Lyman v. City of Lincoln

57 N.W. 531, 38 Neb. 794, 1894 Neb. LEXIS 582
CourtNebraska Supreme Court
DecidedJanuary 4, 1894
DocketNo. 5230
StatusPublished
Cited by56 cases

This text of 57 N.W. 531 (Lyman v. City of Lincoln) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyman v. City of Lincoln, 57 N.W. 531, 38 Neb. 794, 1894 Neb. LEXIS 582 (Neb. 1894).

Opinion

Ragan, C.

Charles W. Lyman brought suit in the district court of Lancaster county against the city of Lincoln, Layne & Sweet, copartners, Joseph C. McBride, and J. H. McMurtry, and in his petition alleged : That on June 5, 1889, the city of Lincoln entered into a contract with Layne & • Sweet, by the terms of which they agreed to furnish material and labor and construct for said city two buildings for the use of its fire department. The buildings were to be accord- . ing to certain plans and specifications, made part of the contract; to be completed, one July 15 and the other August 1, 1889; the city was to pay for them $5,968; payments to be made on monthly estimates of completed work furnished by the city’s engineer; such payments to be eighty per cent of the estimate, and the remainder of the contract price to be paid when the buildings were completed and accepted by the city; that it was also provided in said contract as follows: “ The contractors shall file with the board of public works receipts of claims from all parties furnishing materials and labor in the construction of such engine houses before the final estimate is paid and the work accepted from the hands ofi the contractors.” That on the date of the execution of said contract said Layne & Sweet, as principals, and McBride and McMurtry, as sureties, in consideration of said contract between said city and said Layne & Sweet, made and delivered to said city a bond in words and figures as follows: “ That the above mentioned John Layne and Charles A. Sweet shall well and truly execute all and singular the foregoing stipulations by them to be executed, or on default thereof we, jointly and severally, [798]*798bind ourselves * * to pay the city of Lincoln all damages which may result from such default,” etc. That the-plaintiff furnished Layne & Sweet lumber and material used by them in the construction of said buildings for said city'of the value of $2,155.58, $500 of which had been paid,, leaving a balance due him on said account of $1,655.58 ;. that Layne & Sweet entered upon the construction of said buildings, the city afterwards waiving their completion at the time fixed therefor in said contract, and were prosecuting their construction with reasonable diligence and in all respects according to the contract, when the city of Lincoln,, on September 6, 1889, wrongfully refused to permit Layne- & Sweet to further prosecute the work, canceled said contract, took possession of the unfinished buildings, completed them, and appropriated to its (the city’s) use the labor and materials performed and furnished by Layne & Sweet in the partial construction of said buildings, which labor and materials were of the value of $4,000; that the city had previously paid Layne & Sweet on said contract $2,400, and no more;. that plaintiff was the owner by assignment from Layne & Sweet of their cause of action against the city of Lincoln arising out of this contract. Layne & Sweet made no appearance. McBride and McMurtry submitted to the petition a demurrer, on the grounds that the petition did not state facts sufficient to constitute a cause of action against them.. The answer of the city, outside of the admission of the execution of the contract and bond, and the cancellation by the city of the contract, consisted of a, general denial and an affirmative averment that the city had expended a larger sum in the building of said buildings, according to Layne & Sweet’s contract, than they were to receive for their construction, and that Layne & Sweet were indebted to the city. The court sustained the demurrer of McBride and McMurtry and dismissed Lyman’s suit as to them. Judgment was rendered by default against Layne & Sweet in> favor of Lyman, and on the final hearing the court, sitting-[799]*799without a jury, found the issues for and rendered a judgment in favor of the city of Lincoln, and Lyman brings the case here on error.

There are three points which we notice:

1. Did the court err in sustaining the demurrer of McBride and McMurtry ? It is to be observed that there are in this petition three causes of action, though not separately stated: (a) Lyman sues Layne & Sweet on an account for lumber sold and delivered to them; (b) Lyman sues Layne & Sweet, as principals, and McBride and McMurtry, as sureties, on the bond they gave to the city of Lincoln for the faithful performance by Layne & Sweet of their contract with the city; and (c) Lyman, as assignee of Layne & Sweet, sues the city for the reasonable worth of the labor performed and material furnished and used by them in the partial construction of the buildings they undertook to. build for the city under the contract, and which contract, it is alleged, the city wrongfully canceled. The clause, “The contractors shall file with the board of public works receipts of claims from all parties furnishing them with material and labor in the construction of such engine houses,” found in the contract between the city and Layne & Sweet, liberally and fairly construed, means that Layne & Sweet promised the city that they would make payment to those who furnished them material or labor on said buildings • and the sureties in their bond guarantied that Layne & Sweet would perform this promise. The averment of Lyman in his petition, that Layne & Sweet still owed him a balance of $1,655.58 for lumber which he had furnished them to use in said buildings, under their contract with the city, was a sufficient allegation of a breach by Layne & Sweet of their contract and bond. Counsel for the sureties contend that the waiver by the city of the time for the completion of said buildings by Layne & Sweet released the sureties. That might be correct, were this a suit by the city against the sureties for a failure on the part of Layne [800]*800& Sweet to complete their work in the time fixed by the contract; but this waiver cannot be urged here against Lyman. A second contention of counsel for the sureties is : “ The sum total of obligation of the sureties here is to pay the city of Lincoln the damages it may sustain by reason of Layne & Sweet’s not filing receipts,” etc. If this contention is correct, the clause referred to in the contract is meaningless. The city of Lincoln could suffer no damages by the failure of Layne & Sweet to pay for the labor or material used in the construction of these buildings; and no lien for such labor or materials could be asserted against such buildings. (Ripley v. Gage County, 3 Neb., 397.) But, the nature of the contract and bond considered, counsel’s contention is too narrow a construction. Obviously, the city of Lincoln intended by this bond to protect from defaults of its contractors all those who might labor on or furnish material for its buildings. The petition assailed sets‘out no statute or ordinance authorizing the city of Lincoln to do this, but we do not deem such a statute or ordinance indispensable. The awarding of the contract to Layne & Sweet was a sufficient consideration to them and their sureties to support their promise to pay for this labor and material. The promise they made to the city of Lincoln was for the benefit of all who labored on these buildings and all who furnished material that was used in their construction; and since Lyman had furnished material to these contractors which was used in these buildings for the city, the bond inured to his benefit and he can maintain a suit thereon. (Shamp v. Meyer, 20 Neb., 223; Cooper v. Foss, 15 Neb., 515; Stewart v. Snelling, 15 Neb., 502;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peter Kiewit Sons' Co. v. National Casualty Co.
8 N.W.2d 192 (Nebraska Supreme Court, 1943)
Fremont Foundry & Machine Co. v. Saunders County
285 N.W. 115 (Nebraska Supreme Court, 1939)
Foster v. Kerr & Houston, Inc.
179 A. 297 (Supreme Judicial Court of Maine, 1935)
Fowler v. Doran
241 N.W. 759 (Nebraska Supreme Court, 1932)
William S. Van Clief & Sons, Inc. v. City of New York
141 Misc. 216 (New York Supreme Court, 1931)
E. Nelson Mfg. & Lumber Co. v. Roddy
34 S.W.2d 624 (Court of Appeals of Texas, 1930)
American Surety Co. v. School District No. 64
219 N.W. 583 (Nebraska Supreme Court, 1928)
Gary Hay Grain Co., Inc. v. Carlson
255 P. 722 (Montana Supreme Court, 1927)
Southwestern Portland Cement Co. v. Williams
251 P. 380 (New Mexico Supreme Court, 1926)
National Surety Co. v. Brown-Graves Co.
7 F.2d 91 (Sixth Circuit, 1925)
Myers v. Guernsey
197 N.W. 432 (Nebraska Supreme Court, 1924)
Clatsop County ex rel. Hildebrand v. Feldschau
199 P. 953 (Oregon Supreme Court, 1921)
Trinity Portland Cement Co. v. Lion Bonding & Surety Co.
229 S.W. 483 (Texas Commission of Appeals, 1921)
Royal Indemnity Co. v. Northern Ohio Granite & Stone Co.
100 Ohio St. (N.S.) 373 (Ohio Supreme Court, 1919)
Forburger Stone Co. v. Lion Bonding & Surety Co.
170 N.W. 897 (Nebraska Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
57 N.W. 531, 38 Neb. 794, 1894 Neb. LEXIS 582, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyman-v-city-of-lincoln-neb-1894.