Southwestern Portland Cement Co. v. Williams

251 P. 380, 32 N.M. 68
CourtNew Mexico Supreme Court
DecidedOctober 28, 1926
DocketNo. 3051.
StatusPublished
Cited by28 cases

This text of 251 P. 380 (Southwestern Portland Cement Co. v. Williams) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Portland Cement Co. v. Williams, 251 P. 380, 32 N.M. 68 (N.M. 1926).

Opinion

OPINION OE THE COURT

. WATSON, J.

This appeal is from a judgment for the Southwestern Portland Cement Company, which had furnished materials to the contractor, used in the construction of a public highway known as. federal aid project No. 82, against Southern Surety Company, surety on the contractor’s bond, and against the contractor himself; the latter not appealing. In the specifications for the work appeared the following:

"The action of the engineer, by which the, contractor is to be bound and concluded according to the terms of the contract, shall be evidenced by the final estimate, all prior estimates upon which 85 per centum payments may have been made, being merely partial estimates and subject to corrections in such final estimate. The engineer, when satisfied that the contractor shall have completed the work in accordance with the terms of his contract, shall certify the final estimate for payment. No money under this contract, or any part thereof, shall become due and payable, if the engineer so elects, until the contractor shall satisfy him that he has fully settled and paid for all materials used for all work and labor done in connection therewith, and the engineer, if he so elects, may pay any or all labor and material bills, wholly or in part, and deduct the amount paid from any monthly or final estimates. It is an essential part of this contract and bond furnished in connection therewith that the contractor is obligated to pay in full all just claims for labor, material, and supplies fu; nished for the construction and completion of this contraer.”

The contract provided that tbe specifications “are made a part of this contract and accepted as such.” The bond, after reciting the execution of the contract, was conditioned thus:

"Now, therefore, the conditions of the foregoing obligation are such that, if the said principals shall well and truly perform all obligations under said contract, a copy of which is hereto attached and made a part of this obligation, and shall indemnify and save harmless the state of New Mexico against any damage or loss for which said state may become liable'by the default of said principals, or by reason of any negligence or carelessness on the part of said principals, their agents, servants, or employes, or on account of any act or omission of said principals, their agents, or servants, in the performance of this contract, then these presents shall become void; otherwise, they shall remain in full force and effect.”

it seems plain that one of the obligations assumed by the contractor was to pay all just claims for labor, material and supplies., and that the bond was conditioned upon his doing so. Some point is made that there is no express “promise” to make such payments, either in the contract or in the bond. It is true that the matter. is not expressed in that language. The purpose of a contract is to define the rights and. obligations of the parties. It cannot be material whether the draftsman or the parties choose the form of expression, “the party of the second part promises” to do so and so, or the expression that he “is obligated” to do so and so. The signing of the contract admitted the obligation. The clause in question is not a mere recital of an obligation existing outside the contract. It created the obligation. The bond follows the form of expression used in the contract. It is to remain in full force and effect until the “obligations” of the contract shall have been well and truly performed. One of those “obligations” is to pay all just claims for labor, material, and supplies. That obligation of the contract and condition of the bond has not been performed. So, under the terms of the bond, the surety’s liability has not been discharged.

'It being plain that there has been a default in the contract, for which there is a liability on the part of the surety, it remains to determine whether the default is in respect to a duty owing to the appellee, and whether the liability of the surety therefor is to the appellee.

It was the rule at common law that suits might be had only by those who were parties to the contract, or by their successors in interest. Appellant does not, however, contend that such is the modern rule. It admits that in certain cases a third party, not named in the contract,' and from whom the consideration did not move, but for whose direct and substantial benefit the contract was made, may sue to enforce the same, or for a breach thereof. It urges, however, that this' case does not come within the modern rule.

The first and, as we conceive, the most important question, is the intent of the parties. Was the stipulation of the specifications, incorporated by reference in the contract, and thereafter in the bond, intended for the direct and substantial benefit of laborers and materialmen'? This question involves the construction of the contract, which, of course, is to be interpreted in. the light of the legal relations in which the parties stood to each other, under the circumstances in which they dealt.

It is first to be observed that no then existing statute, required the state highway commission, by bond, or otherwise, to obtain for, or afford to, laborers and materialmen any protection for, or' aid in, collecting their claims against the contractor. Laws 1923, e. 136, “relating to bonds of contractors upon public works,” was subsequently passed, and is not involved here. It is also to be observed, as, one of the circumstances surrounding the transaction, that the lien laws do not apply to public property, and that, unless the state highway commission, by sufficient contract provision, secured payment of the claims of laborers and material-men, they could look only to the contractor himself; having no recourse against the state or its property.

It is apparent, therefore, that it was entirely immaterial to the state, considered as a party contracting in a business, rather than a political, capacity, whether the contractor paid for the labor and material. The mere fact that he furnished them, and by means of them was able to construct the highway, gave to the state every advantage it sought or required so far as concerned its own property and funds. In that respect, it lost nothing if the contractor failed to pay; it gained nothing if he did pay. , Regardless of this lack of pecuniary interest, the state, acting .through the highway commission, was at pains to stipulate as “an essential part of this contract” that the contractor should pay all such claims,. It requires no argument to demonstrate that the appellee, and others similarly situated —prospective laborers and furnishers of material and supplies — would have a direct and substantial interest in such a provision. A provision so emphatically made must have been for the benefit of some one. If it could not directly benefit the state, and must directly benefit laborers and materialmen and no one else, the conclusion seems irresistible that it was incorporated in the contract for their benefit.

The event justifies the foregoing argument. The bond is still in effect, because there has been no performance of the condition of its becoming void. The obligee, the state, has suffered no damage by reason of the default which keeps the bond alive. It has no right of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Szantho v. Casa Maria of N.M., LLC
New Mexico Court of Appeals, 2025
Sims' Crane Service, Inc. v. Reliance Insurance
514 F. Supp. 1033 (S.D. Georgia, 1981)
Town & Country Bank v. James M. Canfield Contracting Co.
370 N.E.2d 630 (Appellate Court of Illinois, 1977)
Chavez v. Pino
525 P.2d 391 (New Mexico Court of Appeals, 1974)
Avco Delta Corp. Canada Ltd. v. United States
484 F.2d 692 (Second Circuit, 1973)
Employment Security Commission v. C. R. Davis Contracting Co.
462 P.2d 608 (New Mexico Supreme Court, 1969)
Berryhill v. United States Casualty Co.
418 P.2d 185 (New Mexico Supreme Court, 1966)
Engert v. Peerless Insurance Company
382 S.W.2d 541 (Court of Appeals of Tennessee, 1964)
Sproul Construction Co. v. St. Paul Fire & Marine Insurance
389 P.2d 194 (New Mexico Supreme Court, 1964)
Gibbs v. Trinity Universal Insurance Company
1958 OK 147 (Supreme Court of Oklahoma, 1958)
Permian Basin Investment Corporation v. Lloyd
312 P.2d 533 (New Mexico Supreme Court, 1957)
Hamill v. Maryland Cas. Co.
209 F.2d 338 (Tenth Circuit, 1954)
Crane O'Fallon Co. v. Via
251 P.2d 260 (New Mexico Supreme Court, 1952)
Rankin v. Ridge
201 P.2d 359 (New Mexico Supreme Court, 1948)
Fuqua v. Trego
133 P.2d 344 (New Mexico Supreme Court, 1943)
Western Steel Casting Co. v. Edland
61 P.2d 155 (Washington Supreme Court, 1936)
Foster v. Kerr & Houston, Inc.
179 A. 297 (Supreme Judicial Court of Maine, 1935)
United States Fidelity & Guaranty Co. v. Rhode Island Covering Co.
8 R.I. Dec. 330 (Superior Court of Rhode Island, 1932)
Hollerman Mfg. Co. v. Standard Accident Insurance
239 N.W. 741 (North Dakota Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
251 P. 380, 32 N.M. 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-portland-cement-co-v-williams-nm-1926.