Crane O'Fallon Co. v. Via

251 P.2d 260, 56 N.M. 772
CourtNew Mexico Supreme Court
DecidedNovember 20, 1952
DocketNo. 5509
StatusPublished
Cited by2 cases

This text of 251 P.2d 260 (Crane O'Fallon Co. v. Via) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crane O'Fallon Co. v. Via, 251 P.2d 260, 56 N.M. 772 (N.M. 1952).

Opinion

SADLER, Justice.

The appellants, H. H. Via and National Surety Company, defendants below, complain of a judgment against them rendered by the district court of Valencia County in favor of Crane O’Fallon Company, the plaintiff, the appellee in this court, in the sum of $3,865.83, for goods, wares and merchandise said to have been sold and delivered to Clifford Taylor, a subcontractor, also a defendant herein, in the construction of a public' building, to-wit, a research laboratory, for the Regents of the New Mexico School of Mines at Socorro under a contract between them and the defendant, Via, with the defendant, National Surety Company, as surety on the public bond given to secure performance of the contract according to its terms.

The plaintiff, Crane O’Fallon Company, is a Colorado Corporation, with its principal place of business at Denver, Colorado, but authorized to do business in New Mexico. The defendant, Via, is a resident of Santa Fe, New Mexico, where she is engaged in business as a general contractor, while Clifford Taylor, d/b/a Taylor Plumbing and Heating Company, is a resident of Valencia County, New Mexico. The names and residences of the parties were as indicated above and the Regents of the New Mexico School of Mines being desirous of constructing a research laboratory at Socorro for use in carrying on the work of that institution, on December 17, 1948, they entered into a contract with defendant, Via, for the construction of the laboratory, a public building, at or near the site of the school in Socorro.

Incident to. the execution of the contract Via, the contractor, furnished the bond provided by 1941 Comp. § 6-511, with the defendant, National Surety Company, as surety conditioned, among other things, and subject to terms of the bond, upon payment for materials and supplies furnished upon or for work under the original contract, or any subcontract. The defendant, Clifford Taylor, was a subcontractor employed by defendant, Via, the contractor, to do the plumbing and heating work on the building. Commencing in March, 1949, the plaintiff furnished the defendant, Clifford Taylor, on an open running account goods, wares and merchandise for work to be done under his subcontract.

On or before September 14, 1949, during the progress of the work, the owner of the premises by its Superintendent, Dr. Workman, objected to a lavatory which had been installed by the plaintiff through subcontractor Taylor as not being satisfactory. On the date last above mentioned William E. Burk, architect under the original contract, at the request of Dr. Workman and with the consent of subcontractor Taylor, ordered from the plaintiff’s office in Albuquerque, New Mexico, a No. 1-270-L 27 x 20" Elayne white lavatory basin as a substitute for the lavatory already furnished and installed.

At the time this order was received at the Albuquerque office of plaintiff, it did not have the Elayne lavatory in stock. Accordingly, it ordered one from its factory in Trenton, New Jersey, with the knowledge and consent of Dr. Workman, architect Bui-k and subcontractor Taylor and delivered same to the premises of New Mexico School of Mines at Socorro on December 6, 1949. It was the last item of material furnished defendant, Clifford Taylor, under his subcontract and was furnished by plaintiff in good faith.

Notwithstanding delivery of the Elayne white lavatory basin as already shown, it was never installed in the building, either under the principal contract or any subcontract. However, it was delivered by the truck driver employed by the School of Mines to the School of Mines at. Socorro where it has since remained, uncrated in a storage room, since the time of its delivery as aforesaid. It should be added that this Elayne lavatory was materially different from the type called for by the specifications in that it was a flat cabinet or table type, the ones required by the contract documents being wall type china lavatories.

The defendant, Via, was not advised personally or through any agent, servant or employee of 'hers of the intended replacement of the lavatory basin previously installed by Taylor with the above-mentioned Elayne white lavatory basin, and there was no change order issued to her for such substitution. Nevertheless, the trial court found along with the above-mentioned facts that not only Clifford Taylor,.the subcontractor, who ordered the Elayne lavatory, was indebted for a balance on open account including the charge to the Elayne lavatory in the sum of $3,865.83, but that the defendants, Via and her surety, National Surety Company, as well, were jointly and severally liable therefor and, accordingly, indebted to plaintiff in the same amount.

Formal written notice was served on defendant, National Surety Company, the surety named in the bond, on February 28, 1950, as provided by law. And, basing its conclusions of law on the foregoing facts found by the court, it deduced that plaintiff was entitled to recover from the three defendants named, Via, the contractor, Clifford Taylor, the subcontractor, and National Surety Company, jointly and severally, the sum of $3,865.83 with interest at six per cent, from June 6, 1950. Judgment was rendered accordingly, to review which and secure its correction the defendants, Via and National Surety Company, prosecute this appeal.

Due to the fact that there were numerous items charged on the open account as having been furnished for this job that were neither called for by the plans and specifications, nor approved as representing changes or extras under the contract, which items were not used in the construction or completion of the contract, it is not disputed that unless the charge as of December 6 (8), 1949, for the Elayne lavatory furnished on order of the subcontractor Taylor as a substitute for the one already installed in Dr. Workman’s apartment the written notice given the surety on February 27, 1950, is ineffective to revive liability of the surety under the bond because given more than 90 days after date of the last charge item properly to be considered in that connection. There is no serious claim by the plaintiff that the questioned charge item on the open account entered as of December 8, 1950, but mistakenly referred to in the findings as December “6” does not represent the critical charge.

Indeed, as disclosed by the following statement from plaintiff’s answer brief, it recognizes its right to recovery depends absolutely upon its right to treat the item of December 8, 1950, as the last item of material furnished by it to the subcontractor, Taylor, for the School of Mines project, to-wit:

“In order for Appellee to recover, it is necessary that this Elayne lavatory constitute the last item of material furnished by Appellee to Defendant Taylor for the School of Mines project.”

The real issue before us on this appeal is so clearly stated in the only assignment of error made by the defendants (appellants) that we shall begin our treatment of the legal side of our opinion by quoting it verbatim. It reads:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Solsbury Hill v. Liberty Mut.
2012 NMCA 032 (New Mexico Court of Appeals, 2012)
State ex rel Solsbury Hill, LLC v. Liberty Mut. Ins. Co.
2012 NMCA 32 (New Mexico Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
251 P.2d 260, 56 N.M. 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crane-ofallon-co-v-via-nm-1952.