Fowler v. Doran

241 N.W. 759, 123 Neb. 37, 1932 Neb. LEXIS 151
CourtNebraska Supreme Court
DecidedMarch 31, 1932
DocketNo. 28143
StatusPublished
Cited by6 cases

This text of 241 N.W. 759 (Fowler v. Doran) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fowler v. Doran, 241 N.W. 759, 123 Neb. 37, 1932 Neb. LEXIS 151 (Neb. 1932).

Opinion

Carter, District Judge.

This is an action brought by the plaintiff, John H. Fowler, against Todd A. Doran and others, alleging the existence of a mechanic’s lien and praying for the foreclosure of the same. The defendant Conservative Mortgage Company by cross-petition alleged that it was the [38]*38holder of a mortgage upon the premises involved upon which was due the sum of $4,792.65 and prayed that said mortgage be declared a first lien on the premises. The defendant Clarence P. Young by cross-petition on behalf of himself and the North Side Planing Mill alleged that the defendant Doran and one Ernest L. Lowell entered into a contract for the construction of a dwelling-house on said premises, and that the faithful performance of said contract by Lowell in the furnishing of materials and the payment of the same was secured by a bond executed by the defendant National Surety Company; that said Young and the North Side Planing Mill upon the order of Lowell, the contractor, and in reliance upon the bond, manufactured certain millwork of the value of $1,695. ■On September 2, 1930, the contractor, Lowell, notified the owner, Doran, of his intention to rescind said contract. At the date of the rescission, millwork of the value of $346 had been delivered by the North Side Planing Mill, which, however, contended that the millwork was a special order, made especially for this job, and claimed that it was entitled to the full purchase price from the contractor and the National Surety Company, his bondsman. On the 19th day of August, 1930, the defendant Conservative Mortgage Company accepted in writing the order for the millwork and agreed to pay the sum of $1,695 on delivery. The trial court found generally for the North Side Planing Mill, and rendered a decree against the National Surety Company for $1,695, with interest, and an attorney’s fee of $250; and a decree in the same amount, in favor of the North Side Planing Mill against the Conservative Mortgage Company. The court further found that the Conservative Mortgage Company accepted the order and agreed to pay the North Side Planing Mill said sum. The court further decreed that upon the payment of said sum by the Conservative Mortgage Company to the North Side Planing Mill the Conservative Mortgage Company was entitled to enforce the payment, of said amount against the National Surety Company to recoup itself. A foreclosure of the mechanic’s lien held [39]*39by the North Side Planing Mill and of the mortgage of the Conservative Mortgage Company was decreed. All other parties holding claims or liens were paid off prior to the trial and their actions were dismissed. From the above decree, the National Surety Company prosecutes this appeal.

The evidence discloses that on January 9, 1930, one Lowell, a contractor, entered into an agreement with Todd A. Doran for the erection of a house to be built on the property involved herein. At or about the' same time Lowell delivered to Doran a builder’s bond, executed by the National Surety Company, the appellant herein, which provided, among other things: “The condition of this obligation is such that if the principal shall faithfully perform the contract on his part, and satisfy all claims and demands, incurred for the same, and shall fully indemnify and save harmless the owner from all costs and damage which he may suffer by reason of failure so to do, and shall fully reimburse and repay the owner all outlay and expense which the owner may incur in making good any such default, and shall pay all persons who have contracts directly with the principal for labor or materials, then this obligation shall be null and void; otherwise it shall remain in full force and effect.” The bond further provides that the contract with the owner is to be considered as a part of the bond, it being set out in the bond as follows: “Which agreement is.by reference made a part hereof.” The building contract referred to in the bond contains, among other things, the following provisions: “The contractor shall furnish and pay for all the materials and perform and pay for all the work for the erection of three (3) residences and three (3) garages as shown on the drawings and described in the specifications,” one of the residences referred to therein being the one involved in this action. Some time prior to July 30, 1930, Lowell contracted with the North Side Planing Mill, which was owned by the defendant Clarence F. Young, for the millwork under the contract. Millwork of the value of $346 was manu[40]*40factored and delivered prior to July 30, 1930, at which time Lowell signed a written contract for all the mill-work for the agreed price of $1,695. On August 19, 1930, Maude Young, the representative of the North Side Planing Mill, demanded assurance that the millwork would be paid for upon delivery, and as a result thereof the Conservative Mortgage Company, which had taken a mortgage on the premises in the sum of $9,000, which said $9,000 was payable to the owner in instalments as the construction progressed, accepted the order by indorsing thereon the following: “Pay $1,695 whenever all millwork has been delivered. Cons. Mtg. Co. By S. J. Fieselman, V. Pres.” The testimony discloses that immediately after the acceptance of the order by the Conservative Mortgage Company, the manufacture of the millwork was commenced, and that the same was completed on September 12, 1930. It also appears from the record that on September 2, 1930, Lowell, the contractor, notified Doran, the owner, that he had rescinded the contract and that he would not complete the same. Clarence F. Young and Maude Young both testified that they or the North Side Planing Mill had no notice of the rescission until after the millwork was manufactured and ready for delivery. The National Surety Company contends that on or prior to August 14, 1930, it, through Lowell, demanded and received a sworn statement of the value of the millwork delivered at that time and that this amounted to notice of the rescission. An examination of the evidence discloses that a request was made of the North Side Planing Mill for the amount then due, but that there was nothing said that could be construed as a notice of a rescission. The testimony furnished by the National Surety Company was to the effect. that Lowell did not leave the work until about August 25, 1930, and that notice thereof was not given to Doran, the owner, until September 2, 1930. It cannot therefore be said that the North Side Planing Mill had or could have had notice by virtue of any transactions prior to August 25, 1930. After the millwork was completed, attempts were made [41]*41by the North Side Planing Mill to deliver it, but because of the fact that there was no suitable place on the premises to protect it from the weather, and damage from other causes, it was held .by the North Side Planing Mill subject to order. On October 17, 1930, Albert S. Johnston, the attorney for the North Side Planing Mill, interviewed John H. Fowler, president of the Conservative Mortgage Company and informed him that the millwork was ready for delivery. The result of this conversation was that it was mutually agreed that the millwork should be retained at the mill, rather than have it delivered at the premises, and that the rights of the parties should not be affected thereby. The evidence further discloses that on October 17, 1930, Albert S. Johnston informed C. F. Reavis, attorney for the National Surety Company, that' the millwork was completed and was ready for delivery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dworak v. Michals
320 N.W.2d 485 (Nebraska Supreme Court, 1982)
Barber v. Barber
296 N.W.2d 463 (Nebraska Supreme Court, 1980)
Dealers Electrical Supply v. United States Fidelity & Guaranty Co.
258 N.W.2d 131 (Nebraska Supreme Court, 1977)
Lundt v. PARSONS CONSTRUCTION COMPANY
150 N.W.2d 108 (Nebraska Supreme Court, 1967)
La Salle Iron Works, Inc. v. Largen
410 S.W.2d 87 (Supreme Court of Missouri, 1966)
Luikart v. Massachusetts Bonding & Insurance
263 N.W. 124 (Nebraska Supreme Court, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.W. 759, 123 Neb. 37, 1932 Neb. LEXIS 151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fowler-v-doran-neb-1932.