Gee v. City of Sutton

31 N.W.2d 747, 149 Neb. 603, 1948 Neb. LEXIS 62
CourtNebraska Supreme Court
DecidedApril 8, 1948
DocketNo. 32389
StatusPublished
Cited by11 cases

This text of 31 N.W.2d 747 (Gee v. City of Sutton) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gee v. City of Sutton, 31 N.W.2d 747, 149 Neb. 603, 1948 Neb. LEXIS 62 (Neb. 1948).

Opinion

Messmore, J.

This is an action at law brought by the plaintiffs to recover from the defendant city the reasonable value of street resurfacing and repairs pierformed by a partnership of which they were members under an oral agreement with the city officials. The agreement failed to comply with the statutory requirements and was an irregular contract. Jury was waived and trial had to the court. The court entered judgment in favor of the plaintiffs and against the defendant in the amount of $2,139.01, with interest thereon at six percent per annum from and after July 1, 1945. Upon the overruling of the motion for new trial, defendant appealed.

[605]*605The plaintiffs’ amended petition, insofar as it need be considered on this appeal, alleged in substance that prior to October 26, 1944, plaintiffs consulted with the officials of the city with reference to repair and resurfacing of certain streets. An agreement was reached whereby six separate blocks were to be repaired and treated with armor coat surfacing, for which the plaintiffs were to receive the sum of 30 cents per square yard. When the work was completed a settlement agreement was entered into by the parties wherein plaintiffs agreed to accept 24 cents per square yard, or a total of $2,500. Thereafter, in June 1946, plaintiffs again met and conferred with the mayor and council with reference to some holes which appeared in some of the streets surfaced by it. It was agreed that plaintiffs should repair the holes and leave a stock pile, of material for defendant’s further use in repairing and maintaining the streets. Certain repairs were made and a stock pile of material was left, accepted, and used by the defendant. By reason of a change of personnel in the city administration, and for the further reason that the agreements and proceedings with reference to the services rendered by plaintiffs were not fully or properly recorded in the minutes of the city council, the matter has not been adjudicated. Plaintiffs prayed for a judgment of $2,500 and interest, as the reasonable value of the services rendered.

The defendant, by answer, in effect denied that any agreement was entered into by and between the city and the plaintiffs, and all other elements with reference to the repair and resurfacing claimed by the plaintiffs. Defendant admitted - “That both parties are desirous of having this obligation settled and the only issue in this action is the reasonable value of said repairs and surfacing. That said matter has not heretofore been settled and paid by reason of the fact that the present Mayor and Council are all different individuals than were the officials of the city in 1945 * * * and proceed[606]*606ings were not fully or properly recorded in the minutes of the Council.” Defendant prayed for dismissal of the plaintiffs’, petition.

For convenience the appellant will be referred to as the city and the appellees will be referred to as the partnership.

The record discloses that Arthur I. Gee, one of the partners, in October 1944 contacted the mayor and some of the councilmen of the city with reference to repairing and surfacing some of the city streets. After some consultation, six city blocks were designated to be surfaced. Two members of the council testified that one or two blocks were to be surfaced as an experiment, and not six blocks; that the cost would be $250 to $300 a block, and if the work did not stand up no charge would be made; and that no payment would be required until July 1, 1945. The partnership brought its equipment, material and workmen to the city and repaired and surfaced six city blocks. The work took six days. Arthur I. Gee in his testimony denied that he made any agreement that if the work did not stand up it would not have to be paid for; and that during the progress of the job he had conversations with the mayor and different members of the council. The mayor testified that he saw the surfacing being done from time to time during the progress of the work.

It is apparent that the defendant city, by its officers, permitted the repair and surfacing of six city blocks without objection- or protest.

The trial court, on this issue, resolved the facts in favor of the partnership. We consider this appeal on .the basis-of the repair and surfacing of six city blocks.

Elmer C. Gee, a member of • the partnership and a graduate construction engineer, testified that the work was commenced on October 26, 1944. The original understanding with the city for the- surfacing was on the basis of 30 cents a square yard. The total items of cost, including profits and engineering, at 30 cents a [607]*607square yard as originally computed, made a total of $3,086. Subsequently, when the work was completed, members of the partnership met with the city council and agreed to accept $2,500 to settle the job, thereby taking off the profit. Subsequent to the completion of the surfacing, in June 1946, the partnership, after meeting with the council, ascertained some holes had developed in the surfacing. The partnership agreed to repair the same, and agreed to and did leave a stock pile of material for the city to use on the repair of the streets.

This witness further testified to items of $373.61, the amount actually expended for oil; $318.75 for gravel; and an item for labor in the amount of $302.40, which included transportation of the men to the work from Minden where they were housed due to war conditions. There was a discrepancy in the figures with reference to the labor, too trivial to be of consequence and not seriously contested by the city. An item of $496.86, with reference to technical skill, engineering and profit was eliminated by the court. We deem it unnecessary to discuss this item; it was properly eliminated as it constituted profit and is covered to some extent in the item of supervision. This witness further testified to an item of $859 for equipment rental for the time the equipment was used on the job, in the. following particulars: The cost of the equipment used, its life expectancy, and the amount per hour rental value of each item of equipment for the time used. Also, he testified to an item of $735.38, as constituting the fair and reasonable cost of supervision of the project, designated as wages, expenses and car for the superintendent, $300; wages, expenses and pickup used by'the foreman on the job, $200; and office expense in the amount of $235.38.

The city set up a chart in' its brief with reference to the items of equipment; the initial cost of equipment used; the life expectancy of equipment as given by the [608]*608partnership; the hours of use; the rental basis per hour; the total rental charged by the partnership for use; the actual cost to the partnership per hour for machinery; and the actual cost to the partnership for machinery used and repairs, including $9 for heating oil, making the total of the actual cost to the partnership, from the city’s viewpoint, for the machinery used, and repairs, $89.05.

The two items testified to by the witness Elmer C. Gee, the rental use of equipment and the supervision of the project as heretofore mentioned, are the principal items which the city attacks on this appeal. The trial court reduced the item for the rental use of the equipment from $859 to $644.25, and reduced the item of supervision from $735.38 to $500.

It is conceded that the city had the authority to enter into a contract for street improvements such as in the instant case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waldinger Corp. v. WorldCom, Inc. (In Re WorldCom, Inc.)
466 F. App'x 28 (Second Circuit, 2012)
Rath v. City of Sutton
673 N.W.2d 869 (Nebraska Supreme Court, 2004)
Lanphier v. Omaha Public Power District
417 N.W.2d 17 (Nebraska Supreme Court, 1987)
Smith v. Daub
365 N.W.2d 816 (Nebraska Supreme Court, 1985)
Barthuly v. Barthuly
223 N.W.2d 429 (Nebraska Supreme Court, 1974)
School Dist. No. 65R v. Universal Surety Co., Lincoln
135 N.W.2d 232 (Nebraska Supreme Court, 1965)
National Fire Ins. Co. of Hartford v. Evertson
60 N.W.2d 638 (Nebraska Supreme Court, 1953)
Albers v. Ziegler
37 N.W.2d 590 (Nebraska Supreme Court, 1949)
Smith v. Platte Valley Public Power & Irrigation District
36 N.W.2d 478 (Nebraska Supreme Court, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
31 N.W.2d 747, 149 Neb. 603, 1948 Neb. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gee-v-city-of-sutton-neb-1948.