Lacy v. Maryland Casualty Co.

32 F.2d 48, 1929 U.S. App. LEXIS 3696
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 9, 1929
Docket2783, 2784
StatusPublished
Cited by41 cases

This text of 32 F.2d 48 (Lacy v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lacy v. Maryland Casualty Co., 32 F.2d 48, 1929 U.S. App. LEXIS 3696 (4th Cir. 1929).

Opinion

PARKER, Circuit Judge.

The appeals in the above-entitled cases were taken from deerees awarding to the Maryland Casualty Company all of the funds due by the North. Carolina highway commission on account of certain road contracts. The other claimants were the Murchison National Bank, which hold assignments from the contractor, and the administratrix of H. D. Lacy, who claimed a ono-half interest in the profits realized from one of the contracts. For convenience we shall discuss the cases together.

*50 The facts are as follows; One C. W. Laey was awarded a number of contracts by the North Carolina highway commission for the construction of roads in Eastern North Carolina. Among these was contract No. 151 covering a road project in Hyde county and contract No. 378 covering a project in Pender county. The contracts were in the usual form, providing for progress payments on estimates of work accomplished, with retention by the commission of 15 per cent, of the amount of the estimates until the completion of the entire work. The casualty company executed a bond in the ease of each contract guaranteeing its performance by the contractor, having previously obtained from him an application in which he agreed to. indemnify the company against loss, and which contained, among other provisions, the following, which are the ones pertinent to the controversy here involved, viz.:

• “Second. * * * And for the better protection of the said company the undersigned do, as of the date hereof, hereby assign, transfer and convey to it, the said Maryland Casualty Company, all our right, title and interest in and to all the tools, plant and equipment and materials of every nature and description that we may now or hereafter have upon said work, or in, on or about the site thereof, including as well materials purchased for or chargeable to said contract which may be in process of construction, on storage elsewhere, or in transportation to said site; hereby assigning and conveying also all our rights in and to all sub-contracts, which have been or may hereafter be entered into, and the materials embraced therein, and authorizing and empowering said company, its authorized agents or attorneys, to enter upon and take possession of said tools, plant, equipment, materials and sub-contracts, and enforce, use and enjoy such possession upon the' following conditions, viz.: This assignment shall be in full force and effect as of the date hereof, should the undersigned fail or be unable to complete the said work in accordance with the terms of the contract covered by said bond, or in event of any default on the part of the undersigned under the said contract. In event of claim, or default under the bond hei'ern applied, for all payments specified m the above mentioned contract to be withheld by the obligee until the completion of the work, shall as soon as the work is completed, fbe paid to the company — and this covenant shall operate as am assignment thereof, and the residue, if any, after reimbursing the company as aforesaid, shall be paid to the undersigned after all liability of the company has ceased to exist under the said bond, and the company shall at its option be subrogated to all the rights, properties and interest of the undersigned in said contract or contracts. (Italics ours.)
• •••••••
“Eighth. That these covenants and also all collateral security, if any, at any time deposited with the company concerning the said bond or any other former or subsequent bonds executed for us or at our instance, shall, at the option of the company, be available in its behalf and for its benefit as well concerning the bond or undertaking hereby applied for, as also concerning all other former or subsequent bonds and undertakings executed for us or for others at our request.”

On May 24, 1923, Lacy had become insolvent and was unable to obtain funds to carry on the work on contracts 151 and 378. Thereupon he entered into a contract with the casualty company under which the latter agreed to advance the money necessary to complete the contracts, taking as security his road working equipment and certain corporate stock. This contract further provided that the money to be advanced by the casualty company thereunder should be under the joint control of Lacy and the company and should not be paid out except upon the counter signature of its representative, and that all moneys which might be received from the highway commission, “including current estimates and retained percentages,” should be deposited in the same fund and disbursed in like manner. The highway commission was promptly advised of the making of this contract and was notified to make no further payments on the road contracts except upon the order of the casualty company.

After the execution of this contract, Lacy continued for several months to prosecute the work under the contracts in his own name but with the funds furnished by the casualty company. Finally, however, the company took over the contracts and completed performance in its own name. No formal notice of default under any of the contracts was ever given to the company by the highway commission. On contract 151, which was nearly completed when taken over, a profit of something over $10,000 was realized.' On project 378, however, a loss was sustained amounting to $139,000, and on all of the contracts taken together the loss far exceeded the profits.

The claim of the casualty company arises out of the furnishing of funds for the completion of the contracts, its contention being *51 that as surety it is entitled to priority over all other assignees and to' treat all of the contracts as one contract and apply the profits realized on No. 15.1 against the losses sustained on the others. The claim of the Murchison National Bank is based upon assignments executed to it by Lacy on March 31, 1923, in which he assigned all moneys then dne or thereafter to become due on contracts 151 and 378. On the strength of these assignments, the bank loaned him money to pay for labor and material, and under them it .claims the May estimates on both contracts, amounting to $1,543.39 and $6,631.92, respectively. It appears that the highway commission was promptly notified of the assignments, and in acknowledging receipt of the notice the auditor of the commission advised that it would “be governed accordingly.”

The claim of the administratrix of H. D. Lacy relates only to contract 151. The parties have stipulated, and the judge below has found as a fact, that after the execution of that contract C. W. Lacy, the contractor, agreed with his brother H. D. Lacy to pay him $50 per week as salary for services on the project covered thereby, and upon its completion to give Mm one-half of the profits of the contract as additional compensation. One-half of the profits amounted to $5,337.-40 and the administratrix of H. D. Lacy claims this under the agreement.

The District Judge denied the claims both of the bank and of the administratrix and held that the casualty company had a prior claim on all of the funds duo by the highway commission on both contracts. We think, however, that different principles are applicable in the case of the funds derived from contract 151, on which a profit was realized, from those which apply in the ease of the funds due on the other contract, and shall accordingly discuss them separately.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alaska National Bank of the North v. Gwitchyaa Zhee Corp.
639 P.2d 984 (Alaska Supreme Court, 1981)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
Stroud Oil Reclaiming Co. v. Community State Bank of Bristow
1970 OK 196 (Supreme Court of Oklahoma, 1970)
Hartford Accident and Indemnity Co. v. Long
245 A.2d 800 (Court of Chancery of Delaware, 1968)
Western Casualty & Surety Co. v. Brooks
362 F.2d 486 (Fourth Circuit, 1966)
Aetna Casualty & Surety Co. v. Harvard Trust Co.
181 N.E.2d 673 (Massachusetts Supreme Judicial Court, 1962)
Hartford Accident & Indemnity Co. v. State Public School Building Authority
26 Pa. D. & C.2d 717 (Dauphin County Court of Common Pleas, 1961)
National Surety Corporation v. Fisher
317 S.W.2d 334 (Supreme Court of Missouri, 1958)
Levinson v. Linderman
322 P.2d 863 (Washington Supreme Court, 1958)
Colusa-Glenn Production Credit Ass'n v. Phoenix Insurance
145 F. Supp. 844 (N.D. California, 1956)
COLUSA-GLENN PRODUCTION CR. ASS'N v. Phoenix Ins. Co.
145 F. Supp. 844 (N.D. California, 1956)
In re Cline Construction Co.
141 F. Supp. 696 (E.D. Kentucky, 1956)
United States v. Crosland Const. Co.
120 F. Supp. 792 (E.D. South Carolina, 1954)
American Fidelity Co. v. Delaney
114 F. Supp. 702 (D. Vermont, 1953)
Danais v. M. De Matteo Const. Co.
102 F. Supp. 874 (D. New Hampshire, 1952)
Massachusetts Bonding & Ins. v. Fago Const. Corp.
82 F. Supp. 619 (D. Maryland, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
32 F.2d 48, 1929 U.S. App. LEXIS 3696, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lacy-v-maryland-casualty-co-ca4-1929.