Hartford Fire Insurance v. Columbia State Bank

334 P.3d 87, 183 Wash. App. 599
CourtCourt of Appeals of Washington
DecidedSeptember 9, 2014
DocketNo. 45320-7-II
StatusPublished
Cited by3 cases

This text of 334 P.3d 87 (Hartford Fire Insurance v. Columbia State Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Fire Insurance v. Columbia State Bank, 334 P.3d 87, 183 Wash. App. 599 (Wash. Ct. App. 2014).

Opinion

Melnick, J.

¶1 Hartford Fire Insurance Company appeals from the superior court’s grant of summary judgment dismissal of Hartford’s claims against Columbia State Bank and the superior court’s denial of Hartford’s summary judgment motion. Hartford had issued bonds for Waka Group Inc., a general contractor, and made payments under one bond when Waka defaulted on a project. Hartford argues that it was entitled to recover progress payment funds Columbia removed from Waka’s collateral control account because Waka had a contractual obligation to hold progress payments in trust for Hartford’s benefit to provide reimbursement for bond payments, and that Columbia knew or should have known the funds were held in trust. In the alternative, Hartford argues that it had an equitable lien on the progress payment funds that was superior to Columbia’s right to the funds.

[602]*602¶2 We hold that the contract between Hartford and Waka did not create an express trust and that Hartford did not possess an equitable lien on the progress payment funds. As a result, we hold that Hartford is not entitled to recover the funds from Columbia. We affirm the superior court’s summary judgment dismissal of Hartford’s claims.

FACTS

¶3 Hartford issued performance and payment bonds as surety for Waka’s construction contracts. On June 13, 2011, as partial consideration for this arrangement, Hartford and Waka executed a general indemnity agreement (Indemnity Agreement). The Indemnity Agreement included a “Trust Fund” provision, which stated:

If a Bond is Underwritten in connection with the performance of any contract, the entire contract price shall be dedicated to the satisfaction of the obligations of the Bond and this Agreement. All money paid or any securities, warrants, checks or evidences of debt given under contracts relating to or for which a Bond has been issued shall be impressed with a trust for the purpose of satisfying the obligations of the Bond Underwritten for said contract and this Agreement and shall be used for no other purpose until all such obligations have been fully satisfied.

Clerk’s Papers (CP) at 13 (emphasis added).

¶4 Waka needed to obtain working capital to complete its projects. On June 14, 2011, Waka executed and delivered a commercial line of credit agreement and note (Note) along with a business loan agreement to Columbia. An addendum to the business loan agreement, titled “Control Account,” stated that Waka

shall deposit all cash, instruments and other proceeds received from the operation of [Waka’s] business into an account established with [Columbia] within two (2) business days after receipt of such amounts (the “Control Account”). [Columbia] is authorized to pay down the unpaid Loan balance, on a daily basis, from funds in the Control Account.

[603]*603CP at 245. At the same time, Waka executed and delivered a commercial security agreement to Columbia to provide collateral for the Note. The security agreement provided Columbia with a Uniform Commercial Code (UCC) article 9 security interest in Waka’s inventory, equipment, chattel paper, accounts, general intangibles, and the products and proceeds thereof, whether then owned or later acquired. On June 20, Columbia timely perfected its security interest in the collateral by filing a UCC financing statement.

¶5 In early 2012, Waka contracted with the General Services Administration (GSA) for a project on the Dalton Cache Border Station in Haines, Alaska (Dalton Project). On March 1, pursuant to the Indemnity Agreement, Hartford issued a performance bond and a payment bond for the Dalton Project.

¶6 For its projects, including the Dalton Project, Waka had automatic deposit payments made into its collateral control account with Columbia. Waka then used that money to pay its subcontractors and suppliers. The Note matured on May 30, 2012, and Waka failed to repay the loan evidenced by the Note. On or about June 18, Columbia met with Waka’s president and told him it was going to call Waka’s loan.

¶7 At approximately the same time, after learning that Waka would be unable to complete the project, Hartford began taking steps to take over and complete the Dalton Project pursuant to its obligations under the bonds. On June 20, Hartford notified the GSA that it would be completing the Dalton Project and requested that the GSA direct all future progress payments to Hartford. Also in mid-June, Waka notified the GSA that it would not be able to complete the Dalton Project.

¶8 On June 21, Waka sent the GSA a letter directing it to send all future payments for the Dalton Project to Hartford. The GSA agreed, but despite its attempts, it could not stop a progress payment in the amount of $103,410 from being deposited into Waka’s collateral control account with Co[604]*604lumbia. On that same day, Hartford sent Columbia a letter notifying Columbia of the trust fund language in its Indemnity Agreement with Waka. It instructed Columbia to hold the Waka funds in trust for the benefit of Hartford and other trust beneficiaries. However, Columbia had already applied the $103,410 GSA progress payment to Waka’s outstanding loan balance.1

¶9 On June 25, the GSA sent Hartford an official demand letter to complete the Dalton Project pursuant to its obligations under the performance bond. On July 13, Hartford and the GSA executed a takeover agreement for Hartford to complete the Dalton Project, and four days later Hartford made its first payment to subcontractors under its bond obligations.

¶10 On August 10, Hartford sent Columbia a letter requesting that the $103,410 progress payment be released to Hartford. Columbia responded it had no obligation to return the funds and declined the request. In January 2013, Hartford filed a lawsuit against Columbia for misappropriation of trust funds, wrongful setoff, conversion, and declaratory relief.

fll Hartford moved for summary judgment and argued that the money deposited on June 21 went into a trust fund for its benefit and that Columbia had sufficient notice of this fact. Hartford also argued that it had an equitable lien on the funds. Columbia also moved for summary judgment and argued that the progress payment was not a trust fund deposit and that Columbia had no way of knowing of Hartford’s claim to the money when GSA deposited it. The superior court granted Columbia’s motion for summary judgment and dismissed Hartford’s complaint with prejudice. Hartford appeals the superior court’s grant of summary judgment in favor of Columbia and the superior court’s denial of its motion for summary judgment.

[605]*605ANALYSIS

I. Standard of Review

¶12 We review an order for summary judgment de novo, engaging in the same inquiry as the trial court. Loeffelholz v. Univ. of Wash., 175 Wn.2d 264, 271, 285 P.3d 854 (2012). Summary judgment is proper if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” CR 56(c). We construe all facts and their reasonable inferences in the light most favorable to the nonmoving party. Loeffelholz, 175 Wn.2d at 271.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
334 P.3d 87, 183 Wash. App. 599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-fire-insurance-v-columbia-state-bank-washctapp-2014.