Associated Indemnity Corp. v. King County School District No. 181

47 P.2d 10, 182 Wash. 414, 1935 Wash. LEXIS 650
CourtWashington Supreme Court
DecidedJuly 10, 1935
DocketNo. 25329. Department One.
StatusPublished
Cited by1 cases

This text of 47 P.2d 10 (Associated Indemnity Corp. v. King County School District No. 181) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Indemnity Corp. v. King County School District No. 181, 47 P.2d 10, 182 Wash. 414, 1935 Wash. LEXIS 650 (Wash. 1935).

Opinion

Tolman, J. —

Respondent, as plaintiff, by its complaint in this action set forth a building contract between the defendant school district and the defendant Lovell, by the terms of which Lovell agreed to do certain work for a specified sum, payment to the extent of eighty-five per cent to be made to him as the work progressed and the remaining fifteen per cent to be retained until after the completion and .acceptance of the work. The contract, among other things, provides:

“Article 5. Acceptance and Final Payment — Final payment shall be due thirty days after substantial completion of the work provided the work be then fully completed and the contract fully performed.
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the architect shall promptly make such inspection, and when he finds the work acceptable under the contract and the contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the contractor, and noted in said final certificate, is due and payable.
“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.”

The plaintiff became the surety on the contractor’s bond. Certain facts bearing upon the question of the completion and acceptance of the work were pleaded, *416 and it is then alleged that, on October 19, 1931, final payment of the retained percentage was made to the contractor; but that, thereafter, there were presented and filed with the school district the claims of a number of materialmen against the retained percentage and against the bond, and that action is threatened thereon. The prayer of the complaint is for determination of whether or not the retained percentage was illegally paid, whether the claims referred to were timely filed, and to what extent, if at all, .the plaintiff, as surety upon the contractor’s bond, is liable therefor, and

“ (4) That, if the court finds that any of said claims constitutes a valid charge and demand against plaintiff herein, the defendants, State of Washington, King-County School District No. 181, H. T. Lundy, W. W. Watson, Gr. J. Gíwinn, and W. A. Lovell be required to restore the amount of the retainage on said contract and that said fund be applied in payment of said claims so held to be valid.”

The contractor defaulted, but issues as to the school district and as to the claims of the various claimants were made up. The cause proceeded to trial on the merits to the court, sitting without a jury, resulting in a decree which awards judgment to certain claimants against the contractor and the surety on his bond; a judgment to certain claimants against the school district in a sum equal to the retained percentage, with a proviso that amounts collected thereon shall be credited upon the judgments in favor of those claimants and against the surety on the bond, and that satisfaction of their judgments against the surety shall constitute a satisfaction of their judgment against the school district. The surety was given a judgment against the contractor and a judgment against the school district for the full amount of the retained percentage, together with the full amount, including in *417 terest, costs and attorney’s fees, allowed to the several claimants against the bond. The school district has appealed from all portions of this decree which adversely affect it, and the plaintiff has appealed from that portion of the decree which allows recovery by the materialmen against it.

The school district on its appeal seems to raise four questions, the first of which, and one upon which it places great stress, is a question of fact only, namely: Did the school district accept the work as completed, or substantially completed, at its meeting of September 1, 1931, or at any time more than thirty days prior to the day when the retained percentage was paid to the contractor?

The evidence upon this issue is involved, conflicting, and'in some respects painfully close. The minutes of the meeting of the school directors of the date relied upon fail to show anything indicating that an acceptance was then considered, although there was oral testimony that a motion was adopted accepting the work as substantially completed. The testimony of the architect rather clearly indicates that there was no acceptance at that time, and our study and search of the testimony in the written form as here presented has failed to reveal anything which will warrant us in deciding that the evidence preponderates ’ against the trial court’s holding that there was no acceptance before October 15, 1931. This being so, we cannot disturb the holding that the claims of the materialmen were timely filed, were entitled to the protection of the bond, and were valid liens on the retained percentage if improperly paid.

It is, however, contended that none of the materialmen brought any action within four months of the time when their claims were filed, and therefore that none can now complain because of the payment *418 to the contractor. This contention is answered by the case of United States Fidelity Guaranty Co. v. Mon-tesano, 160 Wash. 565, 295 Pac. 934, where, in deciding- a like question, it was said:

“When it paid to the contractors that reserved fund within ten days after acceptance of the bridge, the city breached the contract and violated the statute; the city made it unnecessary and useless to file a notice of claim of lien against the reserved fund, as there was no reserved fund by reason of its misappropriation by the city.
“The breach of the contract and violation of the statute on the part of the indemnified respondent, resulted in damage to the appellant surety, therefore the appellant should be compensated for such damage, the extent of which is the amount of the retained fund wrongfully paid by the respondent to the contractors.”

Moreover, this action was brought to settle all controversies and to bind all interested parties, and it was instituted well within the four months period and was a sufficient compliance with the statutory four months limitation.

The third point raised the question of consent by the surety to the payment of the retained percentage as and when such payment was made.

It appears without dispute that one Wayne C. Meek is the attorney-in-fact who executed the bond with which we are here concerned, for and on behalf of the surety, and that, pursuant to notice to the surety, Meek attended the meeting of the school directors which was held on October 19, 1931, for the purpose of making final settlement with the contractor. Meek was, of course, cognizant of all that then took place; and if he had authority, express or implied, to then represent it, he and it were charged with notice that the written minutes showed no prior acceptance of the work, and it was his duty to ascertain at his peril

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
47 P.2d 10, 182 Wash. 414, 1935 Wash. LEXIS 650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-indemnity-corp-v-king-county-school-district-no-181-wash-1935.