Berthot v. Stroble

494 P.2d 1133, 208 Kan. 839, 1972 Kan. LEXIS 510
CourtSupreme Court of Kansas
DecidedMarch 4, 1972
Docket46,263
StatusPublished
Cited by2 cases

This text of 494 P.2d 1133 (Berthot v. Stroble) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berthot v. Stroble, 494 P.2d 1133, 208 Kan. 839, 1972 Kan. LEXIS 510 (kan 1972).

Opinion

The opinion of the court was delivered by

Owsley, J.:

This is an action to foreclose a subcontractor’s mechanic’s lien. Judgment was entered in favor of the plaintiff. The defendant landowner appeals claiming the subcontractor’s lien was not filed within the statutory period of sixty days. (K. S. A. 60-1103 [repealed L. 1967, Ch. 325 (now K.S.A. 1971 Supp. 60-1103)].)

A brief statement of the facts follows.

In the year 1965, James Coleman, doing business as Coleman Equipment Company in Independence, Kansas, was a dealer for Behlen Buildings. On February 27, 1965, Coleman as contractor entered into a contract with defendant for the sale and construction of a Behlen Curvet Building on defendant’s land. In August of 1965, Coleman and the plaintiff entered into a subcontract by which plaintiff acting as subcontractor would construct a building slab and erect the Behlen Building. Coleman entered into a subcontract *840 to purchase a prefabricated building from Behlen Manufacturing Company.

Plaintiff began erection of the building on September 21, 1965. On October 18, 1965, plaintiff completed erection of the building and on October 20, 1965, plaintiff billed Coleman in full for the erection of the building.

When plaintiff submitted his statement to Coleman, all work was completed except an obligation of subcontractor Behlen to provide fiber glass light panels. Fiber glass light panels were specified in the Behlen subcontract, but steel panels were installed in the building since proper fiber glass light panels were not received from the Behlen Manufacturing Company. On November 22 and 23, 1965, plaintiff-subcontractor returned to the job site with a set of fiber glass panels provided by Behlen Manufacturing Company, but the panels would not properly fit. Behlen’s engineers went to the job site to determine what action should be taken.

On December 14, 1965, the plaintiff-subcontractor submitted a statement to Behlen Manufacturing Company in the amount of $177.00 for work performed on October 13, 1965, and November 22 and 23, 1965, which work was done by plaintiff in attempting to install fiber glass panels. On December 27, 1965, Behlen Manufacturing Company issued a check in the sum of $177.00 to the plaintiff.

Behlen Manufacturing Company then sent to the job site a new set of panels which plaintiff installed on December 30, 1965. Additional work was done on the panels by the plaintiff on February 5, 1966, for which Behlen was again billed by plaintiff. This time Behlen paid plaintiff-subcontractor $169.00 for the work performed.

On February 28,1966, the plaintiff filed a subcontractor’s lien with the Clerk of the District Court of Montgomery County, Kansas. The lien did not mention any work done or charges made subsequent to October 20, 1965.

The trial court made the following findings of fact and conclusions of law:

“1. The work performed by Berthot Construction Company after October 20, 1965, was part of the original contract and its performance was necessary to complete the job.
“2. The defendant Coleman was not a general agent of the Behlen Manufacturing Company.
"3. The Behlen Manufacturing Company and the plaintiff, Berthot Construction Company did not enter into a separate contract for the work performed after October 20, 1965.
*841 “A. Plaintiff subcontractor’s lien filed February 28, 1966 was filed within the statutory period.”

After considering a motion to amend the judgment, the trial court further stated:

“The defendant argues in his motion the existence of a new contract between Beblen Manufacturing Company and the Berthot Construction Company. The Court has found that no such contract existed and is of the opinion that the existence of such a contract would in no way affect the performance required under the original contractual arrangements between the Coleman-Stroble and Berthot Manufacturing Company. The satisfactory completion of the roof was part of the original contract. The defendant Stroble didn’t regard the contract as completed as he withheld and still holds $1200.00 of the original contract price. The work performed by Berthot Construction Company after October 20, 1965, was necessary to the completion of the original contract. The fact that Behlen Manufacturing Company paid Berthot Construction Company for the additional time, trouble and work they were required to perform because of the defective panels does not affect and is not deductible from the original contract price.”

The defendant does not argue that the findings of fact made by the trial court are not supported by the evidence. He first claims that the work was completed on October 20, 1965, and the work performed by the plaintiff thereafter did not extend the time of completion of the project. If the time of completion was not extended by the work of plaintiff after October 20, 1965, the lien was not filed in time.

The trial court found the work was not completed until the plaintiff installed the fiber glass panels on December 30, 1965, and pointed out the installation of the fiber glass panels was part of the original contract between the contractor and the defendant landowner. Fiber glass panels were required in the original specifications.

We have held that the subcontractor is bound by the contract between the contractor and the landowner. (Lang v. Adams, 71 Kan. 309, 80 Pac. 593; Eggleston v. White, 113 Kan. 325, 214 Pac. 623.) We have also held that trivial isolated orders cannot serve to extend the time within which to file a mechanics lien. (Star Lumber & Supply Co. v. Mills, 186 Kan. 204, 349 P. 2d 892.)

In Benner-Williams, Inc. v. Romine, 200 Kan. 483, 437 P. 2d 312, the contractor installed certain cabinets except the end splash for the cabinet top which was not installed until later since it was not available at the original installation time. The court held that the time for filing a mechanic’s lien was extended since the installation *842 of the end splash was part of the original negotiations and stated the rule as follows:

. . The test, under K. S. A. 1967 Supp. 60-1101 as to the time when a piece of work is completed in order to preserve a lien, is whether the unfinished work was a part of the work necessary to be performed under the terms of the original contract to complete the job and comply in good faith with the requirements of the contract. (Citing cases.) The ‘end splash,’ for which no additional charge was made, was part of the original contract, and its installation was necessary to complete the job. It is unrefuted that the delay in installation arose because of the lack of material, rather than any bad faith on the part of the appellee.” (p. 487.)

Defendant argues the rule in Benner-Williams is not applicable because it involved a contractor, not a subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holiday Development Co. v. J. A. Tobin Construction Co.
549 P.2d 1376 (Supreme Court of Kansas, 1976)
Stickney v. Murdock Steel & Engineering, Inc.
512 P.2d 339 (Supreme Court of Kansas, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
494 P.2d 1133, 208 Kan. 839, 1972 Kan. LEXIS 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berthot-v-stroble-kan-1972.