United States Fidelity & Guaranty Co. v. City of Montesano

295 P. 934, 160 Wash. 565, 1931 Wash. LEXIS 930
CourtWashington Supreme Court
DecidedFebruary 3, 1931
DocketNo. 22631. Department Two.
StatusPublished
Cited by11 cases

This text of 295 P. 934 (United States Fidelity & Guaranty Co. v. City of Montesano) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. City of Montesano, 295 P. 934, 160 Wash. 565, 1931 Wash. LEXIS 930 (Wash. 1931).

Opinion

Millard, J.

The surety on the bond of the contractors who constructed a bridge for the city of Mon-tesano paid a materialman’s lien, timely filed, against that bond. Before the filing of that claim of lien, and prior to the expiration of thirty days after the acceptance of the bridge, the city paid the contractors the retained percentage on the contract. Alleging the foregoing facts, the surety instituted this action against the city, to recover the amount the city was required by the contract and by the statute to retain for thirty days after the acceptance of the bridge. Trial of the cause resulted in judgment of dismissal. The plaintiff has appealed.

On April 10, 1928, the city of Montesano entered into a contract with Robert Morgan and J. Leonard Hall, contractors, by the terms of which the contractors agreed to construct and install a bridge for the city, the work to be completed on or before June 1, 1928. The contract stipulated that the city retain, from the moneys earned by the contractors, a sum equal to fifteen per cent, as a retained percentage, to be withheld for a period of thirty days following the final completion and acceptance of the entire work by the city. That stipulation is in accordance with the statute relating to public improvement contracts, *567 which provides for the retention of a portion of the contract price, as a reserve fund, for a period of thirty days after the completion and acceptance of the work under such contract. Those furnishing materials and performing labor towards the completion of the improvement, are entitled to a lien against the reserve fund, if notice of claim is timely filed. The statute reads as follows:

“That contracts for public improvements or work by the state, or any county, city, town, district, board or other public body, shall provide, and there shall be reserved from the moneys earned by the contractor on estimates during the progress of the improvement or work, a sum equal to fifteen per cent (15%) of such estimates, said sum to be retained by the state, county, city, town, district board or other public body, as a trust fund for the protection and payment of any person or persons, mechanic, subcontractor or material-man who shall perform any labor upon such contract or the doing of said work, and all persons who shall supply such person or persons or subcontractors with provisions and supplies for the carrying on of such work. Said fund shall be retained for a period of thirty (30) days following the final acceptance of said improvement or work as completed, and every person performing labor or furnishing supplies towards the completion of said improvement or work shall have a lien upon said fund so reserved, provided such notice of lien of such claimant shall be given in the manner and within the time provided in section 1161 of this Code as now existing and in accordance with any amendments that may hereafter be made thereto: Provided, however, That where in any improvement or work the contract price shall exceed two hundred thousand dollars ($200,000), but ten per cent (10%) shall be reserved on estimates in excess of said sum or where the aggregate of previous estimates equals or exceeds said amount. The provisions of this act shall be deemed exclusive and shall supersede all provisions and regulations in conflict herewith.” Bern. Comp. Stat., §10320.
*568 “That after the expiration of thirty (30) days following the final acceptance of said improvement or work, and the expiration of the time for the filing of lien claims, as herein provided, said reserve, or all amounts thereof in excess of a sufficient sum to meet and discharge the claims of materialmen and laborers who have filed their claims, as provided for in section 10320, together with a sum sufficient to defray the cost of such action and to pay attorneys ’ fees, shall be paid to said contractor. ’ ’ Bern. Comp. Stát., § 10321.
“Any person, firm or corporation filing a lien claim against said reserve fund shall have four (4) months from the time of the filing of claim against said fund in which to bring an action for the foreclosure of such lien. The liens provided for in this chapter shall be enforced by a civil action in the superior court of the county wherein the lien was filed, and shall be governed by the laws regulating the proceedings in civil actions touching the mode and manner of trial, and the proceedings and laws to secure property so as to hold it for the satisfaction of any lien that be against it. In the event the lien claimant fails to bring an action within the time provided for and limited herein, the said reserve fund shall be discharged from the lien of said claimant and the moneys so held shall be forthwith paid to the contractor: Provided, however, That the limitation of four (4) months provided for herein shall not be construed as a limitation upon the right to sue the contractor or his surety where no' right of foreclosure against said fund is sought.” Bern. Comp. Stat., § 10322.

Pursuant to the provisions of §§ 1159-1161, Bern. Comp. Stat., the contractors furnished a bond, with appellant as surety. The bond was accepted by the city. So far as material, § 1159, Bern. Comp. Stat., reads as follows:

“Whenever, any . . . council, . . . acting for the . . . municipality . . . shall contract with any person ... to do any work for the . . . municipality . . . such . . . council . . . shall require the person or persons with whom *569 such contract is made to make, execute and deliver to such . . . council ... a good and sufficient bond . . . with a surety company as surety, conditioned that such person or persons shall faithfully perform all the provisions of such contract and pay all laborers, mechanics and subcontractors and material-men, and all persons who shall supply such person or persons, or subcontractors, with provisions and supplies for the carrying on of such work, which bond shall be filed . . . with the clerk (of the city) . . . and any person or persons performing such services or furnishing material to any subcontractor shall have the same right under the provisions of such bond as if such work, services or material was furnished to the original contractor: . . .”

Section 1160, Rem. Comp. Stat., provides that, if the council of such city fails to take such bond, the city shall be liable to the persons mentioned in section 1159 “to the full extent and for the full amount of all such debts so contracted by such contractor.”

The manner and time in which claimants must file claims against the bond taken from a contractor, are prescribed by § 1161, Rem. Comp. Stat., as follows:

“All such persons mentioned in . . . §1159 shall have a right of action ,. . . on such bond for work done by such laborers or mechanics, and for materials furnished ... in the prosecution of such work, . . . Provided, That such persons shall not have any right of action on such bond for any sum whatever, unless within thirty (30) days from and after the completion of the contract with an acceptance of the work by the affirmative action of the . . . body acting for the . . . city ... or person claiming to have supplied materials, . . . for the prosecution of such work, . . . shall present to and file with such . . . body acting for the . . . city ... a notice in writing . . . claim . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foremost-McKesson Systems Division of Foremost-McKesson, Inc. v. Nevis
505 P.2d 1284 (Court of Appeals of Washington, 1973)
Inland-Ryerson Construction Products Co. v. Brazier Construction Co.
500 P.2d 1015 (Court of Appeals of Washington, 1972)
Diamond Parking, Inc. v. City of Seattle
479 P.2d 47 (Washington Supreme Court, 1971)
Guthrie Investments, Inc. v. Bennett
388 P.2d 955 (Washington Supreme Court, 1964)
Fidelity & Deposit Co. v. Herbert H. Conway, Inc.
128 P.2d 764 (Washington Supreme Court, 1942)
Hochevar v. Maryland Casualty Co.
114 F.2d 948 (Sixth Circuit, 1940)
Stover v. Winston Bros. Co.
55 P.2d 821 (Washington Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
295 P. 934, 160 Wash. 565, 1931 Wash. LEXIS 930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-city-of-montesano-wash-1931.