Keenan v. Empire State Surety Co.

113 P. 636, 62 Wash. 250, 1911 Wash. LEXIS 685
CourtWashington Supreme Court
DecidedFebruary 20, 1911
DocketNo. 9120
StatusPublished
Cited by1 cases

This text of 113 P. 636 (Keenan v. Empire State Surety Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keenan v. Empire State Surety Co., 113 P. 636, 62 Wash. 250, 1911 Wash. LEXIS 685 (Wash. 1911).

Opinion

Fullerton, J.

On January 19, 1909, the respondent entered into a contract with the defendants, Frank Armstrong and Fred E. Enevoldsen, whereby they undertook to furnish all the necessary labor and material and construct an apartment house on a certain described lot for a consideration of $13,500, “less two hundred dollars ($200) reserved for the payment of hardware for said building.” The contract was in writing, and was on the form adopted and recommended for general use by the American Institute of Architects and the National Association of Builders, and contained, among others, a provision to the effect that should the contractors at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or materials of proper quality, or fail in any respect to perform the work with promptness and diligence, and such refusal, neglect or failure be certified by the architects, the owner, after three days’ notice to the contractors, should be at liberty to perform the same and deduct the cost thereof from any money then due, or thereafter to become due to the contractors under the contract. It also provided that, should the architects certify that there was sufficient ground for. such action, the owner should be at liberty to terminate the contract, enter upon and take possession of the building, and complete the work according to the contract, at his own expense, and account to the contractors only for such balance as might remain after deducting the cost of the completion of the building from the unpaid balance of the contract price.

At the time of the execution of the contract, the contractor executed a bond to the respondent with the appellant Empire State Surety Company as surety, conditioned for the faithful performance of the contract. The bond contained further stipulations to the effect that the owner should give notice to it at its office in New York city of any default on the.part of the contractors in the performance of any of the conditions of the contract within fifteen days after the default occurs, and should retain not less than fifteen per centum of [252]*252all payments for work performed and materials furnished in the performance of the contract until the complete performance by the contractors of all the conditions of the contract on their part to be performed, and until the expiration of the-time in which liens can be filed, and until the cancellation and discharge of liens if any are filed.

' The contractors entered upon the performance of the contract immediately after its execution, and during the first month thereof performed labor upon, and furnished material for, the construction of the building which entitled them, according to the architects’ estimate, to the sum of $660. This sum was paid them by the owners, and the work was continued for another monthly period. At the end of that time, the .contractors informed the owner that they were unable to meet the expense incurred for labor and material during the preceding month, as required by the contract, and consequently could not obtain the architects’ certificate which authorized the second monthly payment to them by the owner, and requested the owner to make payments directly to the laborers and materialmen, at the same time confessing their inability to proceed further with the contract according to its conditions. The owner thereupon procured from the architects a certificate to the effect that the contract had been violated by the contractors, setting out the particulars, and that the respondent was authorized and empowered to take possession of the work and complete it himself. A notice was immediately sent to the surety company notifying them of the default on the part of the contractors, together with a copy of the architects’ certificate, accompanied by a demand that it take upon itself the completion of the work. A letter was sent the owner by the surety company acknowledging the receipt of the notice, and stating that the matter had been taken up with their local agent, who had been instructed to give it attention and report. The owner thereupon called on the local agent named in the letter, and was informed that a Mr. Eldredge would call upon him. Mr. Eldredge called as [253]*253stated, and an arrangement was made whereby the contractors left the construction of the building in the charge of a Mr. Burgess, the then acting superintendent for the contractors, who undertook to superintend the final construction of the building on behalf of the contractors, the owner agree'ing to meet the bills for such labor and materials as should be necessary to complete the work. The consent of the contractors to this arrangement was put in writing, this being procured from the contractors by the agent of the surety company. The building was completed according to this arrangement, at an expense to the owner of $20,507.87.

In the final estimate made by the architects it was found that $2,078.31 of this sum had been paid for labor and materials not contemplated in the original plans, although permitted by the contract, and that certain deductions had been made from the original plans, making a saving in the cost of the building of $460, leaving a net excess in the cost of the building over and above the contract price of $5,589.56. The contract called for the completion of the building on April 20, 1909. It was in fact completed on July 10, 1909, and for this delay the owner claimed the sum of $700. Demands for these sums were made upon the surety company, but the company denied liability, and the present action was begun to recover the amount thereof. Judgment went for the owner, and the appeal was taken therefrom by the surety company.

The principal contention urged for reversal is that there was a breach of the condition of the bond. It is claimed that the owner did not retain fifteen per centum of all payments becoming due for labor performed or materials furnished until after the completion of the work by the contractors. But notwithstanding its strenuous contention to the contrary, it is clear that this condition of the bond was waived by the surety. It will be remembered that the contractors, at the end of the second month, announced their inability to perform the contract according to its terms, and their requirement of [254]*254financial assistance if the building was to be completed at all; that this condition of their affairs was made known to the surety company by the owner, and that the surety company referred the matter to their agents, who took the matter up with the owner with the result that the owner agreed to so far modify the contract as to pay the obligations incurred in the construction of the building as they matured. Since this was done with the knowledge and co-operation of the surety company’s representative, it is enough to show an implied assent thereto on the part of the surety company, although it may be that there is no evidence in the record of an express assent on the part of the surety company or its representative to a modification of the contract.

It is argued also in this connection that there is no proof in the record that the surety company ever authorized its representative to waive any of the conditions of the bond, but as to this it is enough to say that the company stated, in writing to the owner in answer to his notification, that it had referred the matter to the particular agent, without stating that any limitations had been put upon his powers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
113 P. 636, 62 Wash. 250, 1911 Wash. LEXIS 685, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keenan-v-empire-state-surety-co-wash-1911.