Tile Corp.
6 P.2d 383 (Washington Supreme Court, 1932)
United States Fidelity & Guaranty Co. v. City of Montesano
295 P. 934 (Washington Supreme Court, 1931)
Barrett Bros. Co. v. County of St. Louis
206 N.W. 49 (Supreme Court of Minnesota, 1925)
King County v. Guardian Casualty & Guaranty Co.
175 P. 166 (Washington Supreme Court, 1918)
National Surety Co. v. American Savings Bank & Trust Co.
172 P. 264 (Washington Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
168 P. 1124, 99 Wash. 68, 1917 Wash. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-doren-roofing-cornice-co-v-guardian-casualty-guaranty-co-wash-1917.