Preston v. Frank Forrestal Co.

272 P. 975, 150 Wash. 340, 1928 Wash. LEXIS 995
CourtWashington Supreme Court
DecidedDecember 20, 1928
DocketNo. 21513. Department One.
StatusPublished
Cited by3 cases

This text of 272 P. 975 (Preston v. Frank Forrestal Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preston v. Frank Forrestal Co., 272 P. 975, 150 Wash. 340, 1928 Wash. LEXIS 995 (Wash. 1928).

Opinion

*341 Mitchell, J.

The Frank Forrestal Company, hereinafter called the contractor, made a contract with the city of Seattle on June 3,1927, for the improvement of certain streets under an ordinance creating local improvement district number 4498, and on the same day and in connection therewith, the contractor, together with the United States Fidelity and Guaranty Company, made, executed and delivered to the city a bond as required by law.

The contract provided for the retention of fifteen per cent of all estimates, made monthly, for the purpose of paying labor and material claims, the remaining eighty-five per cent to be paid to the contractor, with certain limitations and restrictions, to be noticed later herein.

On September 28, 1927, the contractor, for a valuable consideration, assigned all its right, title and interest in and to all payments due or to become due, under the contract, to the American Discount Corporation, hereinafter called the discount corporation, notice of which assignment was filed on that day in the office of the city comptroller. The work was completed by the contractor on October 7, 1927, and accepted by the city.

On October 10, 1927, an estimate as of the date of October 1, 1927, was prepared by the city engineer, showing $2,396.42 due for work, over and above the fifteen per cent reserve, which amount of $2,396.42, under the terms of the contract, was payable on October 25, 1927. During the first twenty-four days of October, 1927, that is, prior to pay date for the September estimate, valid claims for labor and material against the job had been filed in a total amount in excess of the amount due the contractor on account of the September estimates, including-the fifteen per cent reserve. Thereafter and within proper time, other *342 valid claims for labor and material against the work were filed, making a total of $6,423.08 for all claims filed both before and after October 25, 1927.

. All of these claims were assigned to Frank M. Preston, who brought this action against the contractor, the city of Seattle, the bonding company and the discount corporation and others, for a judgment declaring the plaintiff, as assignee of the claimants, to have the first lien upon and entitled to all the moneys held by the city owing on the contract, and for judgment against the contractor and bonding company for the balance due the plaintiff.

The city answered, admitting its indebtedness to the contractor. It tendered the same into court to be distributed to the parties entitled thereto.

The discount corporation answered, and by way of cross-complaint set up its claim, by virtue of the assignment from the contractor, to the amount of $2,306.42, which represented the eighty-five per cent due the contractor, and further pleaded that the funds so paid by it to the contractor, in taking the assignment, were used and expended by the contractor in paying for labor, materials, provisions and supplies furnished and expended in the performance of the contract with the city. In its answer it expressly waived any claim to the fifteen per cent reserve held by the city.

The defendant bonding company answered plaintiff’s complaint, - and it also answered the cross-complaint of the discount corporation, alleging that the claims assigned to the plaintiff were valid claims, and demanded that they be given priority so as to reduce the amount it would otherwise be liable to pay under its bond; and further alleged its giving written notice to the city comptroller on October 21,-1927, not to pay or draw a warrant in favor of the contractor for the *343 amount due October 25, 1927, as tbe claims for labor and material were ahead of any claim on tbe part of tbe contractor or its assignee, tbe discount corporation.

Tbe trial resulted in findings of fact, conclusions of law and judgment, giving tbe plaintiff a superior right to all tbe balance due tbe contractor by tbe city, including tbe fifteen per cent reserve, amounting altogether to tbe sum of $4,420.99; and for tbe remainder due on plaintiff’s claims be was given judgment against tbe contractor and tbe bonding company in tbe sum of $2,002.09. Tbe cross-complaint of tbe discount corporation was dismissed with prejudice. Tbe discount corporation has appealed.

Counsel have discussed tbe equities claimed to be in its favor, because tbe money it furnished tbe contractor was used by tbe latter to pay on tbe construction cost of tbe improvement, as compared with tbe equities of tbe bonding company, a compensated surety. But as we view tbe case that controversy is not important.

Tbe controlling question relates to tbe superior right of plaintiff, respondent, over that of tbe appellant to tbe eighty-five per cent of tbe funds that were owing tbe contractor at tbe time tbe claims for labor and material were incurred and filed.

It is necessary to a decision of tbe case to notice other facts proven under tbe pleadings, as follows: Tbe contract provided that:

“Tbe contractor shall pay tbe wages of all persons employed on or about said work, and for all other service. He shall pay for all materials purchased therefor, and tbe city of Seattle may withhold any and all payments under this contract until tbe provisions of this section have been fully complied with.”
“Tbe city comptroller shall not pay to tbe contractor any portion of tbe amount due on this contract, *344 unless at the time of payment all claims filed with the city comptroller for material purchased or labor performed thereon shall have been fully paid. If at any time during the progress of this improvement it shall appear to the city comptroller that the contractor has neglected, refused or failed to pay in cash for any labor performed thereon, and that time checks or other evidences of indebtedness have been issued by such contractor, then the city comptroller, upon presentation to him of such time checks or other evidences of indebtedness, shall issue to such labor claimants a warrant or warrants therefor upon the local improvement contingent fund. The city comptroller shall charge the amount of all warrants so issued against the account of the contractor for this improvement and shall deduct the amounts thereof, together with a penalty of ten per cent (10%) thereon, from the next or succeeding payments to be made to said contractor. Any sum or sums so paid may be deducted from the eighty-five per cent (85%) to be paid to such contractor, as provided in this contract, or from any other sum or sums due said contractor.”

Further, it was proven, and the court found, that the assignment made by the contractor to the appellant contained the following provision:

“This assignment is not valid as against any claim for labor, material, provisions and goods supplied and furnished in the prosecution of this contract.”

Essentially the same kind of facts existed in First National Bank v. Seattle, 71 Wash. 122, 127 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stover v. Winston Bros. Co.
55 P.2d 821 (Washington Supreme Court, 1936)
Building Materials, Inc. v. Electric Equipment & Engineering Co.
7 P.2d 601 (Washington Supreme Court, 1932)
Hall & Olswang v. Aetna Casualty & Surety Co.
296 P. 162 (Washington Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
272 P. 975, 150 Wash. 340, 1928 Wash. LEXIS 995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/preston-v-frank-forrestal-co-wash-1928.