Slutsky v. City of Cincinnati (In Re WM. Cargile Contractor Inc.)

203 B.R. 644, 1996 Bankr. LEXIS 1649, 30 Bankr. Ct. Dec. (CRR) 87, 1996 WL 750102
CourtUnited States Bankruptcy Court, S.D. Ohio
DecidedDecember 31, 1996
DocketBankruptcy No. 1-92-04791, Adversary No. 94-1098
StatusPublished
Cited by3 cases

This text of 203 B.R. 644 (Slutsky v. City of Cincinnati (In Re WM. Cargile Contractor Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slutsky v. City of Cincinnati (In Re WM. Cargile Contractor Inc.), 203 B.R. 644, 1996 Bankr. LEXIS 1649, 30 Bankr. Ct. Dec. (CRR) 87, 1996 WL 750102 (Ohio 1996).

Opinion

DECISION ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

BURTON PERLMAN, Bankruptcy Judge.

This adversary proceeding arises in a bankruptcy case in which the debtor originally filed under Chapter 11 but subsequently converted its case to Chapter 7. The debtor had been engaged in the construction business. Plaintiff in the present adversary proceeding is the Chapter 7 trustee of the debt- or. That trustee here seeks to recover from the defendant City of Cincinnati, the sum of $124,065.28 (the “Fund”) in connection with a project (the “Project”) which debtor had undertaken pursuant to a construction contract (the “contract”) with the City. The City then filed a third-party complaint naming as third-party defendants, all of the subcontractors on the Project which had been the subject of the contract between debtor and the City. The purpose of the City in its third-party complaint is to bring into the action unpaid subcontractors who it believes may have a claim against the Fund.

United States Fidelity & Guaranty Company (“USF & G”) then moved to intervene in the proceeding and to answer as a third-party defendant. USF & G says that it has paid the subcontractors on the Project, and contends that it has a superior right to the plaintiff trustee to the Fund.

USF & G filed a motion for summary judgment in support of its contention, and plaintiff trustee filed a cross-motion for summary judgment. It is these cross-motions which are now before the court.

This court has jurisdiction of this matter pursuant to 28 U.S.C. § 1334(b) and the General Order of Reference entered in this District. This is a core proceeding arising under 28 U.S.C. § 157(b)(2)(A) and (E).

We find the following facts. Debtor filed its Chapter 11 case in bankruptcy on September 18, 1992. The case was converted to one under Chapter 7 on November 29, 1993. On March 16, 1992, debtor entered into the contract with the City of Cincinnati for the Project known as the Main Street Street-Scape Phase 1 Project. USF & G bonded the Project by means of a performance bond issued to the debtor. Debtor, however, did not pay all of its subcontractors. Those subcontractors looked to USF & G for payment pursuant to the bond. The exhibits in the record show that USF & G paid 15 of the 16 subcontractors on the project, all of the subcontractors except for Laborer’s International Union named by the City as third-party defendants. The payments by USF & G to subcontractors exceeded the amount here in controversy.

On these facts, competing claims to the fund now in escrow are asserted by on the one hand, USF & G which asserts that it is entitled to payment to it of the Fund to reimburse it for its payments to subcontractors, and on the other hand, the trustee in bankruptcy, who contends that he is entitled to payment of the Fund into the estate for the benefit of all unsecured creditors. We have concluded that the cross-motion of the trustee for summary judgment should be *646 granted, and the motion of USF & G for summary judgment denied.

Motions for summary judgment are governed by F.R.Civ.P. 56, which is incorporated into bankruptcy practice by F.R.B.P. 7056. That rule provides in part that a motion for summary judgment is to be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law.” The moving party bears the initial burden of showing that there is no issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323-324, 106 S.Ct. 2548, 2552-2553, 91 L.Ed.2d 265 (1986).

Our conclusion in favor of the plaintiff/trustee is reached primarily by reference to In re Construction Alternatives, Inc., 2 F.3d 670 (6th Cir.1993). The court in Construction Alternatives summarized the facts before it as follows:

In the case at bar, it is undisputed that the work on the project was complete at the time that CA petitioned for bankruptcy. There were several bookkeeping and administrative matters, pursuant to state law and CA’s contract with the School District, to be completed and several subcontractors to be paid, but CA owed nothing to the School District, and therefore, no payments to the School District were required or other expenses incurred to perfect CA’s claim to the final progress payment. Thus, we conclude that CA had earned the right to receive its final progress payment, ...

The facts in the case before us are essentially the same. It is undisputed that the work on the Project is complete. Virtually all subcontractors have been paid. (That they have been paid by USF & G pursuant to its bond obligations is immaterial for the purpose of determining completion of the Project.) The legal conclusion which inevitably follows from these facts is that the final payment pursuant to the contract on the Project is property of the estate as that term is defined at 11 U.S.C. § 541. Once this conclusion is reached, it follows that the Fund must be turned over to the trustee for distribution to creditors. This conclusion is fatal to the position of USF & G, for it is indispensable to the position of USF & G that the Fund be held not to be a part of the bankruptcy estate.

USF & G argues for a different result primarily on the basis that the contract required that debtor pay its subcontractors and provide proof thereof to the City before it could collect the final payment. The contract gave the City the right to withhold payment to the extent necessary to satisfy unpaid subcontractor claims. As a basic authority to support its position, USF & G relies upon In re Design International Ohio Corp., Case No. 1-92-00642 (Bankr.S.D.Ohio filed September 14, 1994), an unreported decision of this court, a decision in which the court did indeed reach the conclusion, that the bonding company was entitled to receive the final payment from the owner. Design International, however, is distinguishable from the present case just as that ease was distinguished by the court in its decision from Construction Alternatives.- One fact which distinguishes Design International is that debtor/contractor was not entitled to final payment because “all bills for materials and supplies had not been paid or satisfied” while here such bills have been paid or satisfied. Another distinction, the preeminent one, is that this court distinguished Design International from Construction Alternatives because in Design International the contract provided for a retainage. (p. 11.) In like manner, Design International is distinguishable from the case at hand, for here there is no provision for a retainage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
203 B.R. 644, 1996 Bankr. LEXIS 1649, 30 Bankr. Ct. Dec. (CRR) 87, 1996 WL 750102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slutsky-v-city-of-cincinnati-in-re-wm-cargile-contractor-inc-ohsb-1996.