United States Fid. & Guar. Co. v. OAK GROVE UNION SCH. DIST. OF SONOMA CTY.

205 Cal. App. 2d 226, 22 Cal. Rptr. 907, 205 Cal. App. 226, 1962 Cal. App. LEXIS 2124
CourtCalifornia Court of Appeal
DecidedJune 28, 1962
DocketCiv. 20188
StatusPublished
Cited by14 cases

This text of 205 Cal. App. 2d 226 (United States Fid. & Guar. Co. v. OAK GROVE UNION SCH. DIST. OF SONOMA CTY.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fid. & Guar. Co. v. OAK GROVE UNION SCH. DIST. OF SONOMA CTY., 205 Cal. App. 2d 226, 22 Cal. Rptr. 907, 205 Cal. App. 226, 1962 Cal. App. LEXIS 2124 (Cal. Ct. App. 1962).

Opinion

BRAY, P. J.

Defendant school district appeals from a judgment in favor of plaintiff for $7,988.40 and interest from December 10, 1957.

Questions Presented

1. (a) Is the contractor’s surety subrogated to the rights to foreclose a stop notice lien of laborers and materialmen whose claims the surety has paid? Yes.

(b) Is filing of a claim with the school district a prerequisite to this type of action? No.

2. (a) How may a stop notice be filed?

(b) Were stop notices filed? Yes.

*229 3. Did the district make a premature payment? Yes.

4. Did the surety, by the terms of its bond, waive its rights arising from a premature payment by the district to the contractor? No.

5. Correctness of findings.

Record

Defendant school district contracted with Charles J. Collins-worth, a contractor, for the construction of certain additions to the district’s school building. Prior to July 1, 1957, three progress payments totalling $48,339.36 had been earned and paid on a total contract price, with agreed extras, of $63,520. September 5, 1957, a fourth payment of $7,988.40 was paid Collinsworth, leaving an unpaid balance of $7,192.24, which sum was paid over to plaintiff. This sum was insufficient to pay the remaining claims of laborers and materialmen, including those who had filed stop notices. Plaintiff by reason of its bond paid all claims. Then, contending that it was subrogated to the rights of the stop notice claimants, it brought this action against the district for the amount represented by the stop notice claims.

1. (a) Subrogation.

Defendant contends that there can be no subrogation in favor of a surety who has paid the claims of stop notice claimants and therefore the trial court erred in overruling its demurrer to the complaint, its motion for nonsuit, its objections and counter findings of fact and conclusions of law, and in rendering judgment for plaintiff. Our determination of this and the other questions raised by defendant is that the court committed no error. Defendant claims that the only remedy open to plaintiff, if any, for the defendant’s failure to withhold under the stop notice would be an action against the trustees of the district for negligence. That such a remedy might be available is shown by Mock v. City of Santa Rosa (1899) 126 Cal. 330 [58 P. 826], Payne v. Baehr (1908) 153 Cal. 441 [95 P. 895], and L. W. Blinn Lumber Co. v. Pioneer Drain. Dist. (1920) 50 Cal.App. 364 [195 P. 750], However, such remedy is not exclusive.

Defendant concedes that if a proper and timely stop notice is filed there then arises what is referred to as an equitable garnishment which confers certain rights on the labor and material claimants filing the notices.

*230 “In substance, section 1190.1, subdivision (h) [Code Civ. Proc.], indicates that compliance with the notice and bond provisions thereof effects an ‘ equitable garnishment. ’ The courts have identified the effect of filing a stop notice in connection with the claims of mechanics and materialmen pursuant to similar code provisions as causing ‘an assignment pro tanto,’ ‘establishing an equitable garnishment,’ conferring an ‘equitable lien,’ or resulting in ‘a form of equitable subrogation. ’ [Citations.] Recovery upon such claims by enforcement of the rights thus acquired may be obtained through an action in equity. [Citations.] The remedy thus afforded the mechanic and materialman, which involves a proceeding against the construction loan fund, is different from and in addition to the remedy provided by the statute authorizing the filing of and foreclosure upon a lien against the property improved. [Citations.] The remedies are cumulative. [Citations.] The decisions hereinabove cited consider pertinent applicable provisions of former section 1184 of the Code of Civil Procedure which are substantially the same as those now contained in subdivision (e) of section 1190.1, covering the effect of stop notice proceedings as applied to an owner, as well as those contained in subdivision (h) of that section, governing the effect of such proceedings as applied to the holder of construction funds.

“We conclude that the ‘equitable garnishment’ referred to in section 1190.1, subdivision (h), may be enforced through an action in equity; that the holder of construction funds may not invalidate the effect of a notice and bond given pursuant to the statutory provisions by thereafter transferring those funds to other creditors or using them to advance its own interests, as was done in the case at bar [citations] ; and that, in an action to effect recovery from the funds subjected to the claimant’s equitable garnishment, the person holding those funds must account for the amount thereof which the statute required him to withhold, and if he fails to do so, a personal judgment may be entered against him. [Citations.]” (Calhoun v. Huntington Park First Sav. & Loan Assn. (1960) 186 Cal.App.2d 451, 459-460 [9 Cal.Rptr. 479]; see also Sweeney v. Board of Trustees (1917) 33 Cal.App. 331 [165 P. 42].)

In a public works contract there can be no lien against the property; hence the use of stop notices to provide protection to subcontractors and defaulting contractors. In a sense the stop notice constitutes a lien on the prop *231 erty (earnings) of the contractor held by the owner. When the notice is filed the claimant immediately has a right against those earnings held by the public agency. In effect, the filing imposes a trust obligation on the public agency. (Theisen v. County of Los Angeles (1960) 54 Cal.2d 170 [5 Cal.Rptr. 161, 352 P.2d 529]; Calhoun v. Huntington Park First Sav. & Loan Assn., supra, 186 Cal.App.2d 451; Bates v. Santa Barbara County (1891) 90 Cal. 543 [27 P. 438].)

This is the situation here. Once the stop notices were filed properly (as will hereafter appear) and there was at the time of filing or thereafter money earned by the contractor and unpaid, an equitable assignment or garnishment pro tanto in favor of the stop claimants occurred and a cause of action thereon arose in their favor. The claimants had a right to expect that the stop notices would be observed. Whether the money was actually there or not is immaterial because in legal contemplation the district is deemed to be holding sufficient funds to pay the claimants.

It is clear that an action in equity lies by laborers and materialmen against an owner who disregards their properly filed stop notices. This brings us to the question of whether, in view of the well known rule that where a surety discharges a claim against its principal, any lien that secures that claim is likewise discharged, plaintiff surety here can be subrogated to the rights of the stop claimants whose claims it paid. The answer is that it can be. That answer appears in Street v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Quincy Services District v. General Accident Insurance Co. of America
105 Cal. Rptr. 2d 694 (California Court of Appeal, 2001)
Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Golden Eagle Insurance v. First Nationwide Financial Corp.
26 Cal. App. 4th 160 (California Court of Appeal, 1994)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Leatherby Ins. Co. v. City of Tustin
76 Cal. App. 3d 678 (California Court of Appeal, 1977)
Azusa Western, Inc. v. City of West Covina
45 Cal. App. 3d 259 (California Court of Appeal, 1975)
American Fidelity Fire Insurance Co. v. United States
385 F. Supp. 1075 (N.D. California, 1974)
Harsco Corp. v. Department of Public Works
21 Cal. App. 3d 272 (California Court of Appeal, 1971)
Pacific Employers Insurance v. State of California
477 P.2d 129 (California Supreme Court, 1970)
Allstate Insurance v. Orlando
262 Cal. App. 2d 858 (California Court of Appeal, 1968)
General Electric Co. v. Central Surety & Insurance
232 Cal. App. 2d 590 (California Court of Appeal, 1965)
Sunlight Electric Supply Co. v. McKee
226 Cal. App. 2d 47 (California Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
205 Cal. App. 2d 226, 22 Cal. Rptr. 907, 205 Cal. App. 226, 1962 Cal. App. LEXIS 2124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fid-guar-co-v-oak-grove-union-sch-dist-of-sonoma-cty-calctapp-1962.