Board of Education ex rel. Johnson Heat Regulating Co. v. United States Fidelity & Guaranty Co.

149 S.W. 46, 166 Mo. App. 410, 1912 Mo. App. LEXIS 560
CourtMissouri Court of Appeals
DecidedJuly 2, 1912
StatusPublished
Cited by14 cases

This text of 149 S.W. 46 (Board of Education ex rel. Johnson Heat Regulating Co. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education ex rel. Johnson Heat Regulating Co. v. United States Fidelity & Guaranty Co., 149 S.W. 46, 166 Mo. App. 410, 1912 Mo. App. LEXIS 560 (Mo. Ct. App. 1912).

Opinion

REYNOLDS, P. J.

— We have in this case the same contract and bond which were before us in the case of the Board of Education ex rel. Phillip Carey Co. v. United States Fidelity & Guaranty Co., 155 Mo. App. 109, 134 S. W. 18, hereafter referred to for brevity as the Carey case. In the case at bar, as in the Carey case, a partnership composed of Kohlbry and DeLaney, doing business under the firm name of the National Engineering & Construction Co., and hereafter referred to as the original contractors, entered into a contract with the Board of Education of the city of St. Louis, “to construct, erect and build heating and ventilating plants in the Baden School” in that city. For the performance of that contract the contractors gave a bond to the board of education, the Fidelity & Guaranty Company, appellant here, defendant below, being the surety. The bond and contract were executed March 12, 1907, the -bond being given under and in accordance with sections 6761, 6762, Revised Statutes, 1899, that being the law in force at the date of the execution of it and of the contract. Among the other conditions in the bond is the condition that the principals “shall make payment to the parties furnishing the same for all materials used in the work, provided for in the said contract and specifications hereunto annexed, . . . whether by subcontract or otherwise.” The contract makes the usual provision allowing the board of education to retain from the moneys due and coming to the contractors enough to pay and satisfy the claims of artisans, laborers and all those employed by or furnishing material to the contractors, not however rendering the board of [415]*415education liable for tlie payment of wages and material in case the contractor failed to make payment. As in the Carey case, the condition covered by this provision is not here present. There is also the usual condition authorizing the commissioner of the board to have the work completed on failure of the contractors and to charge the cost therefor against them, the surety of course then being liable.

Shortly after entering into the contract and giving the bond, it appears that the partnership of Kohlbry & DeLaney was dissolved and went out of business, and a corporation called The Advance Engineering & Construction Co., was formed, originally by Kohlbry and two others and into which company De-Laney afterwards entered. Under date of the 18th of March, 1907, the relator here entered into a contract in writing with this Advance Engineering & Construction Co., to place what is called the “Johnson system of temperature regulation” in the Baden school, the installation of this heat regulating apparatus of relator being one of the three systems it was provided in the contract between the original contractors and the school board should be installed. This contract is signed in the name of the Advance Company by Kohlbry as its president. A few months after entering into this contract with the Advance Company, the Johnson Company commenced the installation of these appliances, completing the installation about the 1st of January, 1908. The work of installation of this plant was done under the inspection of the representative of the board of education and was accepted as in all respects satisfactory. The board of education, however, not recognizing the Johnson Heat Regulating Company in the matter, nor anyone but the original contractors, made payments to the original contractors, Kohlbry & DeLaney, under their firm name of National Engineering & Construction Co., the checks by which the payments were made be[416]*416ing indorsed over in the name of the National Engineering & Construction Co., by Kohlbry to the Advance Engineering & Construction Co., and turned over indorsed by Kohlbry as président of the Advance Engineering & Construction Co., to the Johnson Heat Regulating Company. The contract price for the installation of this temperature regulation system was $1875. The amount paid on account of this contract to the Johnson Heat Regulating Company totalled $967.46, leaving a balance unpaid of $907.54. It was for this amount, with interest and costs that this action was instituted in the name of the board of education at the relation and to the use of the Johnson Heat Regulating Company.

So far it will be seen by reference to the Carey case, the bond and the contract and the doing of the work by others than the original contractors, the facts in this ease and those in the Carey case are parallel, save as to names and nature of the work. Here the parallel ends. In the Carey case there was no evidence tending to show any privity of contract between the original contractors and the relator there. In the case before us, there are facts in evidence which it is claimed do make the connection.

It appears that at a meeting of the Advance Engineering & Construction Co., held on the 2nd of May, 1907, the following motion was made and carried: “That all the business of the National Engineering & Construction Company be assumed by the Advance Engineering & Construction Company.” It further appears that at that time Kohlbry was a stockholder and president of the Advance Company and that De-Laney had become a stockholder in it about that date, and that they had turned over to the Advance Company their interest in their late partnership for stock in that company. There is also evidence tending to show that at least from the time of the making of the contract between the Advance Engineering & Con[417]*417struction Company and the Johnson Heat Regulating Company before referred to, and following that contract, Kohlbry & DeLaney, the original contractors, under their firm-name of National Engineering & Construction Company had recognized the Advance Company as having taken over the performance of at least that much of the original contract as covered the installation of the Johnson system in the Baden school. Checks for payments which were made on account of the work were made in the name of the National Company and indorsed in that name by Kohlbry and turned over to the Advance Company and by it to relator. It is also in evidence that the Advance Engineering & Construction Company, shortly after the making of the contract between that company and the Johnson Heat Regulating Company had made an assignment under the statute, it being insolvent. Mr. Kohlbry testified, in subtance, that he and DeLaney were in partnership in March, 1907, under the name of National Engineering & Construction Company, under which name they had entered into the contract and given the bond; that the National Engineering & Construction Company, the partnership, was dissolved and all its business assumed by the Advance Engineering & Construction Company, a corporation. He was one of the incorporators and president of the company but did not remember the exact date of incorporation. That company entered into the contract in evidence and before referred to with the relators, he (Kohlbry) signing it as president of the company. Identifying the minute book of the company in which appeared the resolution before set out, and which was read in evidence, he was asked this: “What arangement, if any, was made between the National Company and the Advance Company with reference to the doing of the heating and ventilating work on the Baden school?” He answered, “Why, the Advance Corn[418]*418pany finally assumed the contract of the National Company, as shown by the minutes of the Advance Engineering &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Insurance v. Hercules Construction Co.
385 F.2d 13 (Eighth Circuit, 1967)
Aníbal L. Arsuaga, Inc. v. La Hood Constructors, Inc.
90 P.R. 101 (Supreme Court of Puerto Rico, 1964)
Sweetser Construction Co. v. Newman Brothers, Inc.
371 S.W.2d 515 (Supreme Court of Arkansas, 1963)
Drew's Hardware & Appliance Co. v. Willis Housing Projects, Inc.
268 S.W.2d 596 (Missouri Court of Appeals, 1954)
State Ex Rel. Lawson v. Warren Br. Roads Co.
59 N.E.2d 912 (Indiana Court of Appeals, 1945)
City of St. Louis Ex Rel. Stone Creek Brick Co. v. Kaplan-McGowan Co.
108 S.W.2d 987 (Missouri Court of Appeals, 1937)
City of St. Louis Ex Rel. Sears v. Southern Surety Co.
62 S.W.2d 432 (Supreme Court of Missouri, 1933)
City of St. Joseph Ex Rel. Consolidated Stone Co. v. Pfeiffer Stone Co.
26 S.W.2d 1018 (Missouri Court of Appeals, 1930)
Builders Material & Supply Co. v. J. B. Evans Construction Co.
221 S.W. 142 (Missouri Court of Appeals, 1920)
School District No. 45 v. Hallock
169 P. 130 (Oregon Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
149 S.W. 46, 166 Mo. App. 410, 1912 Mo. App. LEXIS 560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-ex-rel-johnson-heat-regulating-co-v-united-states-moctapp-1912.