Fidelity & Deposit Co. v. Herbert H. Conway, Inc.

128 P.2d 764, 14 Wash. 2d 551
CourtWashington Supreme Court
DecidedSeptember 1, 1942
DocketNo. 28633.
StatusPublished
Cited by14 cases

This text of 128 P.2d 764 (Fidelity & Deposit Co. v. Herbert H. Conway, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. Herbert H. Conway, Inc., 128 P.2d 764, 14 Wash. 2d 551 (Wash. 1942).

Opinion

Jeffers, J.

This is an appeal by Fidelity & Deposit Company of Maryland (hereinafter referred to as Fidelity) from a decree of the superior court for Cow-litz county, entered on October 30, 1941. As appears from the notice, plaintiff appealed froin that part of the decree granting judgment against plaintiff and in favor of defendant General Roofing Company in the sum of $1,247.74, with interest at six per cent from September 28, 1939, together with an attorney’s fee of seventy-five dollars, and from that portion of the decree denying judgment in favor of plaintiff against school district No. 122, of Longview, Cowlitz county, Washington, for interest on the amount of the retained percentage withheld by the school district from the registry of the court.

On November 7, 1938, Herbert H. Conway, Inc. *553 (hereinafter referred to as Conway), as contractor, entered into an agreement with school district No. 122, for the construction of the R. A. Long gymnasium, designated as public works administration project No. Wash. 1574-F. The building was to be partially financed by funds from the PWA. Conway applied to Fidelity for a statutory performance bond. Such bond, conditioned as required by Rem. Rev. Stat., § 1161 [P. C. § 9727], was issued by Fidelity on November 8, 1938, in the sum of $86,854, and, after acceptance by the school district, was placed on file as a public record in the office of the secretary of the school district.

Conway did not complete performance of its contract, and on September 28, 1939, Fidelity was notified by the district that Conway had defaulted and abandoned the work, and that the district had terminated the contract. Fidelity declining to complete the contract, the building was finished by the district. November 28, 1939, the school district, by resolution, accepted the work as a completed project as of October 27, 1939. At the time of the approval of the final estimate, the retained percentage held by the district, as provided in the contract and required by Rem. Rev. Stat, § 10320 [P. C. § 9727-1], was $13,249.40.

Fidelity, as surety on Conway’s performance bond, instituted this action against Conway, school district No. 122, and a number of creditors who had claims against Conway, among these creditors being General Roofing Company, Inc. The purposes of the action were to require the school district to pay into the registry of the court the retained fund held by it; to require all claimants against such fund or against the surety on the bond to establish their claims; to recognize Fidelity’s claim against such fund for labor and material claims which it had paid; and to require the court to make an equitable disbursement of the funds.

*554 No question is raised as to the right of Fidelity to bring this action. It alleged and proved an assignment from Conway to Fidelity, dated August 28, 1939, of all moneys due or to become due under the contract.

. It is alleged in the complaint that the action was brought for the benefit of all the creditors of the contractor who had legal and enforcible claims, and it admitted its liability as surety upon the bond, to all claimants for labor, material, and provisions, who had complied with the statute and filed the proper statutory notice. It is further alleged that various defendants, other than Conway and the school district, have claims which may be asserted against the fund and the bond.

We are not concerned in this action with any of the parties defendant other than General Roofing Company and the school district.

General Roofing Company filed an answer and cross-complaint, wherein it alleged that, on February 16, 1939, as subcontractor, it entered into a written agreement with Conway, as contractor, to perform certain work and furnish certain materials on the R. A. Long gymnasium; that it has fully complied with the agreement, but that the full contract price has not been paid. It was agreed that $1,247.74 was the balance due on the contract. It is further alleged that, although General Roofing Company did not file a claim in the exact form as required by Rem. Rev. Stat., § 1161, it had written a series of letters, which it claimed gave notice to the school board and Fidelity of its claim, and constituted a substantial compliance with § 1161, supra. It asked for judgment against Fidelity for the amount of its claim and interest.

The school district filed an answer and counterclaim, wherein it alleged that the retained percentage had to come from the PWA. It also alleged there were two *555 prior claims, one for overtime which the district had paid and which the PWA refused to satisfy, and one for demurrage, based upon the fact that the contract had not been completed on the date agreed and the contract provided for damages for such delay.

The trial court rendered judgment in favor of General Roofing Company and against Fidelity, finding that a sufficient notice had been filed by the Roofing Co. It denied Fidelity’s claim against the school district for interest. The claim for demurrage was waived before trial, and the court denied the district’s claim for overtime. Fidelity was given judgment against Conway.

The assignments of error are in admitting respondent Roofing Co.’s exhibit ten, which consisted of letters which form the basis for the statutory notice; in entering judgment in favor of the Roofing Co. against appellant surety and the retained percentage; and in refusing to charge the school district with interest at the legal rate on account of the retained percentage withheld by it from the date this suit was commenced.

The sole question presented on the appeal from the judgment in favor of General Roofing Company is: Did the Roofing Co. file a sufficient notice of its claim to meet the requirements of Rem. Rev. Stat., § 1161? It was admitted that the material was furnished, and the amount still unpaid was agreed upon. This controversy concerns the effect to be given the series of letters contained in exhibit ten.

The first letter, under date of August 12, 1939, was written by the Roofing Co. to the architect, Arch M. Torbitt, at Seattle, Washington. The material part of this letter reads as follows:

“For your information and as a matter of precaution, we are sending you a copy of our final invoice to Herbert H. Conway, Inc. on the R. A. Long Gym *556 nasium and Swimming Pool, P. W. A. Docket No. Wn. 1574-F.

“We thought you might want this as we understand the job. is completed and Conway’s final payment is being held to pay a few outstanding bills.”

A copy of this letter was sent to the superintendent of schools, at Longview.

On September 21, 1939, the Roofing Co. again wrote to Torbitt, at Seattle, asking him for the name of the bonding company which was finishing the job, so that the Roofing Co. could file a claim with the bonding company to protect its interest. Under date of September 23rd, the Roofing Co. was informed by Mr. Weatherby, resident architect, that the contractor’s bond had been written by Fidelity & Deposit Company of Maryland, and that John Whalley, of Seattle, was its agent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Breen v. Ethicon Inc
W.D. Washington, 2021
William J. Templeman Co. v. US Fidelity and Guar. Co.
739 N.E.2d 883 (Appellate Court of Illinois, 2000)
William J. Templeman Co. v. United States Fidelity & Guaranty Co.
317 Ill. App. 3d 764 (Appellate Court of Illinois, 2000)
Keller Supply Co. v. Lydig Construction Co.
789 P.2d 788 (Court of Appeals of Washington, 1990)
Foremost-McKesson Systems Division of Foremost-McKesson, Inc. v. Nevis
505 P.2d 1284 (Court of Appeals of Washington, 1973)
Inland-Ryerson Construction Products Co. v. Brazier Construction Co.
500 P.2d 1015 (Court of Appeals of Washington, 1972)
School District No. 1 Ex Rel. Lynch Co. v. Rushlight & Co.
375 P.2d 411 (Oregon Supreme Court, 1962)
Johnson Service Co. v. Roush
355 P.2d 815 (Washington Supreme Court, 1960)
Taylor v. Via
284 P.2d 211 (New Mexico Supreme Court, 1955)
In Re George & John Hurt
129 F. Supp. 94 (S.D. California, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
128 P.2d 764, 14 Wash. 2d 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-herbert-h-conway-inc-wash-1942.