Danais v. M. De Matteo Const. Co.

102 F. Supp. 874, 1952 U.S. Dist. LEXIS 4814
CourtDistrict Court, D. New Hampshire
DecidedJanuary 23, 1952
Docket1:04-adr-00003
StatusPublished
Cited by18 cases

This text of 102 F. Supp. 874 (Danais v. M. De Matteo Const. Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danais v. M. De Matteo Const. Co., 102 F. Supp. 874, 1952 U.S. Dist. LEXIS 4814 (D.N.H. 1952).

Opinion

CONNOR, District Judge.

This is- an action by the trustee in bankruptcy of the New Hampshire Building and Construction Company, Inc., a 'New Hampshire corporation (hereinafter referred to as the bankrupt), seeking to recover for the bankrupt estate $30,834.16, due as accounts receivable for work and labor performed on three construction contracts for De- *875 Matteo Construction Company, a Massachusetts corporation (hereinafter referred to as DeMatteo). The Maryland Casualty Company, a Maryland corporation (hereinafter referred to as Maryland), which entered as intervener-defendant, claims title to said funds' as equitable lienor by right of subrogation under payment and performance bonds furnished to the bankrupt. Thereunder, it was compelled to meet the cost of completing defaulted work. It alternatively asserts its right to said funds by an assignment contained in the applications for the bonds executed by the bankrupt.

Without trial, the cause was submitted upon .an agreed statement of facts here summarized. For each of the three construction projects there was a written contract between the bankrupt and DeMatteo, DeMatteo being the principal contractor, and the bankrupt a subcontractor. In each instance a bond or bonds with the bankrupt as principal and Maryland as surety were executed in favor of DeMatteo as obligee. The agreed date of default common to all three projects is September 25, 1948. By letter dated September 23, 1948, DeMatteo notified Maryland of the defaults, and thereafter, on September 28, notice of defaults was given to Maryland by the bankrupt. Voluntary petition in bankruptcy was filed October 20, 1948.

The 'first contract, referred to as the “Gate Blouse Job,” a federal dam project in West Peterborough, New Hampshire, was entered into April 20, 1948. On April 21, a performance bond and a payment bond, each in the amount of $85,000, were executed by Maryland pursuant to written application by the bankrupt. The construction contract called for monthly payments for work accepted and for a ten percent retainage by DeMatteo. At the time of default, the bankrupt had earned $18,397.92, and had been paid $10,221.98. By letter dated September 24, 1948, Maryland notified DeMatteo of the assignment contained in the bond application, and thereafter asserted its claim to unpaid funds by assignment and' otherwise. The contract price was $85,000; the balance of the contract price unpaid to the bankrupt at the time of default (earned and unearned) was $74,778.02. Upon completion of the work by Maryland, this amount was paid to it by DeMatteo. Maryland’s loss was $17,177.04 after paying cost of completion, back charges due DeMatteo (including payrolls advanced), unpaid bills, and penalties. The trustee claims under this contract $8,-175.94 ($18,397.92 earned, less $10,221.98 paid).

The second contract, entered into May 25, 1948, designated as the “Lynnfield-Wakefield Job,” was to do certain work on 'a highway project in Wakefield, Massachusetts. Previously, on May 24, the bankrupt, as principal, and Maryland, as surety, had executed a single payment and performance bond in the amount of $80,000, in favor of DeMatteo as obligee. This bond, like the previous bonds, was executed pursuant to an application therefor signed by the bankrupt on the same date. The contract called for bimonthly payments and a fifteen' percent retainage by DeMatteo. When the default occurred, the bankrupt had earned $58,645, and had been paid $38,823.81. As before, Maryland notified DeMatteo of the assignment contained in the bond application in connection with this project. The project was completed by DeMatteo, with which Maryland entered into a settlement agreement in the amount of $11,347.98, representing excess cost of completion, plus payrolls advanced by De-Matteo. In addition, Maryland paid $4,-.662.93, unpaid bills incurred by the bankrupt on this project prior-to default. The contract price was $97,064.25; .the 'balance of the contract price unpaid (earned and unearned) at the time of default was $58,-240.44, the latter amount being applied by DeMatteo to the cost of completion. The trustee’s .claim is in the sum of $19,821.19 ($58,645 earned, less $38,823.81 paid).

The third contract was the “West Peter-borough Highway Job,” entered into June 14, 1948, whereby the bankrupt was to do certain work in connection with a highway and bridge project at West Peterborough, New Hampshire. On the same day, payment and performance bonds were executed pursuant to application signed by the bankrupt. The contract called for payment for *876 work done in each estimate period “less customary retained percentage.” At. the time of default, the bankrupt had earned $2,960.43, and had been ipaid $123.40. By letter dated October 7, 1948, Maryland notified DeMatteo of the assignment contained in the bond application for this project. After completion by DeMatteo, Maryland entered into a settlement with it in the amount of $2,646.51, representing the excess cost of co.mpl.etion, plus payrolls advanced by DeMatteo. The contract price was $10,061.50; the balance of the contract price unpaid at the time of default (earned and unearned) was $9,938.10, which was applied by DeMatteo to the cost of completion. The loss incurred by Maryland was $2,764.17, including the payment of $117.66 incurred by the bankrupt prior to default. On this contract, the claim of the trustee is in the amount of $2,837.03 ($2,-960.43 earned, less $123.40 paid).

Although M. DeMatteo Construction Company is the sole defendant in the original complaint, all of the issues may be' concluded in determining the claim of the trustee and those of the intervener, Maryland Casualty Company. In its capacity as surety for the trustee’s predecessor, Maryland ' has incurred certain expense in undertaking to conclude one contract and in payment to DeMatteo Construction Company for the completion of the remaining two contracts. The funds to which the trustee and the intervener claim title were earned by the bankrupt but unpaid at the time of the defaults. The trustee maintains that such moneys are the property of the bankrupt estate, to be made availablé to meet the demands of all of the creditors. Maryland contends that, by virtue of the relationship of - principal and surety, it has an equitable right to such funds, in that it became subrogated to the rights of the beneficiary, DeMatteo. Alternatively, it maintains that it is entitled to these moneys under an alleged assignment in the applications for the bonds. The issue is whether the trustee’s claim is to be recognized as superior to that of the intervener’s asserted equitable right as surety and/or as that of assignee.

It is well settled that there inures to the surety on a contractor’s bond who completes upon default, or responds in .damages, an equitable right through subrogátion to the funds due its principal in the hands of the obligee. Prairie State National Bank v. United States, 164 U.S. 227, 17 S.Ct. 142, 41 L.Ed. 412; First National Bank of Seattle v. City Trust Co., 9 Cir., 114 F. 529; State ex rel. Southern Surety Co. v. Schlesinger, 114 Ohio St. 323, 151 N.E. 177, 45 A.L.R. 371; Labbe v. Bernard, 195 Mass. 551, 82 N.E. 688, 14 L.R.A.,N.S., 457 and note. And this is so, independent of an assignment. Hartford Accident & Inderimity Co. v. Coggin, 4 Cir., 78 F.2d 471, 477, 478; Lacy v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mickelson v. Aetna Casualty & Surety Co.
452 F.2d 1219 (Eighth Circuit, 1971)
In The Matter Of J. V. Gleason Co., Inc.
452 F.2d 1219 (Eighth Circuit, 1971)
National Surety Corp. v. State National Bank of Frankfort
454 S.W.2d 354 (Court of Appeals of Kentucky (pre-1976), 1970)
Blumin v. Ellis
186 So. 2d 286 (District Court of Appeal of Florida, 1966)
Paul B. Emerick Co. v. Wm. Bohnenkamp & Associates, Inc.
409 P.2d 332 (Oregon Supreme Court, 1965)
Michigan Fire & Marine Insurance v. Genie Craft Corp.
224 F. Supp. 636 (D. Maryland, 1964)
In re Collins & Kiser Construction Co.
204 F. Supp. 42 (S.D. Iowa, 1962)
Levinson v. Linderman
322 P.2d 863 (Washington Supreme Court, 1958)
In Re Webb
160 F. Supp. 544 (S.D. Indiana, 1958)
In re the William P. Bray Co.
127 F. Supp. 627 (D. Connecticut, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
102 F. Supp. 874, 1952 U.S. Dist. LEXIS 4814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/danais-v-m-de-matteo-const-co-nhd-1952.