In Re Alliance Properties, Inc.

35 Cont. Cas. Fed. 75,714, 104 B.R. 306, 1989 Bankr. LEXIS 1400, 1989 WL 98793
CourtUnited States Bankruptcy Court, S.D. California
DecidedAugust 23, 1989
Docket19-00528
StatusPublished
Cited by5 cases

This text of 35 Cont. Cas. Fed. 75,714 (In Re Alliance Properties, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Alliance Properties, Inc., 35 Cont. Cas. Fed. 75,714, 104 B.R. 306, 1989 Bankr. LEXIS 1400, 1989 WL 98793 (Cal. 1989).

Opinion

MEMORANDUM DECISION

LOUISE DeCARL MALUGEN, Bankruptcy Judge.

I. INTRODUCTION

This case is essentially an ownership dispute between Torrey Pines Bank .(“TPB”), a secured creditor, Alliance Properties, Inc. (“API”), the debtor-in-possession, and Insurance Company of North America (“INA”), a surety for the debtor on several bonded federal government contracts. The asset in question is a fund of $375,000 held in a blocked account pursuant to an order of this Court approving a certain contract settlement with the government. TPB holds a security interest in the debtor’s pre-petition accounts receivable, including contract proceeds, and a first priority lien in all post-petition receivables via a cash collateral order approved by this Court. INA asserts an equitable lien in the fund for having paid, post-petition, the remaining claims of various suppliers and subcontractors on the settled contract.

The dispute is before the Court by way of INA’s Motion for Order Releasing Segregated Funds. The Court finds that INA’s motion is well-taken and directs the immediate release of $273,390.65 to INA from the blocked account, with the balance of the fund to be remitted to. TPB.

II. FACTS

A. The Bankruptcy Proceedings.

The debtor was engaged in the performance of several government contracts bonded by INA pursuant to the Miller Act, 40 U.S.C. § 270a et seq. (1982). The debtor encountered serious performance difficulties on a maintenance contract for Randolph Air Force Base (the “Randolph contract”) and these difficulties were, in large part, responsible for its Chapter 11 filing, on January 26, 1987.

API continued to operate the business post-petition under a cash collateral agreement with TPB. The agreement authorized API to take additional draws on a pre-petition line of credit to fund its operations. In return, API granted TPB a first priority security interest in the post-petition receivables, including the Randolph contract proceeds. The Court approved the agreement on April 3,1987, after a hearing *308 on notice to all creditors. 1 Neither the original moving papers, notice of hearing nor the final cash collateral order were ever served on INA.

API and the government eventually resolved the performance difficulties on the Randolph contract by executing an amendment to the contract which required the government to make an additional lump sum payment of approximately $1.2 million to the estate. API then brought a motion to approve the amendment which was granted by the Court at a hearing held on October 17, 1988. The Court further ordered API to deposit the bulk of the payment in a blocked account pending INA’s motion to determine its surety rights in these proceeds.

INA brought the motion on January 12, 1989, requesting the release of $840,000 from the account' as compensation for its total payments to suppliers and subcontractors on several bonded contracts of the debtor. The Court denied this motion but continued the matter for an evidentiary hearing on May 31,1989, to consider INA’s alternate request for the release of funds attributable to payments made under the bond on the Randolph contract. The Court then directed API to release all but $375,-000 of the funds to TPB. The balance was reserved pending hearing on INA’s continued motion.

In preparation for the continued hearing, the Court directed the parties to complete discovery by May 1, 1989, and to prepare and file supplemental memoranda. The parties chose not to introduce testimonial evidence at the hearing and, instead, relied upon their previous pleadings, supplemental declarations and final oral arguments presented at the continued hearing.

B. The Record Before The Court.

The record in this case reveals that the parties are in substantial agreement over most of the essential facts of this dispute. The debtor is a contractor, primarily in the business of constructing, repairing and maintaining military housing units for the federal government. On October 2, 1984— one week after the debtor was awarded the contract — INA posted performance and payment bonds on the Randolph contract, as required by the Miller Act which governs government contracts of this nature. Although the Court has not been provided with a complete copy of the contract, the excerpted portions of the payment provisions show that the government was obligated to make progress payments to API as the work proceeded and entitled to retain up to. 10 percent of the progress payment to secure the debtor’s complete performance.

Within months after work commenced, the debtor began experiencing performance problems in the form of various disruptions and delays allegedly due, in part, to the government’s failure to provide adequate plans and specifications and failure to cooperate with the debtor’s efforts to resolve problems encountered on the job. After incurring substantial, additional costs on the job, the debtor filed this Chapter 11 petition.

On March 13, 1987, a little over a month after the petition was filed, API submitted a claim to the government for an equitable adjustment to the contract as compensation for both the additional costs and the government’s alleged breach of contract. The claim was presented in the form of a letter to the government’s contracting officer for the Randolph contract, generally summarizing the basis for the adjustment. The letter also refers to an appendix which purportedly sets forth the itemization of charges and the total amount of the claim. The appendix was never filed with the Court. However, TPB and API have previously represented to the Court that API was seeking approximately $1,385,324 for the added costs and “in excess of $5 million” for the contract damages. 2 API has *309 verified these amounts for each portion of the claim in a “Quantum Summary” submitted with its supplemental opposition to INA’s motion.

API and the government resolved their dispute on September 30, 1988, and their agreement is memorialized by an “Amendment of Solicitation/Modification of Contract” (the “Amendment”). The Amendment awards API an additional sum of $1,249,094 and states that it is to be a “complete equitable adjustment for the [debtor’s] claims” as well as a complete release of liability. The Amendment does not set forth the precise basis for the additional costs and contract damages. The record is inconclusive on this issue.

INA asserts that the award is an equitable adjustment to the contract to compensate API for its additional costs incurred in the performance of the contract. TPB and API argue that the award is for money damages paid in settlement of a breach of contract claim. They offer the declaration of debtor’s president, V. Allan Johnston, which states that all sums originally owed on the contract have been paid and that the purpose of the claim was to obtain damages for the government’s breach of contract. There is no evidence of the government’s intent in making the award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,714, 104 B.R. 306, 1989 Bankr. LEXIS 1400, 1989 WL 98793, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-alliance-properties-inc-casb-1989.