Holiday Development Co. v. J. A. Tobin Construction Co.

549 P.2d 1376, 219 Kan. 701, 1976 Kan. LEXIS 416
CourtSupreme Court of Kansas
DecidedMay 8, 1976
Docket47,972
StatusPublished
Cited by24 cases

This text of 549 P.2d 1376 (Holiday Development Co. v. J. A. Tobin Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holiday Development Co. v. J. A. Tobin Construction Co., 549 P.2d 1376, 219 Kan. 701, 1976 Kan. LEXIS 416 (kan 1976).

Opinion

The opinion of the court was delivered by

Harman, C.:

This action involves the timeliness of a mechanic’s lien filed by a materialman for rock furnished a subcontractor and the validity of a personal judgment entered in favor of the materialman and against a lessee of the realty. The materialman prevailed on these issues and the les'see has appealed.

Appellant Holiday Development Co., Inc., leased fend owned by the Urban Renewal Agency of Kansas City for a period of ninety-nine years for 'the purpose of building and operating an office building thereon. Holiday entered into a contract with Wilson & Savage Development Company as prime contractor to build the building and an adjacent asphalt parking lot. In March, 1971, Wilson & Savage subcontracted construction of the parking lot to the Jordon Construction Company. Jordon commenced building the parking lot using base rock purchased by it from appellee J. A. Tobin Construction Company. Tobin began furnishing rock October 11, 1971, and last delivered rock for the project on December 3, 1971, for which it has not been paid.

In January, 1972, Jordon ceased working on the lot and never finished it. Dispute exists between the parties as to when Jordon actually abandoned the project. The trial court made no finding on this. There was also dispute between the litigants as to whether Tobin had by the time of its last delivery on December 3, 1971, delivered all the rock necessary for the parking lot — according to Holiday all had been delivered but Tobin says more was still needed. The trial court resolved that dispute in favor of Tobin.

When Jordon ceased working on the lot in January, 1972, it had not paid for rock supplied by Tobin in the amount of $8,878.34. On April 6, 1972, Tobin by its foreman hand-delivered a letter to Wilson & Savage’s construction superintendent stating 'that Jordon had not yet paid Tobin for the rock. According to Tobin’s foreman the construction superintendent stated there were sufficient funds coming to Jordon to pay Tobin and further said, “Don’t worry about it, you will get your money”. Wilson & Savage’s *703 superintendent testified be never told any Tobin representative he would see that they got their money.

Later there were other conversations between representatives of Wilson & Savage and Tobin wherein the former tried to enlist the latter s services in finishing the parking lot or in assisting Jordon to do so but Tobin was not interested in the conditions offered. Thereafter Wilson & Savage employed Suburban Asphalt Company to finish the parking lot. In all Wilson & Savage had to pay for the parking lot $4,500 more than the contract price with Jordon.

Tobin’s rock bill was never paid and on August 11, 1972, it filed a mechanics lien against Holiday. Holiday then commenced this action against Tobin asking that Tobin’s hen be cancelled. Holiday also sought damages beoause of Tobin’s wilful act in clouding its title by the filing of the hen. In its petition Holiday referred to Wilson & Savage as its agent in contracting with Jordon. (Later Holiday tried, unsuccessfully, to amend its petition by deleting this ine.pt allegation, to conform to the evidence that Wilson & Savage was an independent contractor rather than its agent.)

Tobin filed an answer and a three-part counterclaim to the Holiday suit. In the latter, first, it asked for foreclosure of its hen; second, it alleged Holiday through its agent Wilson & Savage agreed to pay Tobin for the rock dehvered; and third, it asserted it was a third party beneficiary of the written contract between Wilson & Savage and subcontractor Jordon, and it asked for a personal judgment against Holiday.

Trial to the court resulted in the following judgment:

“The Court finds that Wilson & Savage Development Company entered into a contract with the Holiday Development Company, Inc., for the construction of an office building and that Wilson & Savage Development Company was the agent of Holiday Development Company, Inc. That subsequent to said contract Wilson & Savage Development Company entered into a construction subcontract with the Jordan Construction Company on or about the 17th day of March 1971 for the construction of an asphalt paving lot and work related thereto. That the said Jordan Construction Company subsequent to obtaining this contract did enter into a contraot with the J. A. Tobin Construction Company to furnish gravel base for the subject parking lot covered by the contract between Wilson & Savage and Jordan Construction Company. That in connection with this work gravel was furnished and subsequently a mechanic’s lien was filed in the Clerk of the District Court’s office of Wyandotte County, Kansas on the 11th day of August, 1972.
“The Court finds from the evidence presented that the last rock delivered on the site by the defendant Tobin Construction Company occurred in December of 1971. That there was additional work to be performed and materials furnished by the subcontractor Tobin Construction Company, and that *704 the job was not complete on 'the date when the last materials as listed in the lien were furnished.
"The Court particularly finds that said date of last material furnished does not constitute the completion of the contract of the Tobin Construction Company with the Jordan Construction Company and that there was work remaining to be performed by Tobin Construction Company, and that said obligation continued and that the subject lien as filed was filed within the statutory time as provided by K. S. A. 60-1101 and 3.
“Therefore, judgment is entered in favor of the defendant versus the plaintiff in the amount of $8,878.34 and oosts, and plaintiff’s petition to oancel the lien is denied in all respects.”

Holiday appeals from the foregoing judgment.

We consider first the validity of the mechanic’s lien, i. e., whether it was timely filed. K. S. A. 1975 Supp. 60-1103 provides in pertinent part:

“(a) Procedure. Any subcontractor or other person furnishing labor, equipment, material or supplies, used or consumed at the site of the property subject to the lien, under an agreement with the contractor, or a subcontractor of the contractor, may obtain a lien for the amount due in the same manner and to the same extent as the original contractor except the lien statement must state the name of the contractor and be filed within three (3) months after the date material or equipment was last furnished or labor performed by the claimant. . . .”

The trial court found that since more rock was necessary to complete the project appellee Tobin’s lien was timely filed even though filed eight months and eight days after rook was last furnished. This conclusion is wrong because there is nothing in the record to support the finding Tobin had a contract, of any kind, to supply all of the base rock for the parking lot project. We further explored this matter at oral argument before this court and Tobin’s response confirmed the fact no contract for a package deal existed for the furnishing of the necessary rock and Jordon was free to buy Rock elsewhere if it desired or any was needed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monarch Build v. DLH Holdings
567 P.3d 831 (Court of Appeals of Kansas, 2025)
Gleason & Son Signs v. Rattan
335 P.3d 1196 (Court of Appeals of Kansas, 2014)
W & W Steel, LLC v. BSC Steel, Inc.
944 F. Supp. 2d 1066 (D. Kansas, 2013)
Alliance Steel, Inc. v. Piland
187 P.3d 111 (Court of Appeals of Kansas, 2008)
State Ex Rel. Stovall v. Reliance Insurance
107 P.3d 1219 (Supreme Court of Kansas, 2005)
Mutual Savings Ass'n v. Res/Com Properties, L.L.C.
79 P.3d 184 (Court of Appeals of Kansas, 2003)
Haz-Mat Response, Inc. v. Certified Waste Services Ltd.
910 P.2d 839 (Supreme Court of Kansas, 1996)
Haz-Mat Response, Inc. v. Certified Waste Services Ltd.
896 P.2d 393 (Court of Appeals of Kansas, 1995)
Bethlehem Steel Corp. v. National Cooperative Refinery Ass'n
871 P.2d 1282 (Court of Appeals of Kansas, 1994)
J. Walters Construction Co. v. Greystone South Partnership, L.P.
817 P.2d 201 (Court of Appeals of Kansas, 1991)
Pioneer Operations Co. v. Brandeberry
789 P.2d 1182 (Court of Appeals of Kansas, 1990)
Kansas Lumber Co. v. Cheng-Yuan Wang
733 P.2d 1266 (Court of Appeals of Kansas, 1987)
DaMac Drilling, Inc. v. Shoemake
713 P.2d 480 (Court of Appeals of Kansas, 1986)
Cornwell v. Jespersen
708 P.2d 515 (Supreme Court of Kansas, 1985)
Lewis v. Wanamaker Baptist Church
692 P.2d 397 (Court of Appeals of Kansas, 1984)
Fidelity Savings Ass'n v. Witt
665 P.2d 1108 (Court of Appeals of Kansas, 1983)
Mai v. Youtsey
646 P.2d 475 (Supreme Court of Kansas, 1982)
Kopp's Rug Co. v. Talbot
620 P.2d 1167 (Court of Appeals of Kansas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
549 P.2d 1376, 219 Kan. 701, 1976 Kan. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holiday-development-co-v-j-a-tobin-construction-co-kan-1976.