Harrison, J.

The petition in this action stated that on the 29th day of June, 1889, Symonds & Blake were awarded and entered into a contract with the state to furnish materials for and perform certain labor upon and about the industrial home at Milford, and executed and delivered to the state a bond for the faithful and full performance of the contract, J. W. Foster and M. J. Kaufmann signing such bond as sureties; that the bond contained the following conditions: “The condition of the above obligation is such that the above bounden Symonds & Blake have been awarded the contract to furnish all the materials and labor and skill necessary to the purpose, and to erect, construct, and fully complete, in a good and workmanlike manner, for the use of the industrial home at Milford, Nebraska, the steam heating, gas fitting, plumbing, ventilation, sewerage, windmill, well, and three cisterns, all to be in strict conformity to tiie plans, specifications, and detailed drawings now on file in the office of the commissioner of public lands and buildings at Lincoln, Nebraska, and to pay off, in full, all claims that may become due for laborers’ and mechanics’ wages or for materials furnished in or about said contract. Now if the above bounden Symonds & Blake shall well and truly keep and perform each and every covenant, promise, and agreement contained in said contract at the several times, and in the manner therein stated, and fully pay all claims due for laborers, mechanics, or furnishers of materials, then this obligation to be void; otherwise to be and remain in full force and virtue in law.” Copies of the contract, the bond, and an itemized statement of the account for material which the party in whose favor the action was instituted claimed to have furnished, were attached to the pleading. To the action there was but one appearance on the part of the defendants, that of Kaufmann, one- of the sureties on the bond. In his answer he denied that the [647]*647material was furnished to Symonds & Blake or by virtue of the contract with them, or that the fact that the bond existed was any inducement to the plaintiff in the action to extend the credit to the parties to whom it was given, and alleged affirmatively that if the plaintiff furnished any material it was to S. C. Blake & Co., and upon the credit of such firm, and without reference to the contract with Symonds & Blake; that the provision of the bond hereinbefore quoted was exacted wrongfully and contrary to legal right, and hence was void; that the firm of Symonds & Blake assigned its contract to S. C. Blake & Co., which was known to plaintiff, and such assignment was acquiesced in or ratified by the state; that the contract contained a provision that Symonds & Blake were to receive for furnishing the material and performance of labor as therein stated the sum of $3,039 “at the times and in the manner following: Eighty-five per cent of the monthly estimates made by the superintendent of construction, as the work progresses; and the balance to be paid when the said contract has been fully completed and tested and accepted by the board of public lands and buildings;” and that a payment was made to plaintiff without any estimate' being made by the superintendent of construction, and other and further payments were made so that in the aggregate they amounted to more than eighty-five per cent of the estimates made during the progress of the work, of all of which these plaintiffs had knowledge and approved; that of and to the doing of these things, all and singular, the answering defendant was not informed, had no knowledge, gave no consent, and his discharge as surety was thereby effected; The reply was a general denial. There was a trial and a verdict and judgment for plaintiff. The defendant Kaufmann, of the sureties on the bond, presents the ease here for review.

We will first notice the portion of the contention on behalf of the surety Kaufmann, in which it is asserted that he [648]*648was discharged from any obligations he had assumed as such surety (1) by the payment of $500 to the plaintiff without any estimate of the superintendent of construction as a basis or authority for such payment, and (2) by the payment of more than eighty-five per cent of an estimate made' of the amount due plaintiff by the superintendent of construction. It may be said in regard to the second of these points that the aggregate sum of eighty-five per cent of an estimate made by the superintendent during progress of the work, of the amount due plaintiff, and the alleged prior payment of $500, the basis of the first point mentioned, would make the payments just $500 more than the amount of the estimate; or, in other words, it is claimed that $500» were paid to plaintiff prior to any estimate made, and that, combining it with the payment made on a subsequent estimate, the whole amount of the payments was in excess of eighty-five per cent of such estimate. The promise in the bond to pay the laborers and parties furnishing material was for their benefit, and in an action thereupon by either it was enforceable, notwithstanding the act or acts of the state in making the alleged payments, which, in an action by the state against the contractor principal in the bond for a default in any of its conditions, might have precluded a recovery and have constituted a defense for the sureties on the bond, and released them from liability thereon (which we do not decide), and the sureties were not released from their obligations to either laborers or material-men whose valid claims were unpaid. (Doll v. Crume, 41 Neb., 655.) In the case cited the doctrine was applied to a state of facts which disclosed a payment on an estimate, in excess of the per cent which, according to the terms of the contract, was to be paid upon estimates, but is equally forcible where, as in the case at bar, a payment has been made unauthorized by an estimate, the reason which supports the rule being in all respects as pertinent and cogent in reference to the latter phase of the case as to the former [649]*649one, or the one as to which it was declared in the case to which we have called attention.

It is urged that the bond, in the particular condition which was made the basis of this action, was illegally required and exacted, was without warrant or authority of law; that inasmuch as the statutes governing the subject involved directed that a bond be taken, and prescribed a number of particulars to be.covered by conditions inserted therein, and did not include the subject of payment to laborers or furnishers of material, the provision in the bond which covered this particular, not coming within thé direct requirements of the statutory provisions, was illegal, unauthorized, and void, and hence not enforceable. A similar question has been presented to, considered, and determined by this court, and it has been decided that it was within the province of the proper officers of the state, upon whom it devolved to let such contract, to exact a bond containing a condition in relation, to the payment of laborers’ wages and the accounts of parties who had furnished material, and it was held that such a condition was valid and any liability arising thereunder could be enforced. (Sample v. Hale, 34 Neb., 220; Korsmeyer Plumbing & Heating Co. v. Me Clay, 43 Neb., 649.)

It is also urged that the plaintiff was not a party to the bond, and that no action could accrue or be based thereon in its behalf.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aníbal L. Arsuaga, Inc. v. La Hood Constructors, Inc.
90 P.R. 101 (Supreme Court of Puerto Rico, 1964)
Peter Kiewit Sons' Co. v. National Casualty Co.
8 N.W.2d 192 (Nebraska Supreme Court, 1943)
Alexander Thomson, Inc. v. B. Perini & Sons, Inc.
10 Conn. Super. Ct. 38 (Connecticut Superior Court, 1941)
Atkinson v. Reynolds
268 N.W. 480 (Nebraska Supreme Court, 1936)
Fowler v. Doran
241 N.W. 759 (Nebraska Supreme Court, 1932)
Danville Hotel Co. ex rel. Stevenson v. Charles Benson, Inc.
262 Ill. App. 288 (Appellate Court of Illinois, 1931)
American Surety Co. v. School District No. 64
219 N.W. 583 (Nebraska Supreme Court, 1928)
Excello Feed Milling Co. v. United States Fidelity & Guaranty Co.
111 So. 94 (Mississippi Supreme Court, 1926)
Webb v. Freng
194 N.W. 155 (Wisconsin Supreme Court, 1923)
Kimmel v. State ex rel. Anderson Banking Co.
128 N.E. 708 (Indiana Court of Appeals, 1920)
Toner v. Long
111 A. 311 (Supreme Court of New Hampshire, 1920)
United States Fidelity & Guaranty Co. v. Burton Lumber Co.
221 S.W. 699 (Court of Appeals of Texas, 1920)
Brioschi-Minuti Co. v. Elson-Williams Construction Co
172 N.W. 239 (North Dakota Supreme Court, 1919)
Forburger Stone Co. v. Lion Bonding & Surety Co.
170 N.W. 897 (Nebraska Supreme Court, 1919)
French v. Farmer
172 P. 1102 (California Supreme Court, 1918)
School District No. 45 v. Hallock
169 P. 130 (Oregon Supreme Court, 1917)
Texas Fidelity & Bonding Co. v. Rosenberg Independent School Dist.
195 S.W. 298 (Court of Appeals of Texas, 1917)
Standard Asphalt & Rubber Co. v. Texas Building Co.
99 Kan. 567 (Supreme Court of Kansas, 1917)
United States Fidelity & Guaranty Co. v. Naylor
237 F. 314 (Eighth Circuit, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.W. 796, 46 Neb. 644, 1896 Neb. LEXIS 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaufmann-v-cooper-neb-1896.