State Ex Rel. Winkle Terra Cotta Co. v. United States Fidelity & Guaranty Co.

40 S.W.2d 1050, 328 Mo. 295, 1931 Mo. LEXIS 399
CourtSupreme Court of Missouri
DecidedJuly 3, 1931
StatusPublished
Cited by9 cases

This text of 40 S.W.2d 1050 (State Ex Rel. Winkle Terra Cotta Co. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Winkle Terra Cotta Co. v. United States Fidelity & Guaranty Co., 40 S.W.2d 1050, 328 Mo. 295, 1931 Mo. LEXIS 399 (Mo. 1931).

Opinions

This is the second appeal in this case, the former opinion being reported in 322 Mo. 121, 14 S.W.2d 576.

The State of Kansas is a nominal party plaintiff. The real party plaintiff, the Winkle Terra Cotta Company, a corporation, brought this suit on a contractor's bond for the balance due for materials furnished for the construction of a building. Olson Johnson Company, a corporation, was the principal in the bond. The name was later changed to Olson-Magee Company. The defendant, United States Fidelity Guaranty Company, was surety on this bond.

The State of Kansas entered into a contract with Olson Johnson Company for the erection of a certain building at Lawrence, Kansas. Plaintiff was a subcontractor and furnished the terra cotta. The Kansas statute provided in part (Sec. 60-1414, R.S. Kan. 1923): "Any person to whom there is due any sum for labor and material furnished, as stated in the preceding section, or his assigns, may bring an action on said bond for the recovery of said indebtedness; Provided. That no action shall be brought on said bond after six months from the completion of said public improvements or buildings." The cause of action is based on plaintiff's contract, the bond and the Kansas statutes. [Secs. 60-1413, 60-1414, R.S. Kan. 1923.] For a full and complete statement of the case, the reader is referred to the former opinion. It is tacitly admitted in this case that the Winkle Terra Cotta Company was a subcontractor under Olson Johnson Company, and furnished the material as alleged in the petition under a contract with the original contractor Olson Johnson *Page 299 and that the amount sued for has not been paid. No evidence was offered at either the first or second trial by defendant to dispute plaintiff's claim. In the answer it is expressly admitted that the plaintiff furnished the material between March 6th and October, 1918. The answer further alleges that the building was completed December 2, 1918, and the state architect made his final monthly estimate of the completion of the said building on January 14, 1919. The suit was filed October 22, 1919. The defendant pleads the Kansas statute of limitations, supra, as a bar to this action. It is also pleaded in the answer that under the Kansas laws the plaintiff is not entitled to and has no right to sue in the name of the State. The defendant pleads in full the Kansas statute and decisions applicable to the issues according to defendant's theory.

At the first trial, judgment was entered for defendant apparently on the theory that the building was completed prior to January 14, 1919, the date of the final estimate of the state architect. The lower court held the case barred by virtue of the Kansas limitation statute, Section 60-1414, supra.

The case on appeal was reversed and remanded in an opinion written by Commissioner HIGBEE and concurred in by all of the judges and commissioners in Division Two of this court.

The case was retried before the court sitting as a jury, a jury having been waived by both parties. Plaintiff offered evidence of the furnishing of the materials and of the balance due and unpaid, also the contract entered into with Olson Johnson, and in general offered evidences in support of the allegations of its petition. The court found in favor of the plaintiff and entered judgment for $32,275.31 and interest $21,961.86. The defendant, failing in his motion for a new trial, appealed.

The issues raised by the answer in this case are identical with those disposed of on the former appeal. During theStare second trial no new issues were presented to the courtDecisis. that were not fully considered and disposed of in the former opinion.

We are not authorized to disturb the rulings in the former opinion unless we find it manifestly erroneous, or that an injustice has been done. [Northstine v. Feldmann,8 S.W.2d 912.] The circuit court on the retrial followed the rulings in the former case, which became and is the law of the case. Those questions therefore adjudicated in the former opinion are not open for re-examination on this appeal. [Chambers' Admr. v. Smith's Admr., 30 Mo. 156; Mullins v. Mt. St. Mary's Cemetery Assn., 168 S.W. 685, 259 Mo. 142; State ex rel. Dolman v. Dickey,231 S.W. 582, 288 Mo. 92; Seibert v. Harden, 8 S.W.2d 905,319 Mo. 1105; Gracey v. St. Louis, 221 Mo. 1; Bagnell v. Railway, 242 Mo. l.c. 21. For other cases see Mo. Digest, Appeal and Error, sec. 1097.] *Page 300

The defendant earnestly insists, however, that the full-faith-and-credit clause of the Federal Constitution was violated or ignored by the court in the former opinion and in the second trial. [Art. 4, sec. 1.] This is a newFull Faith question in the case. The principal point in theand Credit. entire case is the date of the completion of the building. The defendant's theory is that the final report of the state architect is conclusive evidence of the completion of the building, and that the building was actually completed prior to January 14, 1919. The plaintiff's theory is the converse. Referring to the former opinion we find that this question was fully considered and discussed at length at pages 580, 581 (1), 14 S.W.2d. We further find that in the determination of this question, adverse to the defendant, the learned commissioner cited and applied the rules of law as announced by the Kansas courts in similar cases, construing the various statutes now under consideration. [Hull v. Mass. Bonding Ins. Co., 86 Kan. 342, 345, 120 P. 544, 545; State of Kansas v. Mass. Bonding Ins. Co., 91 Kan. 75, 136 P. 905.] The determination of this question was therefore in accordance with the lex loci, the laws of Kansas.

The next contention of the defendant is that plaintiff could not maintain this action in the name of the State of Kansas, in that state. That the lex loci, and not the lex fori, controls in this regard. Therefore, plaintiff's action shouldProper be dismissed. After a careful consideration of thisPlaintiff. question the former opinion holds that the lex fori and not the lex loci governs. The Missouri statute, Section 2855, Revised Statutes 1929, provides that all suits on official bonds must be brought in the name of the State or other obligee named in the bond. The Kansas law requires the suit to be brought in the name of the real party in interest, and not the state. The manner of bringing the suit, as in this case, whether properly brought in the name of the obligee named in the bond, or the real party in interest, pertains to the form of the remedy and does not go to the substance of the action. It is therefore controlled by the lex fori. Such is the uniform ruling of the various courts. [Hefferlin v. Sinsinderfer, 2 Kan. 401; 47 C.J. 17, and cases cited; 12 C.J. 483, 485, and cases cited.]

The defendant also contends that the Kansas statute of limitations should govern. The former opinion holds the contrary. This, however, is a moot question in the case. It was definitely determined against defendant's contention that the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toomes v. Continental Oil Company
402 S.W.2d 321 (Supreme Court of Missouri, 1966)
Nelson v. Browning
391 S.W.2d 873 (Supreme Court of Missouri, 1965)
Schneider v. Campbell 66 Express, Inc.
324 S.W.2d 363 (Missouri Court of Appeals, 1959)
Foster v. Kurn
163 S.W.2d 133 (Missouri Court of Appeals, 1942)
State Ex Rel. United Mutual Insurance v. Shain
162 S.W.2d 255 (Supreme Court of Missouri, 1942)
Poe v. Illinois Cent. Railroad Co.
99 S.W.2d 82 (Supreme Court of Missouri, 1936)
State Ex Rel. Gatewood v. Trimble
62 S.W.2d 756 (Supreme Court of Missouri, 1933)
City of St. Louis Ex Rel. Sears v. Southern Surety Co.
62 S.W.2d 432 (Supreme Court of Missouri, 1933)
Carter v. Burns
61 S.W.2d 933 (Supreme Court of Missouri, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
40 S.W.2d 1050, 328 Mo. 295, 1931 Mo. LEXIS 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-winkle-terra-cotta-co-v-united-states-fidelity-guaranty-mo-1931.