Knapp v. Swaney

56 Am. Rep. 397, 56 Mich. 345
Michigan Supreme Court·Decided April 15, 1885·Published·Cited by 58 cases

Opinion

Cooley, C. J.

The facts of this case, so far as material to the decision, are the following:

The county of Lenawee by popular vote, in the year 1882, decided to raise $50,000 for the construction of a court-house. In providing for the construction the board of supervisors appointed a “ committee on court-house,” to whom it was proposed to refer all matters relating to the building. Of this committee the respondent Swariey was chairman, and the respondent Hunter clerk, and they have continued to be such officers to the present time. It was among the powers conferred upon them that they were .to draw orders upon the county treasury in payment of contractors.

The committee, in pursuance of their authority, proceeded to obtain plans and specifications for the building, and to advertise for proposals for its construction. Bids were received, and among these was one from the copartnership of Allen & Yan Tassel, and this was deemed most favorable and was accepted. A contract for construction was therefore duly entered into with them, and the relators became sureties for due performance on their part.

One of the provisions of the contract was that the eon-tractors were not to sublet the work or any part thereof without the written consent of the committee. Another was that payments were to be made on estimates by the architect, but it was provided that in each case a certificate shall be obtained by the contractor from the register of deeds where liens are recorded, signed and sealed by said register, that he has carefully examined the records in his office, and finds no liens or claims recorded or filed against said works and buildings, or on account of the said contractor. Neither shall there be [347] any legal or lawful claims against the contractor in any manner from an}' source whatever, for work or materials furnished on said work and buildings.”

The contractors proceeded for a time in construction, and then failed, and the relators for their own protection took an assignment of the contract and went on with the work. No objection seems to have been made to this, and their substitution in the place of the contractors was practically assented to. The work proceeded until January 7, 1885, when the relators obtained estimates from the architect for something over $7000, which they presented to the respondents, and re-' quested an order on the county treasurer for the amount. They also at the same time presented a certificate under' the hand and seal of the register of deeds for the county, stating that no other liens or claims appeared in his office except the following: A claim of lien by Townsend & Burton for materials, filed October 20, 1884; a claim of lien by True, Brinkhorst <$t Oo. for materials and labor, filed October 16, 1884; a claim of lien by E. O. Sword for materials, filed January 6, 1885 ; and a claim of lien by Herbert Baker, for labor and materials filed October 30, 1884. Copies of these-several claims appear in the record. The relators denied that there were or could be any liens in such a case, and insisted on their order, but the respondents refused it. A mandamus was thereupon applied for, and the parties have formed an issue upon the application and brought the facts before us.

The position of the relators that there can be no liens in such a case we consider unquestionable. Public property cannot be the subject of such a lien unless the statute shall expressly so provide; it is by implication excepted from lien statutes, as much as from general tax laws, and for the same reasons. Foster v. Fowler 60 Penn. St. 27; Frank v. Freeholders 39 N. J. L. 347; Poillon &. Mayor &c. 47 N. Y. 666; Board of Education v. Neidenberger 78 Ill. 58; Bouton v. McDonough County 84 Ill. 384; Loring v. Small 50 Iowa 271. For tax cases see People v. Doe 36 Cal. 220; People v. Salomon 51 Ill. 37; Louisville v. Com. 1 Duv. 295; Gibson v. Howe 37 Iowa 168; Directors of Poor v. School Directors [348]*34842 Penn. St. 21; State v. Gaffney 34 N. J. Law 133. We may therefore put aside all questions of lien.

But the contract does not provide for liens merely, but also that there shall be no legal or lawful claims against the contractor, in any manner, from any source whatever, for work or materials furnished on said work and buildings,” when payment of estimates is called for. Whether the certificate of the register is to negative such claims, is not very clear as matter of construction nor, perhaps, very important. It is not shown or urged that no such claims exist, and we must assume that they do, or at least that they may. The question then is, are the contractors, under the contract, or the relators, as their assignees, entitled to payment while there are outstanding claims for materials or labor ?

The claims in this case appear to be claims against Allen & Yan Tassel, not against the relators. In our opinion that is an immaterial fact. The relators step into the shoes of the contractors, and can claim nothing under the contract which Allen & Yan Tassel themselves could not have claimed.

But the relators insist that the provision in the contract which makes payment depend upon the non-existence of claims against the contractors was one the committee or the board of supervisors whom they represented had no authority to make, and it was therefore inoperative. The argument on this point shortly stated is that the board of supervisors as a corporation or quasi corporation possesses only certain powers expressly mentioned and defined by law, and that among these is no power to interpose between employers or purchasers and the persons with whom they deal, for the purpose of compelling the performance of contract obligations which such employers or purchasers have assumed. Cases cited to the general doctrine are Vincent v. Nantucket 12 Cush. 103; Halstead v. Mayor &c. 3 N. Y. 430; Minturn v. Larue 23 How. 435; Stetson v. Kempton 13 Mass. 272; Hodges v. Buffalo 2 Den. 110; New London v. Brainard 22 Conn. 552. The following quotations are also made from opinions of this Court: “A municipal corporation has no general authority to exchange promises with other corpora[349] tions or with individuals. Its contracts must be within the scope of the authority conferred upon it by law and for municipal purposes.” Thomas v. Port Huron 27 Mich. 320, 323. “There is a principle of law that municipal powers are to be strictly interpreted, and it is a just and wise rule. Mmiieipalities are to take nothing from the general sovereignty except what is expressly granted.” Port Huron v. McCall 46 Mich. 565, 574.

We hold to these views strictly. Municipal bodies are not philanthropic or charitable institutions, but they are part of the governmental machinery of the State, and exist for public purposes exclusively. It is not within their province to act as collecting agents for individuals, either directly or indirectly. This much should be freely conceded.

Free access — add to your briefcase to read the full text and ask questions with AI

Knapp v. Swaney, 56 Am. Rep. 397, 56 Mich. 345 (Mich. 1885).

56 Am. Rep. 397 (Knapp v. Swaney) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kammer Asphalt Paving Co. v. East China Township Schools
504 N.W.2d 635 (Michigan Supreme Court, 1993)
Milbrand Co. v. Department of Social Services
324 N.W.2d 41 (Michigan Court of Appeals, 1982)
State Highway Commission v. United Pacific Insurance
216 N.W.2d 469 (Michigan Court of Appeals, 1974)
Roulo v. Automobile Club of Michigan
179 N.W.2d 712 (Michigan Court of Appeals, 1970)
Lake States Engineering Corp. v. Lawrence Seaway Corp.
167 N.W.2d 320 (Michigan Court of Appeals, 1969)
Foster v. Kerr & Houston, Inc.
179 A. 297 (Supreme Judicial Court of Maine, 1935)
Union Indemnity Co. v. State Ex Rel. McQueen Smith Farming Co.
114 So. 415 (Supreme Court of Alabama, 1927)
Gary Hay Grain Co., Inc. v. Carlson
255 P. 722 (Montana Supreme Court, 1927)
Southwestern Portland Cement Co. v. Williams
251 P. 380 (New Mexico Supreme Court, 1926)
Aetna Casualty & Surety Co. v. Earle-Lansdell Co.
129 S.E. 263 (Supreme Court of Virginia, 1925)
State Ex Rel. West Virginia Sand & Gravel Co. v. Royal Indemnity Co.
128 S.E. 439 (West Virginia Supreme Court, 1925)
Electric Transmission Co. v. Pennington Gap Bank, Inc.
119 S.E. 99 (Supreme Court of Virginia, 1923)
Clatsop County ex rel. Hildebrand v. Feldschau
199 P. 953 (Oregon Supreme Court, 1921)
Mosher Mfg. Co. v. Equitable Surety Co.
229 S.W. 318 (Texas Commission of Appeals, 1921)
Kief v. Mills
179 N.W. 724 (Supreme Court of Minnesota, 1920)
Toner v. Long
111 A. 311 (Supreme Court of New Hampshire, 1920)