Aetna Casualty & Surety Co. v. Skagit County

207 P. 237, 120 Wash. 351, 1922 Wash. LEXIS 906
CourtWashington Supreme Court
DecidedJune 1, 1922
DocketNo. 16930
StatusPublished
Cited by4 cases

This text of 207 P. 237 (Aetna Casualty & Surety Co. v. Skagit County) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Casualty & Surety Co. v. Skagit County, 207 P. 237, 120 Wash. 351, 1922 Wash. LEXIS 906 (Wash. 1922).

Opinion

Main, J.

— The plaintiff brought this action to recover damages against the defendant county because it had paid out money on a road contract which the plaintiff claimed was to its prejudice. There are other defendants, but the principal controversy was between the plaintiff and the county. The trial resulted in a judgment adverse to the contention of the plaintiff, and it appeals.

The facts necessary to present the questions for determination may be summarized as follows: On August 27,1917, the respondent, Skagit county, entered into a contract with T. L. Grant and L. P. Ervig, copartners under the firm name of Grant and Ervig, for the construction of a certain road in that county known as the Cook road. The contract price was approximately $60,000. The contract provided that, upon the request of the contractor, partial payments should -be made as set forth therein each month, which payments were not to exceed eighty per cent of the estimated value of the work done, which estimate was to [353]*353be made by the county engineer. Final payment was due under the contract within thirty days from completion of the work and when the same was evidenced by a certificate from the engineer for the county. The contract further provided “that before making such final payment the contractor shall show to the satisfaction of said Skagit county that all just debts due for labor performed or material furnished the said contractor have been paid.” As the work progressed, from time to time payments were made upon the estimate of the engineer, and on September 8, 1919, at the time of the final acceptance, there remained in the possession of the county approximately twenty per cent of the amount earned by the contractors under the contract. "While the work was in progress, two claims were filed against the contractors and against the bond, one of the Mt. Baker Contracting Company for $1,750.72, and one by J. H. Burmaster for $208.50. After the acceptance of the work and before the expiration of thirty days, or on October 7, 1919, another claim was filed in the sum of $5,976.55. On September 15, 1919, and before the thirty-day period specified in the contract, the county paid out of the money it then had to C. E. Bingham and Company, a banking-institution, othe sum of $9,000, leaving a balance of only $1,105.11 for the payment of claims.

The appellant was surety for the faithful performance of the contract. Thereafter the appellant brought this action, claiming that the county had wrongfully paid out the $9,000 and sought recovery against it to the extent to which it would be liable upon its bond for the claims filed. ■ The claimants were parties to the action and the claims of the Seiffert Company and the Mt. Baker Contracting Company were adjudged to be valid. The court apportioned the balance in the [354]*354possession of the county to these claims and entered judgment against the surety for the balance.

The first question is whether a payment of the $9,000 to the hank, which was an assignee of the contractors, was with the knowledge and consent of the appellant; A careful examination of the record discloses that there is no evidence from which it can be found that such payment was made with the knowledge or consent of the surety company. The representative of the surety company who had charge of the matter of issuing the bond and who at one time visited the county for the purpose of looking over the situation expressly denied any knowledge or consent. There was no affirmative evidence from which such knowledge or consent could be inferred. It is true that the representative of the company testified that, when he visited the county, he called at the hank and had a conversation with one of the officers with reference to the contract. This was while the work was in progress, and the conversation was only to the effect that the representative of the company thought that the hank, after having advanced some money to the contractors, should in fairness to them make further advance, for the reason that the hank having undertaken to finance the contractors, it was too late for them to call upon any other bank for that purpose. The officer of the hank with whom the conversation took place had no memory of the conversation or of the person with whom he talked. . This evidence has no tendency whatever to show that the $9,000 was subsequently paid out to the hank with the knowledge or consent of the appellant.

The next question is, assuming that the money borrowed from the hank went into labor and material for the contract, whether the bonding company is in a position to question the payment, since upon the bond it would have been liable for such labor and material [355]*355if they had not been paid for ont of money borrowed by the contractors from the bank. In this connection the respondent cites the case of Puget Sound State Bank v. Gallucci, 82 Wash. 445, 144 Pac. 698, Ann. Cas. 1916A 767. In that case a bank was permitted to recover from the bonding company money which it had advanced upon a contract and which money had been used by the contractors for labor and material. The decision was rested upon the provisions of the contract then under consideration. The case was decided on December 11, 1914. At the subsequent session of the legislature (Laws of 1915, eh. 28, p. 61, § 1), § 1159 of Remington’s Code (P. C. §9724), was amended, in which it was provided:

“That the provisions of this act shall not apply to any money loaned or advanced to any such contractor,D subcontractor, or other person in the performance of any such work.” Rem. Comp. Stat., §1159.

By this amendment the legislature, in effect, abrogated the rule of the Gallucci case. The bank that drew the $9,000 as assignee of the contractors had no claim which it could enforce against the surety company for the moneys which it had loaned or advanced to the contractors. The twenty per cent which was to be held for thirty days was a trust fund for the benefit of creditors and collectible claims, and was also a fund to which the bonding company had a right to look for indemnity. In Denham v. Pioneer Sand & Gravel Co., 104 Wash. 357, 176 Pac. 333, it was said:

“The fact that this twenty per cent is also, and, it may be, principally was, held for the benefit of the laborers and materialmen furnishing work and material for public work, as we have held in the following cases: State ex rel. Bartelt v. Liebes, 19 Wash. 589, 54 Pac. 26; First National Bank v. Seattle, 71 Wash. 122, 127 Pac. 837; Maryland Casualty Co. v. Washington National Bank, 92 Wash. 497, 159 Pac. 689; North[356]*356western National Bank of Bellingham v. Guardian Casualty & Guaranty Co., 93 Wash. 635, 161 Pac. 473, yet this fund is a trust fund for creditors and for collectible claims, and is also the bondsmen’s security, as indicated.”

The county, in paying out the $9,000 to the bank within the thirty days fixed by the contract, failed in the performance of its duty, to the prejudice of the rights of the appellant, and for this the county is liable. Maryland Casualty Co. v. Washington Nat. Bank, 92 Wash. 497, 159 Pac. 689. The appellant is entitled to a judgment against the county to the extent to which it has been required to pay valid claims which would have been paid out of the twenty per cent reserve fund had the $9,000 warrant not been given to the bank-, •unless the county should prevail upon the next question to be discussed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
Building Materials, Inc. v. Electric Equipment & Engineering Co.
7 P.2d 601 (Washington Supreme Court, 1932)
United States Fidelity & Guaranty Co. v. City of Montesano
295 P. 934 (Washington Supreme Court, 1931)
Stubbs Electric Co. v. Longview School District No. 112
279 P. 86 (Washington Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
207 P. 237, 120 Wash. 351, 1922 Wash. LEXIS 906, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-casualty-surety-co-v-skagit-county-wash-1922.