Harsco Corp. v. Department of Public Works

21 Cal. App. 3d 272, 98 Cal. Rptr. 337, 1971 Cal. App. LEXIS 1070
CourtCalifornia Court of Appeal
DecidedNovember 16, 1971
DocketCiv. 11558
StatusPublished
Cited by6 cases

This text of 21 Cal. App. 3d 272 (Harsco Corp. v. Department of Public Works) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harsco Corp. v. Department of Public Works, 21 Cal. App. 3d 272, 98 Cal. Rptr. 337, 1971 Cal. App. LEXIS 1070 (Cal. Ct. App. 1971).

Opinion

Opinion

KAUFMAN, J.

J. —■ From that portion of the judgment awarding plaintiff $7,012.46 as against defendant Department of Public Works (hereinafter Department), Department appeals.

The Facts

The essential facts, are not in dispute. In October 1968, the Department entered into a written contract with defendant Ashby Construction Co. (hereinafter Ashby) for the construction of a bridge in Riverside County. Pursuant to Government Code section 4200 (now Civ. Code, § 3247) Ashby filed with the department a labor and material bond executed by United Bonding Insurance Company. Between October 15, 1968, and February 12, 1969, at the request of Ashby, plaintiff furnished scaffolding equipment used in the work of improvement having a reasonable value of $7,012.46. Not having been paid, plaintiff filed a verified claim and notice to withhold (hereinafter stop notice) with defendant Department on March 19, 1969. 1

Before receiving plaintiff’s stop notice, the Department had paid to Ashby a number of progress payments. As of the date plaintiff filed its stop notice, Ashby had been fully paid for its partial performance under the contract except that the Department held retention funds in the amount of $21,-070.05 which had been deducted from the progress payments due Ashby pursuant in part to Government Code section 14402 and, apparently, in part pursuant to Government Code section 14376. 2 The substance of both sections was apparently embodied in Ashby’s contract.

*275 Ashby had defaulted in performance of the contract, and its control over the project was terminated by the Director of Public Works on March 20, 1969. Ashby’s surety, United Bonding Insurance Company, elected not to complete the project, and a completion contract was awarded to Massey Sand and Rock Co. pursuant to Government Code section 14396. Massey completed the contract according to the original plans and specifications at a cost of more than $26,000 in excess of the- price prescribed by the contract between the Department and Ashby.

Upon receiving plaintiff’s stop notice, defendant Department did not withhold any of the retention funds for the purpose of paying plaintiff’s claim. Instead, the retention funds were utilized for completion of the project and, thus, paid to Massey.

Both Ashby and United Bonding Insurance Company were named as defendants in the action. Ashby defaulted, and the bonding company stipulated to judgment against it. Accordingly, the judgment awards plaintiff recovery against those defendants. 3 As to defendant Department, the trial court found that the $21,070.05 in retention funds had been “earned” by Ashby; concluded that the retention funds were properly subject to plaintiff’s stop notice; and, accordingly, rendered judgment against the Department in the amount of $7,012.46, “said sum to be paid out of the $21,-070.05 earned retention held by the defendant DEPARTMENT . . . .” 4

*276 Issue and Resolution

The issue presented is whether, on a work of public construction, funds withheld from a contractor by a public agency pursuant to Government Code sections 14402 and 14376 are subject to the valid stop- notice of a supplier or subcontractor when the cost of completion exceeds the original contract price and consumes all of the retained funds. Defendant Department contends they are not. We agree.

The stop notice procedure is statutorily prescribed. Primarily applicable to the case at bench is former Code of Civil Procedure, section 1190.1, subdivision (c) (now Civ. Code, §§3161 as to private works and 3186 as to public works). Under the statute a stop notice reaches only monies or bonds due or to become due the contractor. (Former Code Civ. Proc., § 1190.1, subd. (c) now Civ. Code, § 3186; see also farmer Code Civ. Proc., § 1192.1, subd. (d) now Civ. Code, § 3193.) The question is, therefore, whether the $21,070.05 retained by the Department constituted monies due or to become due Ashby when the cost of completion substantially exceeded the unpaid balance of the contract price. We hold it did not.

At the outset we note the trial court’s finding that Ashby had “earned” the retained monies. That is true in a sense as to the funds retained pursuant to Government Code section 14402. Had it been possible to complete the project within the contract price, those funds would have been due Ashby, and, thus, subject to plaintiff’s stop notice. (See Gov. Code, § 14399; also Quinn v. United States, 99 U.S. 30, 34 [25 L.Ed. 269, 270].) To the extent, however, the funds were retained pursuant to Government Code section 14376, they cannot be considered to have been “earned.” Retentions pursuant to that section constitute statutorily approved liquidated damages. (Silva & Hill Constr. Co. v. Employers Mut. Liab. Ins. Co., 19 Cal.App.3d 914, 918-920 [97 Cal.Rptr. 498].) In any event, this finding of the trial court cannot be considered equivalent to a finding that the retained funds were due or to become due Ashby, for Department expressly requested special findings on that point, and no such findings were made. Moreover, if the finding that the monies were “earned” were construed as equivalent to a finding that they were due or to become due Ashby, the finding would be unsupported by the evidence and contrary to law.

Government Code section 14402 (see fn. 2, ante) prohibits the Department from making progress payments in excess of 90 percent of the estimated value of labor and materials and compels it to withhold not less than 10 percent of the contract price until final completion and ac *277 ceptance of the project. Government Code section 14399 provides in substance that if the control of the contractor is terminated by the Director the contractor is not entitled to receive any portion of the monies retained until the work is fully completed and, then, only if the unpaid balance exceeds the sum of the amount expended in finishing the work. It is apparent, therefore, that the determination as to whether such retention funds are due or to become due the contractor must abide completion of the work. Where the cost of completion exceeds the unpaid balance of the contract including the amount of the retention funds, the retention funds cannot be considered to have been due or to become due the contractor within the meaning of Code of Civil Procedure section 1190.1 subdivision (c) (now Civ. Code, § 3186). (Gov. Code, §§ 14399 and 14402; Dorris v. Alturas School District, 25 Cal.App. 30, 32-33 [142 P. 795].)

The venerable Alturas School District case, supra, constitutes persuasive, if not controlling, authority. The applicable statute was then Code of Civil Procedure section 1184 (Stats. 1911, p. 1315), the pertinent language of which was substantially the same as that in Code of Civil Procedure section 1190.1 subdivision (c) (now Civ. Code, § 3186). (See Dorris v. Alturas School District, supra, 25 Cal.App. at p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittsburg Unified School District v. S.J. Amoroso Construction Co.
232 Cal. App. 4th 808 (California Court of Appeal, 2014)
East Quincy Services District v. General Accident Insurance Co. of America
105 Cal. Rptr. 2d 694 (California Court of Appeal, 2001)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Holiday Development Co. v. J. A. Tobin Construction Co.
549 P.2d 1376 (Supreme Court of Kansas, 1976)
In Re the Dissolution of the Marriage of Dunn
511 P.2d 427 (Court of Appeals of Oregon, 1973)
In Re Marriage of Walton
28 Cal. App. 3d 108 (California Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
21 Cal. App. 3d 272, 98 Cal. Rptr. 337, 1971 Cal. App. LEXIS 1070, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harsco-corp-v-department-of-public-works-calctapp-1971.