A. Farnell Blair Co. v. Hollywood State Bank

227 P.2d 529, 102 Cal. App. 2d 418, 1951 Cal. App. LEXIS 1325
CourtCalifornia Court of Appeal
DecidedFebruary 20, 1951
DocketCiv. 17703
StatusPublished
Cited by8 cases

This text of 227 P.2d 529 (A. Farnell Blair Co. v. Hollywood State Bank) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Farnell Blair Co. v. Hollywood State Bank, 227 P.2d 529, 102 Cal. App. 2d 418, 1951 Cal. App. LEXIS 1325 (Cal. Ct. App. 1951).

Opinion

SHINN, P. J.

This action arose out of a controversy between plaintiff, a government contractor, and defendant bank over part of the earnings of a subcontractor, who was also a *420 supplier of material to the contractor. The bank claimed as assignee of the earnings in question. The contractor claimed to have expended all the money in the payment of claims against the subcontractor having priority over the rights of the bank. There was also involved a special agreement of the contractor to withhold from payments earned by subcontractor sufficient to pay the loans of the bank. The dispute arose in the following manner.

In January, 1946, one Blair received a contract from the United States Government for construction work at Camp Pendleton, Oceanside, which he assigned to plaintiff corporation. Plaintiff assigned to defendant bank all sums to be earned under the contract and from then on the bank financed plaintiff’s operations. On or about February 9, 1946, plaintiff gave one Cook a purchase order for mixed concrete at $8.00 per cubic yard to be used by plaintiff in performance of the general contract. On February 28,1946, by subcontract, plaintiff let to Cook certain asphaltic concrete work on the job for a price of $79,314. By additions and deletions this price was increased to $96,613.74. Cook, having been introduced at the bank by plaintiff, had borrowed money at different times upon certain security all of which was repaid. He carried on his work under both agreements and by November ■ 25, 1946, had earned considerable sums of money. He then applied to the bank for further financing and arranged to assign to the bank sums due and to become due under the purchase order and subcontract. The bank’s credit manager arranged with plaintiff for its consent to the assignment by Cook on terms which were stated in plaintiff’s letter to the bank of November 25, 1946, reading as follows:

“Mr. Richard Neiderhouser,
Hollywood State Bank,
6801 Santa Monica Boulevard,
Los Angeles, California.
Subject: Assignment of Subcontract of Cal Cook to Hollywood State Bank, A. Farnell Blair Navy Contract NOy-13047
“Dear Sir:
“This will confirm my telephone conversation with you of today regarding the caption subject.
“Please be advised that we are agreeable to Mr. Cook’s assignment of his sub-contract with us to the Hollywood State Bank.
*421 “This is to further advise you that we will protect this assignment by withholding the final payment or necessary payments to assure you the remaining balance due you from Mr. Cook as of that date.
“Upon my return to the city next Saturday, I will be able to advise you the amount due Mr. Cook on his next partial payment.
Very truly yours,
A. Farnell Blair Co., Inc. C. B. Antill Vice President and General Manager. ’ ’

A few days later Cook delivered to the bank the purchase order and the subcontract, and assigned to the bank all of his right, title and interest in and to monies then due or to become due thereunder. Between that date and March 30, 1947, the bank made nine separate loans to Cook.

Under the purchase order Cook was entitled to receive the full amount of his invoices for concrete delivered. Under the subcontract, work was to be paid for as it was placed in position upon invoices furnished by Cook, 10 per cent being withheld by plaintiff until completion and approval of the work and the production of evidence that Cook’s material and labor bills had been paid. Cook proceeded with performance of both agreements as hereinafter stated.

The subcontract provided as follows: “Third. The SubContractor will prosecute the work with due diligence, without delay, and will not in any manner, by delay or otherwise, interfere with the work of the Contractor, or other Subcontractors, and should the Contractor conclude that the Sub-Contractor is delaying the work, he shall so notify the Sub-Contractor, who shall immediately thereafter, furnish whatever materials are required by the Contractor, and in case the Sub-Contractor fails to comply with these demands, the Contractor shall have the right to furnish all materials and employ any additional men and charge the expense thereof against the Sub-Contractor, and deduct same from any monies due or to become due by this contract, and should the amount or balance due on said contract be insufficient, to collect said deficiency by legal process.”

Plaintiff gave Performance and Payment Bonds under the base contract pursuant to the Miller Act (title 40 U.S.C.A. § 270(a) et seq.).

*422 The rights of the parties under the subcontract may be stated broadly as follows: - The bank had a right to receive Cook’s gross earnings under the subcontract less any deductions which might result from the exercise by plaintiff of one or more of the following rights: (a) Upon notice to Cook, in case the work was being delayed, to furnish any material and labor pursuant to paragraph 3 of the agreement and to charge Cook with the cost; (b) upon cancellation of the subcontract for Cook's default or upon abandonment by Cook to finish the job and deduct the cost from Cook’s earnings; (c) to pay and discharge Cook’s obligations for labor and material furnished by him for which plaintiff and its surety were liable under the government contract and bonds.

The rights of the parties under the concrete purchase agreement were the following: Plaintiff had a right to deduct from Cook’s gross earnings sums paid to Cook’s creditors for which plaintiff and its surety were liable under the government contract and bonds; the bank was entitled to the remainder.

The controversy arose as follows: Cook had been performing under the two agreements and by November 25,1946, although he had earned considerable sums of money, was indebted to plaintiff in the principal sum of $7,963.78, balance of a demand note he had given plaintiff in March, 1946, and in certain other amounts. After November 25th he proceeded with the performance of both agreements, and upon invoices furnished by him plaintiff paid by cheeks, payable to Cook and the bank jointly, and delivered to the bank, the amounts of Cook’s earnings after making certain deductions, to which we shall refer later. Upon the basis of Cook’s invoices the bank continued to loan him money once or twice a month. The total amount paid to the bank under the subcontract was $45,909.31 and under the purchase order $50,719.96. Plaintiff made no payment to the bank under the subcontract after February 27, 1947, and paid nothing on the purchase order after March 17, 1947. On April 1st Cook owed the bank on notes $41,336.92, which included a loan of $10,000 made to him on that day. On May 29, 1947, the bank deducted $25,000 from plaintiff’s deposit account, and on or about October 2, 1947, deducted further sums amounting to $17,445.82 and applied the same to extinguish Cook’s indebtedness of $42,445.84. Plaintiff sued for recovery of this sum and was given judgment for about $32,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Quincy Services District v. General Accident Insurance Co. of America
105 Cal. Rptr. 2d 694 (California Court of Appeal, 2001)
Levinson v. Linderman
322 P.2d 863 (Washington Supreme Court, 1958)
Fricker v. Uddo & Taormina Co.
312 P.2d 1085 (California Supreme Court, 1957)
Benson v. Andrews
292 P.2d 39 (California Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
227 P.2d 529, 102 Cal. App. 2d 418, 1951 Cal. App. LEXIS 1325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-farnell-blair-co-v-hollywood-state-bank-calctapp-1951.