Inland-Ryerson Construction Products Co. v. Brazier Construction Co.

500 P.2d 1015, 7 Wash. App. 558, 67 A.L.R. 3d 914, 1972 Wash. App. LEXIS 1009
CourtCourt of Appeals of Washington
DecidedSeptember 11, 1972
Docket877-1
StatusPublished
Cited by8 cases

This text of 500 P.2d 1015 (Inland-Ryerson Construction Products Co. v. Brazier Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Inland-Ryerson Construction Products Co. v. Brazier Construction Co., 500 P.2d 1015, 7 Wash. App. 558, 67 A.L.R. 3d 914, 1972 Wash. App. LEXIS 1009 (Wash. Ct. App. 1972).

Opinion

Callow, J.

This action arose as a result of the building of Interlake High School by Bellevue School District No. 405. The participants in the transaction with which we are concerned are:

a) Inland-Ryerson Construction Products Company, Inc., plaintiff-appellant, the subcontractor.
b) Brazier Construction Co., Inc., the defendant-respondent and cross-appellant, the contractor.
c) United Pacific Insurance Company, respondent and cross-appellant, surety on the contractor’s performance bond.
d) David Brazier, the president of Brazier Construction Co., Inc., and his estate, defendant-appellant.

The parties will be referred to as the subcontractor, the contractor, the surety and David Brazier or his estate.

The subcontractor filed a complaint for breach of contract and for lien foreclosure against the contractor and the surety, and they filed a counterclaim and amended answer which alleged that the subcontractor had released its claim against the contractor and was, therefore, estopped from asserting liability against the surety and the bond. Following trial, judgment was entered in favor of the subcontractor against the contractor and the estate in the sum of $62,380; and the surety was dismissed.

On May 9, 1966, the contractor entered into a contract with the school district for the construction of the high school. The contractor arranged with the surety for a public works bond in the sum of $3,046,066.10, the bond being executed pursuant to RCW 39.08. The subcontractor sup *560 plied labor and material and by April 1968, claimed $91,890.19 was due (approximately $29,000 of the amount was disputed by the contractor) and on or about April 17, 1968, filed a lien against the retainage fund held by the school district pursuant to RCW 60.28.010. At the time of the filing of the lien claim notice with the school district, the project was almost completed and $176,384.91 of the earned retainage was being withheld.

Finding of fact No. 7, as corrected by the court, stated: •

VII.
That a copy of the lien notice was received by United Pacific on or about April 17,1968 and was referred to the Bostik-Monarch [sic] Insurance Agency for investigation. Subsequent to the receipt of the notice, Mr. Bostik [sic] of the insurance agency acting on behalf of Mr. Brazier and United Pacific Insurance Company went to the office of the plaintiff’s attorney, Jerry Schumm, and made inquiry concerning the matters. He thereafter suggested a negotiation meeting between Mr. Schumm and Mr. Brazier, and such suggestion was for the benefit of Mr. Brazier and Brazier Construction, and not for or in behalf of United Pacific Insurance Co.

When the lien had been filed, a meeting was held in May 1968 between David Brazier and the attorney and representatives of the subcontractor. It was agreed that if the lien against the retainage fund was released the contractor would pay approximately $19,000 to the subcontractor immediately and the balance of $62,380 when the retainage fund was released by the school district. The approximate $19,000 was paid, and the lien was released by a letter dated June 4, 1968, to the school district which stated, in part, that a lien had been filed for work performed by the subcontractor for the contractor, as principal, and that the United Pacific Insurance Company was the surety,

which had the bond relative to this work for Brazier. At this time, we wish to release the lien which we filed on said date relative to the Brazier Construction Co., Inc. and United Pacific Insurance Company. We have reached a settlement with Mr. Brazier regarding the back'Charges and monies held by his company.

*561 The surety did not receive a copy of the lien release but was advised by Mr. Bostick, of the insurance agency that acted on behalf of Mr. Brazier and the surety, that the difficulties had been resolved and the lien released. When the retainage fund was released by the school district to the contractor in August 1968, there were no liens filed against the project. The contractor did not pay the $62,380 balance due when the fund was received.

David Brazier died March 27, 1969. The contractor went out of business, and the claim filed by the subcontractor against the estate for $62,380 was denied. Finding of fact No. 12 of the trial court stated:

XII.
That if the plaintiff had not released its claim against the contract retainage fund being held by Bellevue School District #405, it would have been paid in full from this fund and any contingent liability of United Pacific Insurance Company on the account would have been extinguished. That the plaintiff prejudiced the position of United Pacific Insurance Company by voluntarily releasing its security interest in this fund, as a result of which release, the plaintiff’s account was not paid. That United Pacific Insurance Company neither waived its right to rely upon the release, nor agreed that the release was not applicable to both the bond claim and the claim against the retainage. That the release of the bond notice claim was equivalent to the failure to give notice as required by R.C.W. 39.08.030 and no other notice of claim was given by the plaintiff prior to or within 30 days from acceptance of the project.

The subcontractor assigns as error the dismissal of the surety, and the finding that the subcontractor prejudiced the surety’s position by releasing its interest in the retain-age fund. The subcontractor further objects to the finding that Mr. Bostick was not an agent of the surety when he arranged the meeting to negotiate the lien dispute and in finding that the subcontractor was estopped from asserting any claim against the bond after the lien was released. It is the contention of the subcontractor that Bostick was the *562 surety’s agent in the release negotiations and arrangement; and, therefore, the surety is not released, that the surety should be liable on its bond regardless of the lien release since it was a party to the release and that since the consideration to be performed by the contractor was never paid, the release should be rescinded.

Two applicable statutes are set forth for reference. RCW 39.08.030 reads in part as follows:

The bond mentioned in RCW 39.08.010 shall be in an amount equal to the full contract price agreed to be paid for such work or improvement, and shall be to the state of Washington, except in cases of cities and towns, in which cases such municipalities may by general ordinance fix and determine the amount of such bond and to whom such bond shall run: Provided,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SAUTER EX REL. SAUTER v. Houston Cas. Co.
276 P.3d 358 (Court of Appeals of Washington, 2012)
International Ultimate, Inc. v. St. Paul Fire & Marine Insurance
87 P.3d 774 (Court of Appeals of Washington, 2004)
IUI v. St. Paul Fire & Marine Ins. Co.
87 P.3d 774 (Court of Appeals of Washington, 2004)
Transamerica Insurance Company v. City Of Kennewick
785 F.2d 660 (Ninth Circuit, 1986)
Transamerica Insurance v. City of Kennewick
785 F.2d 660 (Ninth Circuit, 1986)
Deacy v. College Life Insurance Co. of America
607 P.2d 1239 (Court of Appeals of Washington, 1980)
National Bank v. Equity Investors
546 P.2d 440 (Washington Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
500 P.2d 1015, 7 Wash. App. 558, 67 A.L.R. 3d 914, 1972 Wash. App. LEXIS 1009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/inland-ryerson-construction-products-co-v-brazier-construction-co-washctapp-1972.