State Construction Inc v. Hartford Fire Insurance Company

CourtCourt of Appeals of Washington
DecidedJanuary 13, 2020
Docket78753-5
StatusUnpublished

This text of State Construction Inc v. Hartford Fire Insurance Company (State Construction Inc v. Hartford Fire Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Construction Inc v. Hartford Fire Insurance Company, (Wash. Ct. App. 2020).

Opinion

IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON

STATE CONSTRUCTION, INC., a ) No. 78753-5-I Washington Corporation, ) ) DIVISION ONE Appellant, ) ) v.

CITY OF SAMMAMISH, a governmental ) entity, PORTER BROTHERS ) UNPUBLISHED OPINION CONSTRUCTION, INC., a Washington ) Corporation,

Defendants,

HARTFORD FIRE INSURANCE ) COMPANY, a corporation, Bond No. ) 52BCSDL1 582, ) Respondent. ) FILED: January 13, 2020

ANDRUS, J. — State Construction, Inc., a subcontractor on a public works

project, challenges the dismissal of its lien and bond claims. Because its claims

were untimely, we affirm.

FACTS

In May 2014, Porter Brothers Construction, Inc. contracted with the City of

Sammamish (City) to construct the Sammamish Community & Aquatic Center (the No. 78753-5-1/2

Project).1 The City and Porter Brothers entered into an American Institute of

Architects Standard Form Agreement between Owner and Contractor (AlA

Agreement). Under this agreement, Porter Brothers invoiced the City monthly, and

when the City paid the invoice, it retained five percent of the funds owed to Porter

Brothers, as required by RCW 60.28.011 ~2 A retainage fund totaling $1 ,351 ,472

is now on deposit in an escrow account at Heritage Bank pursuant to a retainage

agreement between Porter Brothers and the City.

Porter Brothers subcontracted with State Construction on June 10, 2014, to

perform certain excavation and utilities work. State Construction began this work

shortly thereafter.

Porter Brothers also obtained a payment and performance bond3 for the

value of the Project, $28 million, from Hartford Fire Insurance Company. On

October 12, 2015, Hartford filed a Uniform Commercial Code (UCC) financing

statement against Porter Brothers, attaching, as collateral for debts owed to

Hartford, Porter Brothers’ interest in any payments due to the contractor, including

monies to which it might be entitled from retainage funds.

1 The Project involved the construction of a 69,000 square foot building with a 6-lane, 25-yard lap pool and other spaces, a parking structure and surface parking lot, and an access loop road. 2 RCW 60.28.011(1)(a) required the City to hold back a contract retainage not to exceed five

percent of the moneys earned by the contractor and to deposit the retained funds into a trust fund for the protection and payment of claims and state taxes and penalties. This is commonly referred to as a retainage fund. ~ RCW 39.08.010(1)(a) provides that on public improvement projects, contractors must post a performance and payment bond to ensure that they have the financial ability to perform all provisions of the contract; to pay all laborers, mechanics, subcontractors, and material suppliers; and to pay all state taxes, increases, and penalties. Contractor bonds guarantee that the contractor will perform the contract and will pay bills for labor and materials for which it contracts. 11 LEE R. Russ & THOMAS F. SEGALLA, COUcH ON INSURANcE 3D, § 163:10 (2005). If the contractor defaults, the surety agrees to pay an owner’s damages up to the limit of the bond and to pay claims of unpaid subcontractors and suppliers. Id. -2- No. 78753-5-1/3

Porter Brothers subsequently executed multiple “Irrevocable Assignment”

documents, in which it assigned to Hartford any right to payment it had on several

outstanding projects, including this Project. The assignment at issue here,

executed November 3, 2015, included the right to receive any portion of the

retainage funds held by the City:

FOR VALUE RECEIVED, the undersigned, Porter Brothers Construction, Inc., hereby irrevocably assigns, transfers and sets . . .

over to Hartford Fire Insurance Company. all Contract Funds of. .

any nature, including, but not limited to, progress payments, earned or unearned funds, change orders, extras, claims of any nature, retainages, with all the interest accruing thereon, and whether said Contract Funds are due now or in the future under the contract . .

[for the Project].

The City determined that the Project was “substantially complete” on April

1, 2016.~ The building was operational at that point and, according to the City,

punch list items5 were completed thereafter. State Construction completed punch

list items in June 2016.

At some point around this time, Porter Brothers experienced financial

difficulty and notified the City it was abandoning the contract because it was unable

to complete the work. After Porter Brothers’ voluntary default, Hartford stepped in

~ Although the record does not contain a complete copy of the City’s AlA Agreement with Porter Brothers, they executed the AlA Standard Form of Agreement Between Owner and Contractor, Document Al 01-2007, which, in section 9.1.2, incorporated by reference AlA Document A201- 2007, General Conditions of the Contract for Construction (General Conditions). Under paragraph 9.8.1 of the General Conditions, “substantial completion” is defined as “the stage in the progress of the Work when the Work . is sufficiently complete . . .so that the Owner can occupy or utilize the . .

Work for its intended use.” WERNER SABO, LEGAL GUIDE TO AlA DOCUMENTS § 4.56 SUBSTANTIAL COMPLETION: ¶9.8, at ¶9.8.1 (6th ed. 2019); see also I JONATHAN J. SWEET, SWEET ON CONSTRUCTION INDUSTRY CONTRACTS: MAJOR AlA DOCUMENTS § 15.14, at 627-28 (5th ed. 2009). ~ Under paragraph 9.8.2 of the General Conditions, when the Contractor considers the work substantially Complete, the Contractor submits a list of items needing to be Corrected before final payment. LEGALGUIDETOAIADOCUMENTS § 4.56 SUBSTANTIAL COMPLETION: ¶ 9.8, at~T 9.8.2. This list is known as the punch list. SWEET ON CONSTRUCTION INDUSTRY CONTRACTS: MAJOR AlA DOCUMENTS § 15.14, at 628.

-3- No. 78753-5-1/4

and paid certain debts, including monies owed to union trust funds for employee

fringe benefits and dues, and materials and supplies furnished by various

companies.

The City stated in discovery that landscaping work was completed on

August 31, 2016. The landscaping subcontractor testified that it completed its

punch list work in November 2016. The City received as-built drawings on January

13, 2017. Porter Brothers indicated that the last subcontractor to perform services

on the Project was Milne Electric, which completed its work on January 19, 2017.

In discovery, the City stated that “Porter Brothers, by and through its

subcontractors, was performing work under the contract through February 2017,

of which the City has no[] specific knowledge. After February 21, 2017, warranty

work was completed.”6

On February 21, 2017, the City’s council passed a resolution recognizing

the “[P]roject was substantially completed by the contractor on April 1, 2016,”

accepting the Project as officially complete, and authorizing the contract closure

process. The City filed a notice of completion with the state agencies, pursuant to

RWC 60.28.051, on April 13, 2017, listing the “Date Work Completed” as

“4/1/2016,” and the “Date Work Accepted” as “2/21/2017.”

On March 27, 2017, State Construction filed with the City a notice of a lien

claim against the retainage fund and notified Hartford of its claim against the bond

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
Shope Enterprises, Inc. v. Kent School District
702 P.2d 499 (Court of Appeals of Washington, 1985)
Thompson v. Peninsula School District No. 401
892 P.2d 760 (Court of Appeals of Washington, 1995)
Jacobsen v. City of Seattle
658 P.2d 653 (Washington Supreme Court, 1983)
Johnson Service Co. v. Roush
355 P.2d 815 (Washington Supreme Court, 1960)
Keller Supply Co. v. Lydig Construction Co.
789 P.2d 788 (Court of Appeals of Washington, 1990)
Airefco, Inc. v. Yelm Community Schools No. 2
758 P.2d 996 (Court of Appeals of Washington, 1988)
Levinson v. Linderman
322 P.2d 863 (Washington Supreme Court, 1958)
Geschwind v. Flanagan
854 P.2d 1061 (Washington Supreme Court, 1993)
Guillen v. Contreras
238 P.3d 1168 (Washington Supreme Court, 2010)
Housing Authority of City of Seattle v. Bin
260 P.3d 900 (Court of Appeals of Washington, 2011)
City of Redmond v. Moore
91 P.3d 875 (Washington Supreme Court, 2004)
AMER. SAF. CAS. INS. CO. v. City of Olympia
174 P.3d 54 (Washington Supreme Court, 2007)
Hisle v. Todd Pacific Shipyards Corp.
93 P.3d 108 (Washington Supreme Court, 2004)
HOUSING AUTHOR. OF CITY OF EVERETT v. Kirby
226 P.3d 222 (Court of Appeals of Washington, 2010)
Kinskie v. Capstin
722 P.2d 876 (Court of Appeals of Washington, 1986)
National Blower & Sheet Metal Co. v. American Surety Co.
248 P.2d 547 (Washington Supreme Court, 1952)
State, Dept. of Ecology v. Campbell & Gwinn
43 P.3d 4 (Washington Supreme Court, 2002)
Seattle Plumbing Supply Co. v. Maryland Casualty Co.
276 P. 552 (Washington Supreme Court, 1929)
Fidelity & Deposit Co. v. Herbert H. Conway, Inc.
128 P.2d 764 (Washington Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
State Construction Inc v. Hartford Fire Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-construction-inc-v-hartford-fire-insurance-company-washctapp-2020.