City of St. Louis Ex Rel. Sears v. Southern Surety Co.

62 S.W.2d 432, 333 Mo. 180, 1933 Mo. LEXIS 555
CourtSupreme Court of Missouri
DecidedJune 24, 1933
StatusPublished
Cited by1 cases

This text of 62 S.W.2d 432 (City of St. Louis Ex Rel. Sears v. Southern Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of St. Louis Ex Rel. Sears v. Southern Surety Co., 62 S.W.2d 432, 333 Mo. 180, 1933 Mo. LEXIS 555 (Mo. 1933).

Opinions

* NOTE: Opinion filed at October Term, 1932, April 20, 1933; motion for rehearing filed; motion overruled at May Term, June 24, 1933. This is the second appeal in this case. The first appeal was granted to the St. Louis Court of Appeals from a judgment in defendants' favor. The Court of Appeals reversed and remanded the case for a new trial. [See City of St. Louis ex rel. v. Clark, 35 S.W.2d 986.] In the meantime the interest that accrued increased plaintiffs' claim and at the second trial plaintiffs received a judgment in the sum of $8,778. Hence the appellate jurisdiction in this court.

The suit was based on the theory that plaintiffs, as subcontractors, furnished certain labor and material for the construction of a public building. Defendant John J. Clark was the original contractor, and defendant Southern Surety Company, surety on Clark's bond. Plaintiffs' suit is on the bond for the balance due by Clark to plaintiffs. Clark entered into a contract with the city of St. Louis, Missouri, for the construction of a men's infirmary building on the grounds of Robert Koch Hospital. This is a public building, therefore, Clark was required to give a bond, as provided for by Section 1040, Revised Statutes 1919, now section 2890, Revised Statutes 1929, as amended by Laws, 1925, page 127, 1 Missouri Annotated Statutes, page 744.

By the contract here in question Clark sublet the installation of the metal door frames and partitions, as was contemplated on pages 23 to 25, inclusive, of the specifications governing the construction of the building. The specifications called for the material to be equal to that manufactured by the Jamestown Metal Door Company or the Dahlstrom Metallic Door Company. In the contract of *Page 185 subletting, entered into by Clark as the party of the first part and Sears and Piou parties of the second part, we find the following clause, which is the main subject of dispute:

"It is understood that the Party of the Second Part is acting as agent for the Dahlstrom Metallic Door Co., who will furnish the hollow metal material in accordance with their standard practice and as called for in the plans and specifications for the above named institution."

At the first trial, the lower court held that the clause quoted made the contract that of the Dahlstrom Company, and that plaintiffs could not recover for the items furnished by that company. Plaintiffs offered to introduce evidence to prove that the contract was not in fact the contract of the Dahlstrom Company and that the parties by their conduct had not so treated it. This evidence was rejected by the trial court. The St. Louis Court of Appeals held that the contract was ambiguous. It remanded the case with instructions to the trial court to admit extrinsic evidence, if any plaintiff had, to show that the contract was in fact their own.

Plaintiffs at the second trial introduced evidence that they had an exclusive contract with the Dahlstrom Company to sell their product in the city of St. Louis, and for that reason the clause was placed in the contract to insure that they could furnish material in compliance with the specifications. H.H. Piou, one of plaintiffs, when asked why the clause quoted was placed in the contract, testified as follows:

"A. Well, the specifications specifically call for material — the hollow metal material had to be manufactured by Dahlstrom or one other competitor in Jamestown. Mr. Clark, in order to be sure that he was getting material to comply with specifications, insisted on having the name Dahlstrom mentioned and also wanted to be sure the material was paid for and he had the privilege of paying direct for it if he felt like it.

"MR. GRAND (Q.): Was there any other concern in the City of St. Louis that could furnish Dahlstrom material other than Sears Piou? A. No. We had the exclusive right to sell it in St. Louis and Kansas City, and we still have.

"Q. Did you and Mr. Clark discuss that phase of the matter at all? A. Yes, we discussed that.

"Q. What was said? A. I told him we could furnish Dahlstrom material and the City liked Dahlstrom material because it was good material.

"MR. GRAND (Q.): What, if anything, did Mr. Clark say about inserting anything in the contract with reference to your agency here in St. Louis for Dahlstrom? A. Mr. Clark asked us to put the fact that we could furnish Dahlstrom material in the contract, embody it in the contract, and we put it in there." *Page 186

Plaintiffs, under their contract, also furnished materials that were obtained from other manufacturing companies. There is also a provision in the contract that the material furnished by the Dahlstrom Company should be paid for by defendant Clark, direct to that company, the balance due on the contract to be paid to plaintiffs' Sears and Piou. Clark, by his contract with plaintiffs, agreed to pay $16,000 for all of the labor and material called for in the contract. For this item, Clark, under his contract with the city, received $17,336. Plaintiffs' petition sufficiently alleged compliance by them with their contract and a breach thereof by defendants.

Plaintiffs asked judgment for the penalty of the bond in the sum of $60,471.25 to be satisfied on the payment of the balance due plaintiffs on the contract in the sum of $6,693.84, and interest at six per cent per annum from the tenth day of October, 1925. Defendant Surety Company filed an answer admitting the execution of the bond. Its defense, as pleaded in the answer, was "that plaintiffs are neither material-men, laboring-men nor mechanics, and by the terms of said bond none other can maintain any suit on said bond." Defendant Surety Company further alleged that the failure of Clark to pay a subcontractor was not a breach of the bond. Defendant Clark filed a separate answer in substance the same as that of defendant Surety Company coupled with a general denial. Defendant Clark also filed a counterclaim in two counts. In the first count Clark asked damages in the sum of $2,011.17, which he alleged was sustained by him on account of the failure of plaintiffs to complete their contract within a reasonable time. In the second count he asked judgment for $225.75, alleged to be due him, by plaintiffs, for insurance paid in the sum of $11.25, and $214.50 expended for labor and trucking material for and on behalf of plaintiffs. The jury returned a verdict for plaintiffs against both defendants in the sum of $6,600 and interest in the sum of $2,178, a total of $8,778. The jury found for defendant Clark on the first count of the counterclaim in the sum of $214.50, and found against him on the second count.

[1] The principal contention, made by appellants for a reversal of this case, is that the trial court erred in not sustaining a demurrer to the evidence. The St. Louis Court of Appeals, by its opinion, practically settled that question. It reversed and remanded the case with instructions to permit plaintiffs to introduce evidence that plaintiffs were the real parties to the contract. At the second trial plaintiffs introduced such evidence. The contract itself, as the Court of Appeals pointed out, personally bound plaintiffs to perform the contract. The reason for the clause in the contract, referring to the Dahlstrom Company, is easily understood when one considers the requirements of the specifications which called for material equal to that manufactured by the Dahlstrom Company. There was also *Page 187 evidence tending to prove that the parties subsequently treated the contract as if it were between plaintiffs and defendant Clark. The evidence introduced was ample to support a finding that plaintiffs were the real parties to the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
62 S.W.2d 432, 333 Mo. 180, 1933 Mo. LEXIS 555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-st-louis-ex-rel-sears-v-southern-surety-co-mo-1933.