Ram Construction Co. v. American States Insurance

749 F.2d 1049
CourtCourt of Appeals for the Third Circuit
DecidedDecember 6, 1984
DocketNo. 84-3146
StatusPublished
Cited by21 cases

This text of 749 F.2d 1049 (Ram Construction Co. v. American States Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ram Construction Co. v. American States Insurance, 749 F.2d 1049 (3d Cir. 1984).

Opinion

OPINION OF THE COURT

WEIS, Circuit Judge.

In this appeal we determine that the bankruptcy judge’s ruling — that two separate agreements existed between a contractor and owner — was a matter of contract construction subject to plenary review. Although the district court used the clearly erroneous test, the error is not reversible because under either standard the result here is the same. We also conclude that the bankruptcy judge did not err in ruling that a surety’s right of equitable subrogation does not include the right to use profits from a post-bankruptcy contract to offset losses on pre-bankruptcy jobs. Accordingly, we will affirm.

In two consolidated adversary proceedings, the bankruptcy judge determined that liens of a surety should be avoided and denied it priority. The district court on appeal affirmed the orders of the bankruptcy judge.

Ram Construction Company filed for reorganization under Chapter 11 of the Bankruptcy Code on January 21, 1983. At that time, among other construction jobs, Ram was engaged in the removal of a landslide on Saw Mill Run Boulevard in Pittsburgh, Pennsylvania (Slide I), pursuant to a contract with the City dated December 8, 1982. As it had for other projects Ram was performing for the City, American States furnished a performance bond, as well as a labor and material bond, for the Slide I contract.

On February 16, 1983, about three weeks after the filing of the petition, a large rock slide occurred at the project site on the Boulevard (Slide II). There were two fatalities, and the road was closed, causing severe traffic congestion. The City was anxious to remove all debris from the roadway, to stabilize the hillside, and to reopen the Boulevard promptly. The Director of Public Works requested a proposal from Ram to undertake the work.

On February 21, 1983, Ram responded to the City by a letter agreeing to clear the road, but at substantially increased unit prices on all categories of earth and rock removal. Part of the increase was the result of the City’s insistence that the work proceed 24 hours a day, seven days per week until completion. To facilitate the work the road would remain closed for the duration of the project, a change from the Slide I contract under which traffic had to be maintained.

The Director of Public Works then asked City Council for “Authorization and Approval for Extra Work on the Saw Mill Run Boulevard rock slide.” After receiving that approval, the Department of Public Works issued an “Authorization for Additional Work,” utilizing the City Controller’s number for the original contract. A new written contract between the City and Ram was not prepared nor were new surety bonds executed.

Under the provisions of the Slide I contract, the City could have required Ram to perform “additional” work at the same unit prices, unless the amount of added work exceeded twenty-five percent of the original contract. The bankruptcy judge found that proviso inapplicable to the situation presented here because of the substantial increase in work required by the second slide.

[1052]*1052American States presented evidence that it had suffered losses on other contracts that Ram had performed for the City, e.g., the “sewer job,” and that a profit was expected on Slide II. With these facts established, the surety contended that it was entitled to offset its earlier losses against the profits earned on Slide II.

The bankruptcy judge concluded that new contract rights and accounts had been created because the amount of work as well as the unit prices were greatly increased and the around the clock working conditions were significantly different from the original undertaking. That the City, for its convenience and for purposes of internal administration, labeled the project as “additional work” was not dispositive of whether there were two contracts or one. Consequently, the subrogation interest of American States, created by payments made in connection with pre-bankruptcy contracts, did not carry through to the Slide II project begun after the filing of the petition.

The district court affirmed the bankruptcy judge’s finding that two separate contracts had been executed and stated, “the factual finding of the bankruptcy court was not clearly erroneous; the court correctly construed the intent of the parties in determining the existence of distinct contracts.”

In this court, American States contends that the district court erred in applying the clearly erroneous standard to review the bankruptcy judge’s conclusion that there were two separate contracts, and that both forums erred in denying setoff rights. Ram argues that because the Slide II agreement was post-petition, there was no right of setoff against pre-petition obligations to which the surety’s subrogation rights could apply.

I

We turn first to the surety’s contention that the district court applied an inappropriate standard of review.

The distinction between issues of fact and law in contract disputes is not always sharply defined. When the controversy is over “historical” or “narrative” facts, the clearly erroneous rule is appropriate. For example, in this case, the price agreed on, the amount of work to be performed, and the terms of performance are narrative facts. As to those matters, the surety admits “there is little, if any, dispute as to the facts of this case, and American States does not contend that the factual findings are clearly erroneous, but many of the legal conclusions drawn from these findings are in error.”

When the question is one of contract interpretation, the difference between factual and legal conclusions is often confused with the assignment of functions between court and jury. When the agreement is in writing, ambiguous terms are interpreted by the jury, unambiguous ones by the court. Although this latter function is sometimes said to be a legal one, see Brokers Title Co., Inc. v. St. Paul Fire & Marine Ins. Co., 610 F.2d 1174, 1178 (3d Cir.1979), commentators differ.

Some authorities maintain that all questions of contract interpretation are factual matters, some of which are entrusted to the jury in ordinary civil litigation (ambiguous writings), and others which are for resolution by the judge (unambiguous terms). See Community College of Beaver County v. Community College of Beaver County, Society of the Faculty (PSEA/NEA), 473 Pa. 576, 592, 375 A.2d 1267, 1275 (1977); RESTATEMENT (SECOND) OF CONTRACTS § 212 comment d (1981); 3 CORBIN ON CONTRACTS § 554 (1960); 4 WILLISTON ON CONTRACTS § 616 at 648-49, 660-63 (3d ed. 1961). This distribution of functions rests on outdated common law policy considerations, such as jury illiteracy and lack of respect for writings, as well as such continuing concerns as a judicial desire for uniformity. Meyers v. Selznick Co., Inc., 373 F.2d 218, 222 (2d Cir.1966); RESTATEMENT OF CONTRACTS 2d § 212; 4 WILLISTON ON CONTRACTS § 616.

[1053]*1053In instances of contract interpretation, therefore, assignment to judge or jury does not of itself determine the standard of review to be applied on appeal. Interpretation by a trial court of a factual matter is reviewable on a clearly erroneous basis, rather than as a plenary one.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.K. v. Prestige Academy
D. Delaware, 2020
Transamerica Insurance v. United States
37 Cont. Cas. Fed. 76,037 (Court of Claims, 1991)
Roe v. Operation Rescue
920 F.2d 213 (Third Circuit, 1990)
Herbert v. Federal National Mortgage Ass'n
102 B.R. 407 (E.D. Pennsylvania, 1989)
Herbert v. FEDERAL NAT. MORTG. ASS'N
102 B.R. 407 (E.D. Pennsylvania, 1989)
Smith v. Commercial Banking Corp. (In re Smith)
87 B.R. 329 (E.D. Pennsylvania, 1988)
In Re Beck Rumbaugh Associates, Inc.
84 B.R. 369 (E.D. Pennsylvania, 1988)
Kroblin Refrigerated Xpress, Inc. v. Pitterich
805 F.2d 96 (Third Circuit, 1986)
Schoenborn v. Boeing Co.
769 F.2d 115 (Third Circuit, 1985)
Wagman v. Carmel
601 F. Supp. 1012 (E.D. Pennsylvania, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
749 F.2d 1049, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ram-construction-co-v-american-states-insurance-ca3-1984.