Builders Material & Supply Co. v. J. B. Evans Construction Co.

221 S.W. 142, 204 Mo. App. 76, 1920 Mo. App. LEXIS 15
CourtMissouri Court of Appeals
DecidedApril 6, 1920
StatusPublished
Cited by7 cases

This text of 221 S.W. 142 (Builders Material & Supply Co. v. J. B. Evans Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Builders Material & Supply Co. v. J. B. Evans Construction Co., 221 S.W. 142, 204 Mo. App. 76, 1920 Mo. App. LEXIS 15 (Mo. Ct. App. 1920).

Opinion

REYNOLDS, P. J.

This is an action on a contract- or’s bond to recover the cost of certain material furnished by the appellant, plaintiff below, for a certain school building at Scranton, Iowa. The contract for the erection of the building was entered into between the Evans Construction Company of Mexico, Mo., and the independent School District of Scranton, Green County, Iowa. Its first article sets out that “the contractor (Evans Construction Company), shall and will provide all the material and perform all the work for the erection and completion (except plumbing and heating) of a two-story and basement High and Grade.School building to be erected at Scranton, Green County, Iowa, as shown on the drawings and described in the specifications and supplement prepared by Trunk & Gordon, architects, which drawings and specifications are identified by the signatures of the parties hereto, and become hereby a part of this contract. ’ ’ The concluding paragraph of the contract is that it, “is not to be binding on the part of the owner until the contractor files an approved surety bond for fifty per cent, of the contract.”

The contract price for the erection of the building was $30,990, it being stipulated that “such sum shall be paid by the owner to the contractor, in current funds,” in instalments as thereafter stated.

In the plans and specifications appears this clause:

“The contractor must furnish the owner an acceptable surety bond for the full amount of the contract •price, guaranteeing the payment for all valid claims for all labor or material furnished for the building regardless of liens.”

The Evans Construction Company is named as principal in the' bond, the Maryland Casualty Company as surety, and the Board of Education of the school district *81 as obligee, and is for tbe sum of $15,000. Tbe parts of tbe bond material to tbe consideration of this question are these:

“Whereas, the principal has entered into a written contract, dated April 12., 1915', with the obligee, for the erection and completion (except plumbing and heating), of a two-story and basement High and ¡Grade School building, to be erected a.t Scranton, Green County, Iowa, as shown on the drawings and described in the specifications and supplement prepared by Trunk & Gordon, Architects, St. Joseph, Missouri, a copy of which is hereto annexed, and which contract is made a part thereof, as fully, as if recited at length herein.
“Now, therefore, the condition of this obligation is such that, if the principal shall indemnify the obligee against any loss (W damage directly arising by reason of the failure of the principal to faithfully perform 'said contract, then the obligation shall be void; otherwise to remain in full force and effect. (Italics ours).
“It is expressly agreed that the said principal and surety will keep the said obligee harmless and indemnified from and against any and all costs, damages and expenses which it may incur or become liable for, by reason of any claim or demand that may be made against it, or against said building, or the real estate upon which the same is situated, on account of any act or thing done or omitted by the said principal in the premises; and that the principal and surety shall and will keep the said obligee harmless and indemnified from and against any and all things, liens of mechanics, laborers ’, materialmen, and subcontractors, and that they shall and will pay to said obligee all sums of money which it may be required to pay to auv other persons, on account of work or labor done, or material furnished on and for said building, and all costs and expenses incurred in relation thereto.”

In the petition upon which the cause was tried the plaintiff avers the entering into of the contract and the conditions we have set out, and avers that under and by *82 the terms of the contract “defendant J. B. Evans Construction Company agreed to furnish said School Board an acceptable surety bond for 50 per cent, of the contract price, which Board should guarantee the payment of all valid claims for all labor and material furnished for the building, regardless of lien, the purpose and intent of which bond was to protect and indemnify said School Board and all persons furnishing labor and material for the building aforesaid.” It is further averred that in consideration of the contract the Evans Construction Company, as principal, and defendant Maryland Casualty Company, as surety, “executed and delivered to the School Board their certain contract or bond for the penal sum of $15,500, for the benefit of said School Board and all persons furnishing labor and material used in said construction and erection, conditioned upon the full performance of all of the provisions and covenants in said contract and specifications contained, including the payment of all valid claims for all labor or material furnished for the building aforesaid, regardless of liens.” Averring that the Evans Construction Company entered into the erection and construction of the school building, as provided in the contract, it is averred; that between September 25 and November 29, 1915', the Evans Construction Company purchased from plaintiff certain material known as “Master Builders Hardner,” to be used for the construction of the floors in the building, at and for the reasonable price and value of $440.67, all of .which material was duly delivered to the Evans Construction Company and by it used in said construction, “as more particurlarly shown in an itemized statement'thereof hereto atr tached and marked Exhibit I), ’ and made a part hereof. ’ ’ Averring that the Evans Construction Company had kept and performed the condition of the bond, and contract but had committed a breach thereof, in failing to pay plaintiff for this material used in the building, and that the same is long past due and payable to plaintiff, although demand has been made, plaintiff pleads section 3467 of,the Iowa Code. This is contained in “Title XVIII,” Iowa Code of *83 Civil Practice, chapter 1 of which treats of preliminary provisions; chapter 2 of limitations of actions; and chapter 3, in which this section is found, treats of parties to an action and is as follows:

“When a bond or other instrument given to the State or county or other municipal or school corporation, or to any officer or person, is intended for the security of the public generally, or of particular individuals, action may be brought thereon in the name of any person intended to be thus secured, who has sustained an injury in consequence of a breach thereof, except when otherwise provided. ’ ’

The plaintiff further pleads a decision of the Supreme Court of Iowa—Hipwell v. National Surety Co., 130 Iowa, 656—and sets out that opinion m extenso, commenting on it and introducing the section of the statutes and the opinion in evidence.

The defendant J. B. Evans Construction Company, although answering by general denial, thereafter did not appear and has not appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ill-Mo Contractors, Inc. v. Aalcan Demolition & Contracting Co.
431 S.W.2d 165 (Supreme Court of Missouri, 1968)
Bourrett v. W. M. Bride Construction Co.
84 N.W.2d 4 (Supreme Court of Iowa, 1957)
Glens Falls Indemnity Co. v. American Awning & Tent Co.
180 A. 367 (Supreme Court of Rhode Island, 1935)
Hollerman Mfg. Co. v. Standard Accident Insurance
239 N.W. 741 (North Dakota Supreme Court, 1931)
Crum Et Ux. v. Jenkins
143 S.E. 21 (Supreme Court of South Carolina, 1928)
Southwestern Portland Cement Co. v. Williams
251 P. 380 (New Mexico Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
221 S.W. 142, 204 Mo. App. 76, 1920 Mo. App. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/builders-material-supply-co-v-j-b-evans-construction-co-moctapp-1920.