Levinson v. Linderman

322 P.2d 863, 51 Wash. 2d 855, 1958 Wash. LEXIS 510
CourtWashington Supreme Court
DecidedMarch 7, 1958
Docket33974
StatusPublished
Cited by27 cases

This text of 322 P.2d 863 (Levinson v. Linderman) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levinson v. Linderman, 322 P.2d 863, 51 Wash. 2d 855, 1958 Wash. LEXIS 510 (Wash. 1958).

Opinions

Foster, J.

The United States Fidelity and Guaranty Company appeals from a judgment subordinating its claim to moneys in the court’s registry, representing the final payment on school construction contracts, to the claims of respondent Victor Osina Company, a judgment creditor, and respondent The National Bank of Commerce of Seattle, a contract creditor, whose assignment caveat was filed in the office of the secretary of state.

On March 22, 1953, the Grays Harbor county consolidated school district No. 97 executed separate contracts for the construction of a school building and teachers’ cottage with the L. & L. Construction Company, a partnership. On the same day, the contractor filed separate statutory performance bonds (RCW 39.08.010), on which the United States Fidelity and Guaranty Company was surety. Thereafter, the contractor started the construction.

On July 29, 1953, respondent The National Bank of Commerce of Seattle filed in the office of the secretary of state a statutory notice (RCW 63.16.020) that the contractor intended to assign accounts receivable to it. On April 19, 1954, the bank loaned the contractor fifteen thousand dollars upon its promissory note, secured by an assignment of a single progress payment. Neither the school district nor the surety was advised of the assignment. The note remains unpaid.

On July 7, 1954, the school board’s architect advised the board that the contractor had breached its contract in four particulars. On the following day, July 8, 1954, the school board, by resolution, found the contractor in default in the particulars specified by the architect and gave the contractor written notice thereof, and, at the expiration of the contractual ten-day grace period, demanded the completion [857]*857of the buildings by the surety under its bond, which it did at a cost of $89,159.70.

The application for the performance bond provides, among other things, that, in case of the default of the contractor, the surety shall have the right to complete the contract at the expense of the principal.

The supplemental special conditions of the contract 2 require the contractor to furnish proof of payment of all bills before final payment; otherwise, the school district may itself pay the bills. Both construction contracts, which are in identical form, provide, in the event of the contractor’s default, the school district may itself complete the work or employ others to do it, and take and use the contractor’s equipment and materials for that purpose, in which event no further money shall be due the contractor unless a surplus exists after payment of all expenses.3

Respondents Dave Levinson and Victor Osina, doing business as the Victor Osina Company, obtained a judgment [858]*858against the contractor for $3,413.54, and thereafter, on October 24,1955, served a writ of garnishment upon the school district, which answered; but, by stipulation of the parties, the unpaid balance on the construction contracts of $62,-200.29 was deposited in the court’s registry and the school district dismissed.

By stipulation of the parties, the court retained sufficient funds in its registry to satisfy the claims of both respondents, but released the balance to the surety.

Briefs were submitted, and, subsequently, the trial court, in a memorandum opinion, determined that the respondents had priority. The court’s thesis was that, while the plans and specifications prohibited the assignment to the bank in very specific terms, such were not part of the contract; therefore, having filed its caveat in the office of the secretary of state to accept assignments from the contractor under the accounts receivable act, and because the surety failed to do so, the bank’s claim was adjudged superior to that of the surety. The decision is fundamentally erroneous because the act has no application.

The contracts for both the construction of the school building and the teachers’ cottage contain the following provision:

“First. The Contractor under the direction and to the satisfaction of Architect Charles A. Baylon, acting under this contract as agent of the said Owner, shall and will provide all the materials and perform all the work mentioned in the specifications and shown on the drawings prepared by the said Architect for construction of a Teachers’ Cottage at Lake Quinault, Grays Harbor, State of Washington, . . . which drawings and specifications are identified by the signature of the parties hereto.” (Italics ours.)

The performance bond itself makes the contract, and the plans and specifications, a part of the bond by reference.

It is beyond cavil that the contractor defaulted in the performance of his contract, because of which the school board terminated the contract and called upon the surety to complete the buildings pursuant to the performance ■bond, which it did at a very substantial loss.

[859]*859 The general conditions of the contract and the supplemental special conditions contained in the plans and specifications prohibit the assignment in unmistakable terms; but the respondents contend, and the trial court found, that such were not part of the contract. We hold otherwise, and that all the documents were executed simultaneously and are but one contract.

Although there were separate documents, the two contracts, the two performance bonds, and the plans and specifications were all executed at the same time as part of one transaction and constitute a single contract. The bank and the judgment creditor contend that the reference to the plans and specifications in the two contracts is insufficient to make the plans and specifications a part of the contract. We decide otherwise. The applicable rule of law is stated in 17 C. J. S. 714, § 298, as follows:

“As a general rule, sometimes by reason of express statutory provision, where several instruments are made as part of one transaction, they will be read together, and each will be construed with reference to the other. This is true, although the instruments do not in terms refer to each other.”

Our decisions are in accord. Paine-Gallucci, Inc. v. Anderson, 41 Wn. (2d) 46, 246 P. (2d) 1095; Standring v. Mooney, 14 Wn. (2d) 220, 127 P. (2d) 401; State ex rel. Noble v. Bowlby, 74 Wash. 54, 132 Pac. 723.

This is not an ordinary contract, but a printed form copyrighted by the American Institute of Architects, designed for the specific purpose of making all documents one contract. The definition is unmistakable:

“ (a) The Contract Documents consist of the Agreement, the General Conditions of the Contract, the Drawings and Specifications, including all modifications thereof incorporated in the documents before their execution. These form the Contract.”

Under such circumstances, although the documents are physically separate, they constitute a single contract. This conclusion was reached under the identical form of contract in Valley Constr. Co. v. City of Calistoga, 72 Cal. App. (2d) 839, 165 P. (2d) 521.

[860]*860We said in Young v. Borzone, 26 Wash. 4, 18, 66 Pac. 135, 421:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montes v. National Buick GMC
2024 UT 42 (Utah Supreme Court, 2024)
Hartford Fire Ins. Co. v. Columbia State Bank
Court of Appeals of Washington, 2014
Hartford Fire Insurance v. Columbia State Bank
334 P.3d 87 (Court of Appeals of Washington, 2014)
In Re Plitt Amusement Co. of Washington, Inc.
233 B.R. 837 (C.D. California, 1999)
Boyd v. Davis
897 P.2d 1239 (Washington Supreme Court, 1995)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
Portland Electric & Plumbing Co. v. City of Vancouver
627 P.2d 1350 (Court of Appeals of Washington, 1981)
Cordell v. Regan
598 P.2d 416 (Court of Appeals of Washington, 1979)
Washington Trust Bank v. Circle K Corp.
546 P.2d 1249 (Court of Appeals of Washington, 1976)
Turner v. Wexler
538 P.2d 877 (Court of Appeals of Washington, 1975)
Lynch v. Higley
510 P.2d 663 (Court of Appeals of Washington, 1973)
Diamond Parking, Inc. v. City of Seattle
479 P.2d 47 (Washington Supreme Court, 1971)
Green River Valley Foundation, Inc. v. Foster
473 P.2d 844 (Washington Supreme Court, 1970)
Boman v. Austin Co.
469 P.2d 199 (Court of Appeals of Washington, 1970)
Rocks v. Brosius
217 A.2d 531 (Court of Appeals of Maryland, 1966)
Guthrie Investments, Inc. v. Bennett
388 P.2d 955 (Washington Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
322 P.2d 863, 51 Wash. 2d 855, 1958 Wash. LEXIS 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levinson-v-linderman-wash-1958.