Western Casualty & Surety Co. v. Brooks

362 F.2d 486, 9 Ohio Misc. 61
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 1, 1966
DocketNo. 10236
StatusPublished
Cited by11 cases

This text of 362 F.2d 486 (Western Casualty & Surety Co. v. Brooks) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Casualty & Surety Co. v. Brooks, 362 F.2d 486, 9 Ohio Misc. 61 (4th Cir. 1966).

Opinion

Jones, S. J.

The question presented on this appeal is the right of a surety on two public construction contracts, both performed by the same contractor, to set off losses incurred on one bond with the excess realized on the other. In the bankruptcy proceedings against the contractor, the referee held that the surety had no right of setoff, and therefore should surrender to the trustee the $23,882.26 excess realized on one con[63]*63tract. The District Court affirmed and this appeal followed. We affirm.

The facts in this case, as stipulated by the parties, are briefly as follows: In 1958 the bankrupt, Bruns Coal Company, Inc., contracted with the state of Ohio to perform two separate road construction projects — Projects 24 and 37. Each contract was signed independently of the other and covered work in separate counties.1 As a prerequisite to entering into these two contracts, the contractor was required by state statute2 to execute a separate performance-payment bond for each contract. This was done, with the appellant becoming surety on both bonds.3 In the applications for these bonds, the contractor-principal assigned to the surety as collateral security all sums in the hands of the obligee-state and due to the contractor at the time of any breach, or which might become due thereafter. These agreements further provide that the assigned funds could be used by the surety to offset losses incurred on the individual bond or on any other bond between the two parties. The assignments were never recorded as required by state law.4

By the end of 1960 the contractor had completed all required construction work on the two projects. However, it had failed to pay certain subcontractors, laborers, and materialmen, [64]*64who, in accordance with state law,5 filed mechanic’s liens with the state notifying it of the debts owed by the contractor. This statute further provided that the state upon receipt of these lien notices, was to withhold all subsequent payments becoming due to the contractor until the laborers and materialmen had been paid. If payment did not follow, the state was to make payments directly to the laborers and materialmen out of the retained funds. If this latter course was not followed, the statute permits the unpaid parties to recover against the state up to, but not exceeding, the balance due to the contractor.

Upon receipt of these various liens on the two projects, the state withheld all further payments to the contractor. The surety then proceeded to satisfy these various claims as it was obligated by the bond agreement and by state statute.6 By August 1962 all claims arising under both contracts had been paid by the surety.

In December 1960, the contractor directed the state, by letter, to send all future payments falling due on each contract to the surety. This was done, and between December 8, 1961, and June 11, 1962, the surety received a total of $103,414.87 from the state: $87,141.69 on Project 24 and $16,273.18 on Project 37. The payments the surety was required to make on Project 24 totaled $63,259.43, thereby leaving an excess on that bond of $23,882.26. However, the payments on Project 37 totaled $160,702.45, thereby causing a loss of $144,429.27.

An involuntary petition in bankruptcy was filed against the contractor on March 15, 1962. This date was within 4 months of the receipt of the first payments by the surety from the retained funds in the hands of the state. The contractor was adjudged a bankrupt on April 9, 1962, and the trustee in bank[65]*65ruptcy filed a petition for turnover of all the sums received hy the surety from the state — $103,414.87, claiming these payments were voidable preferences under Section 60 of the Bankruptcy Act.7

It was decided by the referee in bankruptcy that the assignments made to the surety in the bond applications, not having been recorded in accordance with state law, were invalid as against the trustee in bankruptcy. Section 70c of the Bankruptcy Act.8 The referee further held that the $103,414.87 in payments received by the surety within 4 months of the filing of the involuntary petition in bankruptcy were voidable preferences under Section 60 of the Bankruptcy Act, unless the equitable doctrine of subrogation could be made applicable. On this latter point, both the referee and the District Court agreed that subrogation was applicable on each bond to the extent of the claims made by laborers and materialmen on that particular bond. In other words, the surety was not permitted to apply the $23,882.26 in excess payments realized on Project 24 to offset either its legal or miscellaneous expenses on that project or its losses on Project 37.

[66]*66The surety has not appealed the decision holding the assignments invalid, or the determination that the payments were voidable preferences if subrogation is inapplicable to the $23,-882.26. Likewise the trustee in bankruptcy has not appealed the decision that the surety is legally entitled to $79,532.61 of the payments via subrogation. Therefore, the sole issue raised by this appeal is whether the appellant-surety is entitled to the $23,882.26 excess realized on the Project 24 bond, by way of subrogation.9

It is now settled law,10 since the decision in Pearlman v. Reliance Ins. Co. (1962), 371 U. S. 132, 9 L. Ed. 2d 190, 83 S. Ct. 232,11 that when a surety meets its obligations on a contract bond by paying the claims of the laborers and materialmen, it subrogates to whatever rights the owner (state), contractor, and laborers and materialmen had in the retained funds, “to the extent necessary to reimburse it.”12 And since this “equitable [67]*67right”13 of the surety to the fund relates hack to the date of the surety bond,14 it entitles the surety to priority in payment over all subsequent lienholders and general creditors.15 By the surety’s acquiring this equitable interest in the retained funds, “this property interest of the surety never became a part of the bankruptcy estate to be administered, liquidated, and distributed to general creditors of the bankrupt.16

In the only pronouncement by the Supreme Court of Ohio related to this question, State, ex rel. Southern Surety Co. v. Schlesinger (1926), 114 Ohio St. 323, 151 N. E. 177, 45 A. L. R. 371, it was held that the surety on a performance bond, upon completing the performance of the contract (not the payment of claims by laborers and materialmen) was subrogated to the rights of the state in the retained funds. It may therefore be inferred that the Ohio Supreme Court would also apply the doctrine of subrogation where the surety acts on the payment bond to pay off the claims of laborers and materialmen.17

The right of subrogation is an equitable doctrine,18 designed to perform substantial justice. “ [I]t goes no farther than the strict demands of equity and justice demand.” First Nat. Bank of Seattle v. City Trust, Safe Deposit & Surety Co. (9 Cir. 1902), 114 F. 529, 533.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
362 F.2d 486, 9 Ohio Misc. 61, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-casualty-surety-co-v-brooks-ca4-1966.