State ex rel. Bartelt v. Liebes

54 P. 26, 19 Wash. 589, 1898 Wash. LEXIS 429
CourtWashington Supreme Court
DecidedJuly 6, 1898
DocketNo. 2952
StatusPublished
Cited by25 cases

This text of 54 P. 26 (State ex rel. Bartelt v. Liebes) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Bartelt v. Liebes, 54 P. 26, 19 Wash. 589, 1898 Wash. LEXIS 429 (Wash. 1898).

Opinion

The opinion of the court was delivered by

Gordon, J.

On the 20th of March, 1897, the city of Spokane entered into a written contract with George J. Loy for the construction of a certain sewer (which had theretofore been authorized by ordinance), the price to be paid said contractor therefor being, $3,972, in special sewer improvement bonds, which were to be issued and delivered when the contract was completed. The contract provided that the work should be performed and the materials furnished under the provision, direction and control, and to [590]*590the complete satisfaction, of the city engineer, and to he approved by the hoard of public works, and also contained the following provision:

“ It is further mutually agreed and understood that no payment shall he made by the city to the contractor, George J. Loy, until said sewer shall have been completed, and all labor paid thereon. . . . And should any claims be filed with the comptroller by the employees of the contractor, or by the material men, before the final settlement has been had, the same shall be adjusted and satisfied before any bonds herein provided for shall he issued to said contractor.”

Said contract also contained a provision making it “ subject to all the conditions and requirements of ordinance A 203, being an ordinance relating to contracts for public works, passed May 2, 1892, and as amended.” Section 16 of ordinance A 203, referred to in this contract, provides:

“ Whenever the hoard of public works shall notify the contractor by notice personally served, or by leaving a copy thereof at the contractor’s last place of abode, that no further vouchers or estimates will be issued or payments made on the contract until the workmen and employees have been paid, and the contractor shall neglect or refuse for the space of ten days after such notice shall have been served to pay such workmen or employees, it shall and may he lawful for the city to apply any money due, or that may become due under the contract, to the payment of said workmen and employees without other or further notice to said contractor; . . .”

The contractor completed the work, and the sewer was accepted and approved by the city. The relator, Bartelt, is the assignee of the contractor of the first $2,000 of said bonds to he issued under the city’s contract to Loy; and in the instrument of assignment it was agreed that the bonds might be issued to the relator, instead of to the [591]*591contractor. The respondent Liehes is comptroller, and respondent Olmsted mayor, of the city. During the construction of the work the contractor incurred labor debts to the amount of $3,000, and an indebtedness for materials furnished and used in the construction of the sewer to the amount of $800, none of which indebtedness, either for labor or material, was paid. Written claims therefor were filed prior to August 1,1897, in the office of the city comptroller. Authority to issue the bonds was conferred on November 15, 1897, by ordinance, and thereafter the relator duly demanded of the respondents that they issue and deliver to him $2,000 of said bonds. This demand being refused, he instituted a proceeding in the superior court for the purpose of compelling the officers of the city to issue and deliver the same. In response to the alternative writ, defendants appeared and set up as a reason why they refused to issue the bonds the provisions in the contract between the city and Loy hereinbefore referred to; also, the facts in regard to Loy’s incurring the indebtedness for which claims had been filed with the city’s comptroller. After the alternative writ was issued, and before judgment, all of the appellants, except relator, obtained permission of the lower court to intervene. Their complaints set up that the several intervenors had performed work or furnished material for the contractor, Loy, in the construction of the sewer, for which labor and materials they had not been paid, and that, in conformity with the provisions of ordinance A 203, already referred to, they had filed their claims with the comptroller. They also set up that the contractor was insolvent, and asked that the city should be required to deliver to them, out of the bonds which the city had contracted to deliver to Loy, an amount sufficient to pay their respective claims. After motions to strike portions of these complaints in intervention had [592]*592been denied, and demurrers thereto overruled, the cause was set down for trial; and, at the trial, objections by the respondent city and the relator to the introduction of any evidence on behalf of the intervenors, upon the ground that their respective complaints failed to state facts sufficient to entitle them to intervene, or to any relief, were sustained, and they were dismissed from the proceeding. The trial between the relator and the city resulted in a judgment in the latter’s favor; and it was adjudged that the relator was not entitled to any relief and his proceeding was dismissed. Both the relator and the intervenors have appealed. It will thus be seen that the contest is a three-cornered one, and that the appeals of the relator and the intervenors are hostile to each other.

It is the contention of the relator that the provision in the contract between Loy and the city, providing that the bonds should not be issued until the contractor had paid for all labor and material, was ultra vires, and that no privity of contract existed between the intervenors and the city. His position is that there was not at the time of the execution of the contract any provision of statute, or of the charter of the city, which conferred upon the board of public works, or the city, authority to- insert in the contract the provision in reference to withholding payment from the contractor until the laborers and material men had been paid, and that for the same reason the provisions of the ordinance in relation to the same subject were also void. In support of this position counsel cite Clough v. Spokane, 7 Wash. 279 (34 Pac. 934), and Sears v. Williams, 9 Wash. 428 (37 Pac. 665). The first of these cases simply decided that § 2415 of the General Statutes (Bal. Code, § 5925) did not apply to street grading contracts, and that the city was not liable to laborers and material men for a failure to exact a bond contemplated [593]*593by tbat section. In Sears v. Williams, supra, tbe city of Anacortes bad taken a bond conditioned as required by § 2415; and tbe action was against tbe sureties on tbe bond, to recover tbe value of materials furnisbed. Tbe court, while conceding tbat tbe bond could be enforced in favor of tbe obligee — tbe city — held tbat it could not be enforced by tbe plaintiff, wbo at tbe time of its execution was not a party thereto, nor in any manner interested in tbe subject matter thereof. Tbe decision in each of these eases received tbe sanction of a bare majority of tbe court, as then consituted, two of tbe judges expressly dissenting. Tbe writer of tbe present opinion is constrained to say tbat be fully endorses tbe views expressed in tbe dissenting opinion in Sears v. Williams, supra, and believes tbat tbe doctrine announced by tbe majority is opposed to. reason and tbe great weight of authority. Baker v. Bryan, 64 Iowa, 561 (21 N. W. 83); Sample v. Hale, 34 Neb. 220 (51 N. W. 837); Lyman v. City of Lincoln, 38 Neb. 794 (57 N. W. 531); State ex rel. Palmer v. Webster, 20 Mont. 219 (50 Pac. 558); Knapp v. Swaney, 56 Mich. 345 (23 N. W. 162, 56 Am. Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. McCollum
136 P.2d 165 (Washington Supreme Court, 1943)
Building Materials, Inc. v. Electric Equipment & Engineering Co.
7 P.2d 601 (Washington Supreme Court, 1932)
United States Fidelity & Guaranty Co. v. City of Montesano
295 P. 934 (Washington Supreme Court, 1931)
Fidelity Deposit Co. of Baltimore, Md. v. Rainer
125 So. 55 (Supreme Court of Alabama, 1929)
Preston v. Frank Forrestal Co.
272 P. 975 (Washington Supreme Court, 1928)
Canton Exchange Bank v. Yazoo County
109 So. 1 (Mississippi Supreme Court, 1926)
Pacific Coast Steel Co. v. Old National Bank
235 P. 947 (Washington Supreme Court, 1925)
United States Fidelity & Guaranty Co. v. Ryan
214 P. 433 (Washington Supreme Court, 1923)
Aetna Casualty & Surety Co. v. Skagit County
207 P. 237 (Washington Supreme Court, 1922)
Smith v. Town of Tukwila
203 P. 369 (Washington Supreme Court, 1922)
Beyer v. Zindorf
198 P. 977 (Washington Supreme Court, 1921)
Denham v. Pioneer Sand & Gravel Co.
176 P. 333 (Washington Supreme Court, 1918)
Northwestern National Bank v. Guardian Casualty & Guaranty Co.
161 P. 473 (Washington Supreme Court, 1916)
Maryland Casualty Co. v. Washington National Bank
159 P. 689 (Washington Supreme Court, 1916)
Du Pont De Nemours Powder Co. v. National Surety Co.
155 P. 1050 (Washington Supreme Court, 1916)
United States Fidelity & Guaranty Co. v. Star Brick Co.
1915 OK 1038 (Supreme Court of Oklahoma, 1915)
Rust v. United States Fidelity & Guaranty Co.
151 P. 248 (Washington Supreme Court, 1915)
Southern Surety Co. v. Waits
1915 OK 77 (Supreme Court of Oklahoma, 1915)
Dolese Bros. Co. v. Chaney Rickard
1915 OK 611 (Supreme Court of Oklahoma, 1914)
First National Bank v. City of Seattle
127 P. 837 (Washington Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
54 P. 26, 19 Wash. 589, 1898 Wash. LEXIS 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-bartelt-v-liebes-wash-1898.