Bendon v. Andrade & Associates (In Re Colt Engineering, Inc.)

288 B.R. 861, 2003 Bankr. LEXIS 101, 40 Bankr. Ct. Dec. (CRR) 245, 2003 WL 345326
CourtUnited States Bankruptcy Court, C.D. California
DecidedJanuary 28, 2003
DocketBankruptcy No. RS 00-16583 MJ, Adversary Nos. RS 00-1366 MJ, RS 01-1094 MJ, RS 01-1146 MJ
StatusPublished
Cited by4 cases

This text of 288 B.R. 861 (Bendon v. Andrade & Associates (In Re Colt Engineering, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bendon v. Andrade & Associates (In Re Colt Engineering, Inc.), 288 B.R. 861, 2003 Bankr. LEXIS 101, 40 Bankr. Ct. Dec. (CRR) 245, 2003 WL 345326 (Cal. 2003).

Opinion

AMENDED MEMORANDUM OF DECISION

MEREDITH A. JURY, Bankruptcy Judge.

These related adversary proceedings came on regularly for trial on July 9, 2002, before the honorable Meredith A. Jury. Cross-complainant Ulico Casualty Co. appeared through counsel Wilson, Elser, Moskowitz, Edelman & Dicker LLP by *864 John J. Immordino; cross-defendant Merrill Lynch Business Financial Services, Inc. appeared through counsel Frandzel, Robins, Bloom & Csato, L.L.C. by Thomas S. Arthur; defendant and cross-defendant Andrade & Associates appeared through counsel Andrade & Associates by Frank A. Satalino and Snipper, Wainer & Markoff by Maurice Wainer; and Trustee Sandra Bendon appeared through Danning, Gill, Diamond & Kollitz, LLP by Robert Hess-ling and Matthew Kennedy. Evidence, both oral and documentary, was received and argument of counsel presented. The matter was then submitted for post-trial briefs, which were filed on or before August 12, 2002, at which time the matter was submitted for decision. Good cause appearing therefore, the court submits the following memorandum of decision, which shall be deemed the findings of fact and conclusions of law as allowed by Federal Rule of Bankruptcy Procedure 7052(a).

I.

SUMMARY OF FACTS AND ARGUMENT

Debtor Colt Engineering filed a voluntary petition under chapter 7 of the Bankruptcy Code on April 28, 2000. Sandra L. Bendon is the duly appointed chapter 7 trustee. The court has jurisdiction over these combined adversary proceeding pursuant to 28 U.S.C. §§ 157(b)(2)(H) and 1334. These actions are core proceedings under 28 U.S.C. § 157(a)(2)(A), (E),(F),(H),(K) & (O).

On December 11,1997, Colt entered into a written sub-contract agreement with Biltmore Construction Corporation to perform specified work at the San Diego Town Center (the San Diego project). On November 25, 1997, Ulico Casualty Company issued a subcontract performance and payment bond no. B97-114170, which named Biltmore as obligee and which assured payment for all labor performed and materials furnished to the San Diego project. Certain suppliers on the San Diego project asserted that Colt failed to pay them for all labor and materials supplied to the project 1 . Each of these suppliers recorded a mechanic’s lien against the San Diego project and perfected its mechanic’s lien by filing the necessary lawsuit within the statutory period. Each of these suppliers refused to release its mechanic’s lien until it was paid in full on its claims. No competent evidence was presented at trial to refute the validity of any of these claims. In compliance with the performance bond it issued, Ulico paid a total of $296,811.34 to these four claimants on the San Diego project. Payments were all made prior to the chapter 7 filing by Colt and prior to the settlement of the San Diego project, which settlement was consummated in approximately December, 1999 for $375,000. Prior to settlement of the San Diego project, Andrade & Associates on behalf of Colt commenced litigation against Biltmore and others, asserting that Colt was entitled to recover money based on its subcontract agreement with Biltmore. Andrade was attorney of record for Colt at the time the settlement was achieved.

On February 16, 1998, Colt entered into a written subcontract agreement with RB & G Construction Company to perform specified work at the Glendale Fashion Center (Glendale project). On March 17, 1998, Ulico issued its subcontract labor and material payment bond no. B98114342, which named RB & G as an obli *865 gee and which assured payment for all labor performed and materials furnished by Colt to the Glendale project. Certain suppliers alleged that Colt failed to pay them in full for labor and materials furnished to the Glendale project 2 . All of these contractors, with the exception of Southern Counties Oil, recorded mechanic’s liens against the Glendale project. All of these contractors, including Southern Counties Oil, refused to give lien releases on the project until they were paid in full. No competent evidence was presented at trial to refute the validity of any of these claims. Ulico paid a total of $138,189.49 to these five claimants on the Glendale project.

Andrade commenced litigation on behalf of Colt against RB & G and others in connection with the Glendale project. Despite efforts by Andrade, this litigation was not settled until after the bankruptcy was commenced 3 . The payments made by Ulico to the five claimants were all made prior to the bankruptcy proceeding and prior to the settlement agreement.

On August 28, 1997, Colt entered into a written subcontract agreement with RB & G to perform specified work at the Long Beach Town Center project (Long Beach project). On September 11, 1997, Ulico issued its subcontract labor and material payment bond no. B97-014056, which named RB & G as obligee and which assured payment for all labor performed and materials furnished to the Long Beach project by Colt. Certain suppliers alleged that Colt failed to pay them in full for labor and material supplied to the Long Beach project 4 . No competent evidence was presented at trial to refute the validity of any of these claims. Ewles, Mad Dog, United Rentals and Jagur recorded mechanic’s liens against the Long Beach project. All of the six contractors refused to grant lien releases until they were paid in full for their work on the Long Beach project. Ulico paid a total of $124,925.33 to these six claimants, all prior to settlement of the Colt litigation.

Andrade filed suit on behalf of Colt against RB & G and others in connection with the Long Beach project. Although attempts were made, Andrade was unsuccessful in settling the Long Beach litigation prior to the commencement of the bankruptcy proceeding. Special counsel for the trustee achieved the settlement during the bankruptcy proceeding, netting $100,000.00.

In July 1998, for value received, Colt executed and delivered to Merrill Lynch Business Financial Services a WCMA Note, Loan and Security Agreement. Colt granted Merrill Lynch a security interest based on the WCMA Agreement in certain personal property assets, including inventory, equipment, fixtures, general intangibles and accounts. In August 1998, Colt executed and delivered to Merrill Lynch a Term WCMA Reducing Revolver Loan and Security Agreement. In August 1998, Colt granted Merrill Lynch a security interest based on the Revolver Agreement in *866 certain personal property assets, including accounts, inventory, equipment, general intangibles and fixtures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
288 B.R. 861, 2003 Bankr. LEXIS 101, 40 Bankr. Ct. Dec. (CRR) 245, 2003 WL 345326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bendon-v-andrade-associates-in-re-colt-engineering-inc-cacb-2003.