School Dist. No. 65R v. Universal Surety Co., Lincoln

135 N.W.2d 232, 178 Neb. 746, 1965 Neb. LEXIS 570
CourtNebraska Supreme Court
DecidedMay 21, 1965
Docket35880
StatusPublished
Cited by13 cases

This text of 135 N.W.2d 232 (School Dist. No. 65R v. Universal Surety Co., Lincoln) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School Dist. No. 65R v. Universal Surety Co., Lincoln, 135 N.W.2d 232, 178 Neb. 746, 1965 Neb. LEXIS 570 (Neb. 1965).

Opinion

White, C. J.

This is a suit against a surety on a builder’s bond. The juncture of a sand and gravel roof deck with the higher outside or parapet wall was defectively constructed and was not in accordance with the specifications. The wall was not high enough above the roof deck. Flashings and counter flashings were not properly installed, were too low, and were not properly covered. The stone coping on top of the wall was not properly mortared and water leaked into the wall *748 underneath the stone coping. Drain scuppers connecting to downspouts were improperly sealed and welded, and water leaked down through or inside of the wall into the interior of the building. Construction of the building took place in 1955 and 1956. Final payment on the contract was ■ made in November and December 1956 and without knowledge by the School District of these defects. The architect authorized final payment after inspection of the building. The School District discovered the defects in about March 1957 and contracted for and had the defects corrected in October or November 1959. Two layers of brick were required to build the outside wall to the proper height. Then, the coping, flashings, cant strip, and other structures were installed to properly guard against water leaking from the roof. The reasonable .cost for remedying these defects: in workmanship and for failure to build in accordance with the specifications was in the sum of $2,800. The School District recovered this amount in this action and the defendant surety company has appealed.

Liability in this case is governed by the contract between the parties. The bond itself guarantees the faithful performance of the contract and agrees to save the owner harmless from any damages by reason of the contractor’s failure to do so. By its terms, the plans, specifications, and drawings were incorporated into the surety bond contract. The specifications detailed the duties of the architect in the supervision of the building contract. The general principles of the law involved are that the surety is bound in the manner and to the extent provided in the obligation. A builder’s bond is construed most strongly against the surety and in favor of the indemnity which the obligee has reasonable grounds to expect. Brennan v. Clark, 29 Neb. 385, 45 N. W. 472; Sun Ins. Co. v. Aetna Ins. Co., 169 Neb. 94, 98 N. W. 2d 692; 50 Am. Jur., Suretyship, § 318, p. 1112.

Article 16 of the specifications provided as follows: “Neither the final certificate nor payment nor any pro *749 vision in the Contract Document shall relieve the Contractor of responsibility for negligence or faulty materials or workmanship■ within the extent and period provided by law, and upon the written notice he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom. All questions arising from this article shall be decided under Article 10 and 45.” (Emphasis supplied.)

Article 27 of the specifications provided in part as follows: “No certificate issued for payment made to the Contractor nor partial nor entire use or Occupancy of the Work by the Owner shall be an acceptance of any work or materials not in accordance with this Contract. The making and acceptance of final payment shall constitute a waiver of all claims by the Owner; otherwise than under Article 16 and 29, of these conditions or under requirements of the specifications, and of all claims' by the Contractor, except those previously made and still unsettled.” (Emphasis supplied.)

The defects were discovered by the School District 3 or 4 months after completion of the building and the final payment. A detailing of the evidence is not necessary. It conclusively establishes faulty workmanship in the installation of the flashings, negligence in the performance of the work, and an entire failure to construct the wall and roof juncture in accordance with the plans and specifications. It would therefore seem apparent, under the plain import of the surety’s obligation as set out above, that the plaintiff is entitled to recovery.

But, the defendant argues that the plaintiff made an unauthorized final payment to the contractor and that this constituted a surrender of security to the surety’s damage. The defendant further argues that under the contract it was entitled to the protection of a payment based upon an architect’s: final certificate. The contract provided that payments were to be made to the contractor and were to be based upon the submitted estimates of the contractor and approval by the architect. *750 Exhibit 18 is the contractor’s final estimate. It states: “Estimate No. 20 (Final).” It shows a final balance of $14,134.43. The record shows that a previous balance of $209,374.30 had been paid in accordance with the submitted written progress estimates. This final estimate was signed by the contractor and written thereon is an approval and the signature of the architect dated October 23, 1956. Pursuant to this written approval, the balance of the contract was paid by the plaintiff, the last payment in the amount of $50 being made on December 3, 1956. This money was paid with the understanding that certain trivial items on the contract requiring completion would be finished. None of these items are involved in this controversy. The defendant surety company’s contention that the plaintiff made an unauthorized payment under the contract cannot be sustained. The architect testified as follows: “Q. When the work on the roof and the walls, and the coping, flashing and the scuppers and drains was completed, did your inspection show the defects that we have described in the evidence here today? A. No; it was general inspection; we looked the building over, of course, for the final inspection. Q. You couldn’t by an ordinary visual inspection see these defects, could you, at that time? A. No. Q. That would be in the fall of 1956? A. That is correct. Q. Now is this final estimate, Exhibit 18, and which is called a final estimate, does that serve as a final certificate as far as an architect is concerned? * * * A. At that time we were using final estimates — approval of final estimates at the conclusion of the project. Q. That would be the custom in the business — in the construction business at that time in this community, is that right? A. In this area. Q. Use it as the final certificate? A. In this area.”

The contract did not provide for notice to the surety or approval by the surety of the final payment. Exhibit 18, in substance, complied with the requirements of the contract as to the final certificate under the evidence. *751 Failure to comply with some of the formal requirements becomes immaterial. No notice was required to the surety and the above testimony is conclusive that the architect himself intended it to be a final certificate and that final payment was authorized as the result of it. The plaintiff made the final payment after this written authorization and did not breach the contract in this respect by making an unauthorized payment. Defendant relies solely on O’Rourke v. Burke, 44 Neb. 821, 63 N. W. 17. But, in that case it was specifically held that it was shown there never was a certificate made by the architect that would justify the owner’s payments. This argument fails, however, for another more cogent reason.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Wagner v. Gilbane Bldg. Co.
757 N.W.2d 194 (Nebraska Supreme Court, 2008)
Goldberg. Marchesano. Kohlman. Inc. v. Old Republic Surety Co.
727 A.2d 858 (District of Columbia Court of Appeals, 1999)
Stultz v. Taska (In Re Maine Marine Corp.)
20 B.R. 426 (D. Maine, 1982)
Rudel v. Rudel
279 N.W.2d 651 (North Dakota Supreme Court, 1979)
Cagle, Inc. v. Sammons
254 N.W.2d 398 (Nebraska Supreme Court, 1977)
Schweitz v. Robatham
234 N.W.2d 834 (Nebraska Supreme Court, 1975)
City of Wahpeton v. Drake-Henne, Inc.
215 N.W.2d 897 (North Dakota Supreme Court, 1974)
Becker v. Koza
53 F.R.D. 416 (D. Nebraska, 1971)
Twin City Plaza, Inc. v. Central Surety & Insurance
409 F.2d 1195 (Eighth Circuit, 1969)
Lundt v. PARSONS CONSTRUCTION COMPANY
150 N.W.2d 108 (Nebraska Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.W.2d 232, 178 Neb. 746, 1965 Neb. LEXIS 570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-dist-no-65r-v-universal-surety-co-lincoln-neb-1965.