Lundt v. PARSONS CONSTRUCTION COMPANY

150 N.W.2d 108, 181 Neb. 609, 1967 Neb. LEXIS 599
CourtNebraska Supreme Court
DecidedApril 14, 1967
Docket36392
StatusPublished
Cited by18 cases

This text of 150 N.W.2d 108 (Lundt v. PARSONS CONSTRUCTION COMPANY) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lundt v. PARSONS CONSTRUCTION COMPANY, 150 N.W.2d 108, 181 Neb. 609, 1967 Neb. LEXIS 599 (Neb. 1967).

Opinion

Boslaugh, J.

This is an action for damages brought by T. H. Lundt, doing business as the T. H. Lundt Construction Company, against the Parsons Construction Company. The jury returned a verdict for the plaintiff in the amount of $43,000. The defendant’s motion for new trial was overruled and it has appealed.

*610 Commencing November 12, 1959, and pursuant to a contract with the city of Omaha, Nebraska, the plaintiff constructed a storm sewer along the north edge of Dodge Street from about Seventy-second Street west to Little Papillion Creek. On April 19, 1960, the defendant commenced construction of a sanitary sewer along the north edge of Dodge Street. From about Seventy-seventh Street to the Little Papillion Creek, the sanitary sewer was parallel to and just north of the plaintiff’s storm sewer. On that date the plaintiff’s project was complete and its request for payment had been approved by the supervising engineer, but the storm sewer had not been accepted by the city of Omaha.

During the construction of the sanitary sewer by the defendant, damage to the plaintiff’s storm sewer was observed. After the construction of the sanitary sewer had been completed, the city required the plaintiff to reconstruct that part of the storm sewer which was adjacent to the sanitary sewer constructed by the defendant. This action was brought to' recover the expense incurred by the plaintiff in the reconstruction of the storm sewer.

The petition alleged two causes of action. The first cause of action alleged that the defendant had negligently damaged the storm sewer. The second cause of action alleged that the defendant’s contract required it to protect all property along its line of construction and pay for all damage by it, and that the plaintiff was entitled to recover its damages under these provisions of the contract. The trial court submitted both causes of action to the jury. The defendant contends this was error and that the plaintiff has no right of recovery upon the theory of contract.

The defendant’s contract in this case provided that it was required to use care in excavating for the sewer and that all utilities encountered must be protected at its expense. The contract further provided: “The Contractor shall, at his own expense, protect by false work, *611 braces, shoring or other effective means, all buildings, walls, fences and other property along his line of work or affected directly by his work, against damage and shall repair or repay the injured owners for such damage. * * * The Contractor shall exercise care to protect .from injury all water pipes, existing sanitary sewer pipes, gas mains, telephone cables, electric cables, service pipes, and other fixtures which may be encountered during the progress of the work. Water and other service pipes and fixtures, if damaged, shall be repaired by the Contractor without additional compensation. * * * The Contractor shall personally check and verify utility information on plans. Protection is Contractor’s responsibility.”

The plaintiff’s theory is that he is a third-party beneficiary entitled to sue the defendant directly for the damage to the storm sewer caused during the construction of the sanitary sewer. This court has recognized the right of a materialman to sue directly on a bond guaranteeing the performance of a construction contract where the contractor has promised to pay for all materials. Fowler v. Doran, 123 Neb. 37, 241 N. W. 759. In other jurisdictions a similar rule has been applied to property owners where the contractor promises to protect existing utilities and other property and agrees to repair damage caused by the construction. Oman Constr. Co. v. Tennessee Central Ry. Co., 212 Tenn. 556, 370 S. W. 2d 563; Baker v. S. A. Healy Co., 302 Ill. App. 634, 24 N. E. 2d 228; Louisville Gas & Electric Co. v. Longley & Co., 250 Ky. 324, 62 S. W. 2d 1036; Keefer v. Lombardi, 376 Pa. 367, 102 A. 2d 695; Bator v. Ford Motor Co., 269 Mich. 648, 257 N. W. 906; La Mourea v. Rhude, 209 Minn. 53, 295 N. W. 304; Freigy v. Gargaro Co., Inc., 223 Ind. 342, 60 N. E. 2d 288; Hayunga Holding Corp. v. Rodgers & Hagerty, Inc., 82 N. Y. S. 2d 340; Coley v. Cohen, 258 App. Div. 292, 17 N. Y. S. 2d 101; New York Pneumatic Service Co. v. P. T. Cox Contracting Co., 187 App. Div. 1, 175 N. Y. S. 153. See, also, Restate *612 ment, Contracts, § 145, p. 173; 43 Am. Jur., Public Works and Contracts, § 82, p. 825; 17A C. J. S., Contracts, § 519 (7), p. 993. Although there is a division of authority on the question, we believe the better rule permits a property owner to sue the contractor directly where the contract contains a promise to protect existing property and repair damage resulting from the construction.

The defendant further contends that the evidence was not sufficient to support a finding that the damage to the storm sewer was: caused by the defendant’s construction of the sanitary sewer. In determining this question, the evidence must be considered in the light most favorable to* the plaintiff. McGerr v. Beals, 180 Neb. 767, 145 N. W. 2d 579.

The storm sewer was constructed of corrugated metal pipe 54 inches in diameter. The pipe itself was fabricated from 12-gauge metal which is approximately 1/10 of an inch in thickness. The pipe is relatively flexible, and requires lateral support from the soil or fill adjacent to it to maintain its circular shape and support the loads above it.

The sanitary sewer constructed by the defendant was located from 3 to 5 feet north of the storm sewer. The defendant excavated its trench by using a machine described as a “three-quarter yard backhoe.” This machine was supported upon crawler tracks which were positioned upon either side of the trench. The jury could find that one track of this machine operated on the newly replaced fill above the storm sewer and exerted a heavy downward pressure as the trench for the sanitary sewer was dug. The jury could also find that the lateral support along the north side of the storm sewer was removed by the excavation of the trench for the sanitary sewer.

The construction of the storm sewer was supervised by the Leo A. Daly Company. Robert K. Dickerson, an engineer and a vice president of the Daly firm, testified *613 that in his opinion the failure of the storm sewer was caused by the removal of the fill from one side of the pipe and subjecting the fill above the pipe to heavy loads from construction equipment.

The construction of the sanitary sewer was supervised by Henningson, Durham & Richardson, Inc. Paul R. Ombruni, an engineer employed by the Henningson firm, designed the sanitary sewer constructed by the defendant. Ombruni testified that it was his opinion that the failure of the storm sewer was caused by the removal of lateral support in excavating for the sanitary sewer. Ombruni also testified that he felt that the defendant did not do' a workmanlike job in protecting the storm sewer and that some other protection was necessary to protect the storm sewer during construction of the sanitary sewer.

Exhibit 29 is a copy of a letter from Henningson, Durham & Richardson, signed by Ombruni, dated June 17, 1960, and addressed to the sewer engineer of the city of Omaha. It is a five-page report concerning the damage to the storm sewer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sussex Tool & Supply, Inc. v. Mainline Sewer & Water, Inc.
605 N.W.2d 620 (Court of Appeals of Wisconsin, 1999)
Simons v. Tri-State Construction Co.
655 P.2d 703 (Court of Appeals of Washington, 1982)
Barber v. Barber
296 N.W.2d 463 (Nebraska Supreme Court, 1980)
St. Joseph Light & Power Co. v. Kaw Valley Tunneling, Inc.
589 S.W.2d 260 (Supreme Court of Missouri, 1979)
Sandberg v. Hoogensen
266 N.W.2d 745 (Nebraska Supreme Court, 1978)
El Fredo Pizza, Inc. v. Roto-Flex Oven Co.
261 N.W.2d 358 (Nebraska Supreme Court, 1978)
Hewitt v. Hutter
432 F. Supp. 795 (W.D. Virginia, 1977)
Insurance Co. of North America v. Hawkins
246 N.W.2d 878 (Nebraska Supreme Court, 1976)
K & R, INC. v. Crete Storage Corp.
231 N.W.2d 110 (Nebraska Supreme Court, 1975)
Ritzau v. WIEBE CONSTRUCTION COMPANY
214 N.W.2d 244 (Nebraska Supreme Court, 1974)
United States v. Lambert
362 F. Supp. 609 (D. Nebraska, 1973)
Becker v. Koza
53 F.R.D. 416 (D. Nebraska, 1971)
Lundt v. Insurance Company of North America
166 N.W.2d 404 (Nebraska Supreme Court, 1969)
Inland Drilling Company v. Davis Oil Company
158 N.W.2d 536 (Nebraska Supreme Court, 1968)
Mid States Engineering v. Rohde
156 N.W.2d 149 (Nebraska Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
150 N.W.2d 108, 181 Neb. 609, 1967 Neb. LEXIS 599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lundt-v-parsons-construction-company-neb-1967.