East Quincy Services District v. General Accident Insurance Co. of America

105 Cal. Rptr. 2d 694, 88 Cal. App. 4th 239, 2001 Cal. App. LEXIS 259
CourtCalifornia Court of Appeal
DecidedMarch 20, 2001
DocketC033482
StatusPublished
Cited by7 cases

This text of 105 Cal. Rptr. 2d 694 (East Quincy Services District v. General Accident Insurance Co. of America) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Quincy Services District v. General Accident Insurance Co. of America, 105 Cal. Rptr. 2d 694, 88 Cal. App. 4th 239, 2001 Cal. App. LEXIS 259 (Cal. Ct. App. 2001).

Opinion

*241 Opinion

DAVIS, Acting P. J.

Nominal plaintiff East Quincy Services District (the District) filed a “Complaint in Intervention” [sic], 1 which interpled General Accident Insurance Company of America (the Surety) and the Division of Labor Standards Enforcement (the Division) as defendants contesting entitlement to funds the District was holding. The defendants subsequently stipulated to the dismissal of the District from the lawsuit. 2

The gist of the dispute was whether the District should deduct penalties for prevailing wage and overtime violations 3 on its public works project from the balance of the contract price otherwise owing to defendant Surety. (The Surety funded the completion of the project after its principal defaulted.) The defendants filed' cross-motions for summary judgment. The superior court denied the Division’s motion and granted defendant Surety’s motion, ruling the funds were no longer owed to the contractor and thus were not “payments to the contractor of money due under a contract” out of which the penalties are forfeited by operation of law. 4 The Division challenges this conclusion. We agree and shall reverse with directions.

Facts

We review the superior court’s ruling on a motion for summary judgment de novo. 5 As there are no material disputes and the few evidentiary objections are waived for failure to obtain rulings on them at the hearing, 6 we will depart from the usual paradigm in which we compare the showings of the parties 7 and focus on the pertinent facts. The Division’s notice of appeal is from a judgment that ruled on both motions, and thus the totality of the facts before the trial court are part of this appeal.

The District and P & M Pipelines (the contractor) entered into a contract for a sewer project in April 1996. The original contract cost for the project *242 was $2,289,000. 8 This amount was later increased to $2,304,000 as a result of change orders. The contract expressly incorporated an Invitation to Bid and Information for Bidders. The latter noted the application of statutory prevailing wage and overtime requirements for public works projects and the penalties for violations.

Defendant Surety issued payment and performance bonds on the contract for the original amount of the project. The contract expressly incorporated these bonds. In the performance bond, defendant Surety expressly agreed to “cause the obligations and duties of the Principal, as set forth in the Contract referred to herein, to be carried out in full.”

According to its accounting, the District had paid the contractor $1,346,000 for $1,854,000 in completed work as of October 31, 1996. The contractor, experiencing financial difficulties, defaulted in November 1996. It assigned its right to contract proceeds to defendant Surety. In accordance with its obligations under the bonds, defendant Surety reimbursed all unpaid creditors and engaged another contractor in December 1996 to complete the contract. Defendant Surety’s expenses were $1,059,000 and its payments from the District were $492,000. The District filed a notice of completion for the project in September 1997.

During an unspecified period of time, the Division had conducted an investigation, and determined the contractor had failed to pay the prevailing wage. Although not articulated explicitly, it appears the Division also found violations of the maximum workday and workweek requirements for public projects. 9 In November 1997, the Division notified the District to withhold forfeited “payments which are or hereafter may become due to the contractor” in the amount of $97,000 in unpaid wages plus $80,000 in penalties for prevailing wage and overtime violations. 10 Neither the contractor nor defendant Surety filed suit for the recovery of the penalties or forfeitures within the 90-day limitations period. 11 In January 1998, the Division made a demand of the District to remit the forfeited payments and penalties. In June 1998, defendant Surety remitted the unpaid wages to the Division (less an amount paid directly to two workers). The Division subsequently reduced its demand of the District to the amount of the penalties.

The District then filed the instant action. As we read defendant Surety’s statement of undisputed facts, the District deposited the disputed amount with the superior court, retaining an additional $9,000 of the contract price.

*243 Discussion

Under the statutes, a contractor forfeits wage and overtime penalties out of money due under a contract for public work. 12 We confront two questions—determining when defendant Surety extinguished the contractor’s rights to unpaid construction funds, and when the penalties accrued.

A

The trial court reasoned there was no money due the contractor under the contract out of which to withhold the penalties after the point of default and defendant Surety’s assumption of the contract. In an application of subrogation to this case, the court apparently found defendant Surety could not be considered to be subrogated to the right of the contractor to compensation under the contract because the District was its principal (“[h]ad there been no bond the District would have taken the hit”) and the contractor had “lost any rights to which [defendant Surety] could have been subrogated.”

In point of fact, the contractor was the principal—having paid for the bond—and the District was a creditor of the principal to whose rights against the principal defendant Surety succeeded after it paid its principal’s debt to the creditor, 13 which would presumably include the right under principles of setoff to charge the costs of completion against the unpaid balance of the contract price. 14

The trial court also cited Harsco Corp. v. Department of Public Works, 15 which held that a supplier’s stop notice claim against funds “due or to become due” a contractor 16 (an equitable equivalent of a mechanic’s lien on a public works project that imposes a trust on the funds held by the agency rather than the public property itself) 17 did not reach funds an agency *244

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittsburg Unified School District v. S.J. Amoroso Construction Co.
232 Cal. App. 4th 808 (California Court of Appeal, 2014)
Scie LLC v. Xl Reinsurance America, Inc.
397 F. App'x 348 (Ninth Circuit, 2010)
State Farm General Insurance v. Wells Fargo Bank
49 Cal. Rptr. 3d 785 (California Court of Appeal, 2006)
Whiteley v. Philip Morris, Inc.
11 Cal. Rptr. 3d 807 (California Court of Appeal, 2004)
Henley v. Philip Morris Inc.
113 Cal. Rptr. 2d 494 (California Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
105 Cal. Rptr. 2d 694, 88 Cal. App. 4th 239, 2001 Cal. App. LEXIS 259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-quincy-services-district-v-general-accident-insurance-co-of-america-calctapp-2001.