Royal Indemnity Co. v. Independence Indemnity Co.

29 F.2d 43, 1928 U.S. App. LEXIS 2607
CourtCourt of Appeals for the Ninth Circuit
DecidedNovember 12, 1928
DocketNo. 5580
StatusPublished
Cited by1 cases

This text of 29 F.2d 43 (Royal Indemnity Co. v. Independence Indemnity Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royal Indemnity Co. v. Independence Indemnity Co., 29 F.2d 43, 1928 U.S. App. LEXIS 2607 (9th Cir. 1928).

Opinion

DIETRICH, Circuit Judge.

Upon sustaining a demurrer to plaintiff’s complaint, the court below entered a judgment of dismissal, from which the plaintiff appeals.

From the complaint and exhibits attached thereto it appears that in districts designated as Nos. 1, 2, 3, 4, and 5, the city of Reeds-port, Or., projected certain street improve[44]*44ments, involving, among other things, the making of fills. At the same time the port of Umpqua was desirous of having deepened a section of the Umpqua river channel, and' as suitable equipment for such work it was the owner of a suction dredge, derrick, scow, and accessories. By carrying on the two improvements at the same time, the material removed in deepening the river channel could be economically utilized in making the fills. Accordingly the Inland Construction Company secured contracts from the city of Reedsport for the street improvements in the several districts, and also entered into a contract with the port of Umpqua, under the terms of which it obtained the use of the dredge and other equipment, in consideration of ,its doing certain specified work in deepening the river channel, and also making payment of a stipulated rental.

When the other contracts for the street work were made does not appear, but the one for district No. 1 bears date August 1,1925. It required a bond from the Inland Construction Company in an amount equal to 75 per cent, of the contract price, “conditioned for the faithful performance of the contract according to the plans and specifications and the original proposal.” Accordingly, on August 8, 1925, the construction company, with the defendant, Independence Indemnity Company, as-surety, furnished such bond, in the penal sum of $17,742.51, conditioned that the construction company would indemnify the obligee, city of Reedsport, against any loss or damage directly arising out of any failure on its part faithfully to perform the contract. Among other things, the bond expressly provided “that no right of action shall accrue upon or by reason hereof, to or for the use or benefit of any other than the obligee [city of Reedsport] herein named,” and further that no assignment of any interest therein or right of action thereon should be made without the prior consent, in writing, of the surety.

The contract between the port of Ump-qua and the construction company, dated August 7, 1925, after reciting that the construction company had a contract or contracts for the street work in districts Nos. 1, 2, 3, 4, and 5 in Reedsport, and was desirous of getting the fill material from the channel of Umpqua river, and that the port of Ump-qua was desirous of having the channel deepened,-and was the owner of the dredge equipment of which the construction company wanted the use, provided for the leasing of the' dredge and the deepening of the channel and stipulated the rentals to be paid.. It also required that the construction company should furnish a bond with surety in the penal sum of $15,000, conditioned upon the faithful performance by the construction company of all its obligations under the contract. Accordingly, on the same day, such a bond was given, with the Royal Indemnity Company, plaintiff herein, as surety.

Thereafter the construction company undertook the work as required by its contracts, but failed to make full payment to the port of Umpqua of the rentals for the dredge, and in the course of time the plaintiff was called upon to, and it did, pay a balance of $8,-094.08.

Upon the assumption that, under its bond to the city of Reedsport, the defendant was obligated to discharge all obligations to laborers and materialmen for work done for and material used by the construction company in the street work, and that the dredge, having been used in the execution of that contract, is in law to be deemed material or labor, plaintiff brought this action under the theory that the port of Umpqua had the right, had it seen fit so to do, to recover from the defendant the $8,094.08, and that plaintiff, having paid the amount, became subro-gated to such right.

While in point of fact the use of the dredge for which the $8,094.08 became due may in some measure have contributed to the street work covered by the contract to which defendant’s bond pertains, it is not shown what the contribution was or how the value of the use for that purpose could be determined. As already stated, under the port of Umpqua contract the dredge was to be employed in dredging the channel of the river, and the material so removed was to- be used upon the streets in the city of Reeds-port, but in five different districts, only one of which is covered by the defendant’s bond, namely, the contract herein referred to as relating to district No. 1. For this reason alone we doubt whether the complaint states a cause of action.

But, however that may be, by the very terms of its bond defendant restricted its obligation to the city of Reedsport. To supply an obligation which the bond expressly purports to preclude, plaintiff invokes sections 2991 and 6718 of Olson’s Oregon Laws, as amended by the Laws of Oregon for 1923, c. 24. Section 6718 provides that every contract made by the state or any municipal corporation shall contain a condition “that the contractor shall promptly, as due, make payment to all persons supplying to such contractor labor or material for the prosecution [45]*45of the work provided for in sueh contract” and further, that “a penal bond, with good and sufficient sureties, shall be required of each and every such contractor to secure the faithful performance of all the usual or particular obligations of sueh contract.” Section 2991 provides that any person entering into a formal contract with the state of Oregon or any municipality for the prosecution or completion of any work shall be required, before commencing sueh work, “to execute the usual penal bond with good and sufficient sureties, with the additional obligations that sueh contractor or contractors shall promptly make payments to all persons supplying him or them [with] labor or materials for any prosecution of the work provided for in sueh contracts.” This section further provides that any one who has furnished labor or material for the prosecution of sueh work for which he has not been paid, may, upon complying with certain specified conditions, secure a copy of the contractor’s contract and bond, and maintain suit upon such bond in his own right against the contractor and the surety. Then follows a proviso to which we shall presently advert.

The argument is that, whatever may be the form or language of the bond given by a contractor for the construction of a publie work, these provisions of law must be read into it, and held to impose upon the surety the obligations therein defined, even though by the terms of the bond the parties have attempted expressly to preclude them. To sustain this contention, appellant cites Multnomah County v. United States Fidelity & Guaranty Co., 92 Or. 146, 180 P. 104; Fitzgerald v. Neal, 113 Or. 103, 231 P. 645; Philip Carey Co. v. Maryland Casualty Co., 201 Iowa, 1063, 206 N. W. 808, 47 A. L. R. 495; Globe Indemnity Co. v. Barnes (Tex. Civ. App.) 281 S. W. 215; Southern Surety Co. v. Klein (Tex. Civ. App.) 278 S. W. 527; Ingold v. Hickory, 178 N. C. 614, 101 S. E. 525. This position may be conceded to be correct, if the statutory provisions evince such a legislative intent, but not otherwise. That neither the obligor nor the obligee here understood that the bond in question was given in full compliance with the Oregon statutory requirements is too plain to be open to argument.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
29 F.2d 43, 1928 U.S. App. LEXIS 2607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-indemnity-co-v-independence-indemnity-co-ca9-1928.