Maryland Casualty Co. v. Shafer

208 P. 197, 57 Cal. App. 573, 1922 Cal. App. LEXIS 471
CourtCalifornia Court of Appeal
DecidedMay 4, 1922
DocketCiv. No. 2438.
StatusPublished
Cited by4 cases

This text of 208 P. 197 (Maryland Casualty Co. v. Shafer) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. Shafer, 208 P. 197, 57 Cal. App. 573, 1922 Cal. App. LEXIS 471 (Cal. Ct. App. 1922).

Opinion

BURNETT, J.

This is a companion case to numbers 2439 and 2440 (post, pp. 580, 585 [208 Pac. 192, 194]), in which the opinions are filed herewith. The appellants herein are laborers and materialmen who claim under the bond executed by plaintiff for their benefit. The bond was given in accordance with the requirement of section 1 of said “act to secure the payment of the claims of material-men, mechanics, or laborers, employed by contractors upon state, municipal or other public work,” to which act ref *574 erenee is made in the other opinions. (Stats. 1897, p. 201.) The trial court found: ‘1 That there is due and unpaid from defendant, M. T. Shafer, to each of the following persons named in this paragraph, for and account of work and labor performed, rental of teams and equipment, supplies and materials furnished under and pursuant to the contract set forth in the complaint herein by and between the said M. T. Shafer and said county of Tulare, by each of the following persons together with interest, the following sums.” Then follow the names with some typographical errors of all the appellants herein except Luis Clarín, H. E. French, Blakeley Hughes, Morris & Co., Nick Pazin, and Steve Pazin, together with the respective amounts due' them.

However, the court further found: “That each and every of the following parties to this action who did not file a complaint, answer or cross-complaint praying judgment against said Maryland Casualty Company on said materialmen’s bond within six months from the time he filed a verified statement with the board of supervisors is barred from any relief against said Maryland Casualty Company by the provisions of the statute of 1897 and amendments thereto, providing for the execution of said materialmen’s bond.” Then follow the names of all but four of appellants herein. Said finding was based upon said statute (Stats. 1915, p. 926) providing: “At any time within six months after the filing of such claim the person, company or corporation filing the same may commence an action against the surety or sureties on the bond, specified and required in section one thereof.”

[1] We are entirely satisfied, though, that the trial court made a wrong application of said provision. Upon principle and authority we are convinced that the filing of the complaint by plaintiff suspended the operation of said statute of limitations. Said complaint was filed before the expiration of six months after the verified claims were filed with the board of supervisors, and it set forth the contract and the whole transaction upon which the claims of appellants depend; and their appearance in the action, in response to the invitation of respondent and the command of the court, for the very purpose of having their claims adjudicated, must be regarded as though made at the time *575 the complaint was filed. If the action were brought by the maker of a promissory note against the payee to determine its validity, it would hardly be questioned, we think, that the payee would be allowed to maintain the legal integrity of the note and to establish the obligation of the maker, although in the meantime the statutory period of limitations had expired. In this ease, the whole issue as to the rights and obligations of the parties is tendered by the complaint, and any defense or counterclaim relating to the instrument which is brought in question is cognizable as of the time when the litigation is instituted.

A similar ease to this is McDougald v. Hulet, 132 Cal. 154 [64 Pac. 278], wherein the action was brought by a surety, “who had signed a joint and several guaranty of rent payable under a lease, to have it decreed what amount was due and unpaid to the lessor, and that the other surety, and corporation of which he was president, were principal debtors, and that they be compelled to pay the unpaid rent and save plaintiff harmless therefrom,” and it was held that “the lessor may set up in his answer, by way of counterclaim or cross-complaint, the contract of guaranty and the amount due thereunder, and seek judgment therefor against the plaintiff.” It was further held therein that “the filing of the complaint suspended the statute of limitations as to the matters arising out of the transaction pleaded; and where such matter is set forth in the answer, counterclaim or cross-complaint, and arose upon contract and existed at the commencement of the action, the statute of limitations can not run thereupon after the commencement of the action.”

In Perkins v. West Coast Lumber Co., 120 Cal. 27 [52 Pac. 118], the action was by an attorney at law to recover against his client upon a special contract for services and it was held that a counterclaim for damages for bad advice given under the contract alleged and arising out of the transaction set forth in the complaint was not barred by the statute of limitations, “if not so barred at the commencement of the action, notwithstanding the lapse of the period fixed by the statute before the filing of the answer setting forth such counterclaim.”

In 24 R. C. L. 837, the rule as to setoffs and counterclaims is stated as follows: “It is generally held that the *576 object of statutes of setoff was to prevent multiplicity of lawsuits, and not to interfere with or affect the operation of the statute of limitations, and that the statute of limitations applies as well to a demand attempted to be set off as to one upon which an action is brought. A claim which is barred by the statute is not therefore available as a setoff or counterclaim. If, however, a counterclaim or setoff is not barred at the commencement of the action in which it is pleaded it docs not become so afterward, during the pendency of that action.”

It seems difficult to conceive of a situation wherein it would be more manifest than herein that the counterclaim or cross-complaint relates to and depends “upon the contract or transaction upon which the action is brought,” creating the condition for the application of sections 438 and 442 of the Code of Civil Procedure.

Indeed, it was not necessary for the prevailing appellants herein to file a counterclaim or cross-complaint. The facts upon which their claims are based are disclosed by the allegations of the complaint, and it is a fair inference from these allegations that said defendants were entitled to judgment against the plaintiff for the respective amounts. It is true that plaintiff alleged upon information and belief that said claims were invalid, but this should be disregarded as the mere opinion of the pleader, since no reason is assigned nor legal foundation disclosed for its support.

For confirmation of this view we may direct specific attention to its material allegations as they relate to the claim of these appellants. In paragraph 2 it appears that on February 9, 1918, the contract was executed for the construction of the highway, and the various provisions of said contract are set out, including the requirement that the contractor should furnish said bond for the payment of laborers and materialmen and that he should pay all such claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham v. California Drilling Exploration Co.
122 P.2d 88 (California Court of Appeal, 1942)
Union Sugar Co. v. Hollister Estate Co.
47 P.2d 273 (California Supreme Court, 1935)
Hubbard v. Robert B. Wallace Co.
208 N.W. 730 (Supreme Court of Iowa, 1926)
Whittier v. Visscher
209 P. 23 (California Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
208 P. 197, 57 Cal. App. 573, 1922 Cal. App. LEXIS 471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-shafer-calctapp-1922.