Maryland Casualty Co. v. Shafer

208 P. 192, 57 Cal. App. 580
California Court of Appeal·Decided May 4, 1922·No. Civ. No. 2439.·Published·Cited by 12 cases

Opinion

FINCH, P. J.

The county of Tulare and the defendant M. T. Shafer, on the 9th of February, 1918, entered into *581 a contract by the terms of which Shafer agreed to construct a concrete highway for the county. Shafer completed the construction of the highway and the same was accepted by the county January 28, 1919. He failed, however, to pay many persons for labor, material, supplies, team hire, and rental of equipment employed, furnished, and used in the construction of the work. He also made assignments to various persons of sums due or to become due under the contract, and which remain unpaid. The plaintiff, as surety of the contractor, brought this action against the county, the contractor, and all claimants under the contract to secure an adjudication of their respective rights in and to the unpaid installments due from the county and the plaintiff’s liability under its contracts of suretyship. The various claimants filed cross-complaints setting up their respective claims to the unpaid installments and their rights of recovery against the plaintiff. The county paid into court the balance due under the contract, $12,919.81, to be distributed in such manner and to such parties as the court might adjudge, and none of the parties are now claiming anything against the county. Prom the judgment rendered, three separate appeals are being prosecuted. This appeal is by Thompson Brothers from that part of the judgment denying recovery against the plaintiff and adjudging that other parties have superior rights to payment out of the unpaid installment.

The contract provides “that the contractor shall pay all bills for labor, team hire, material and supplies contracted for by him on account of the work herein contemplated, when the same becomes due and payable.” By the terms of the contract Shafer was required to furnish “a good and sufficient bond and undertaking in the sum of $16,426.55 conditioned for the faithful performance of this contract by the contractor, according to the terms and provisions herein expressed.” Pursuant to this requirement, Shafer and the plaintiff executed a “bond for faithful performance of contract” in the usual form, providing, among other things, that the contractor “shall in all things stand to and abide by and well and truly keep and perform the covenants, conditions, stipulations, contracts, agreements and obligations in the foregoing contract, . . . on his part to be kept or performed at the time and in the *582 manner therein specified . . . and shall idemnify and save harmless the said county of Tulare.”

[1] It is contended that the plaintiff is liable under the faithful performance bond for the claim of Thompson Brothers. In support of such contention the following cases are cited: French v. Farmer, 178 Cal. 218 [172 Pac. 3102 ] Fuller v. Alturas School Dist., 28 Cal. App. 609 [153 Pac. 743]; Callan v. Empire State Surety Co., 20 Cal. App. 483 [129 Pac. 978, 981], If the faithful performance bond were the only 'one furnished, appellant’s position would seem to be invulnerable, but the contract required and Shafer and the plaintiff executed a separate bond in express compliance with the requirements of the act of 1897 (Stats. 1897, p. 201), and acts amendatory thereof, entitled “An act to secure the payment of the claims of materialmen, mechanics, or laborers, employed by contractors upon state, municipal or other public work.”

Liability under a contract of suretyship, as under other contracts, is dependent upon the intention of the parties thereto. In the discussion of a similar question in French v. Farmer, supra, it is said: “If . . . any effect whatever is to be given to this clause in the condition of the bond, it must be held that it was the intention of the parties to benefit such third persons. . . . The courts of Nebraska Missouri, Iowa, Indiana, and Michigan seem to hold to the view that if it can be fairly said from either the contract or the bond, which are to be construed together, that the parties intended to and did agree to pay such third persons, a suit could be brought on such bond by such third person to recover upon the promise so made for his benefit.” Here, in compliance with the contract and the statute, a separate bond was given to secure payment of claims of the character under consideration and it would be unreasonable to hold that the parties intended the faithful performance bond to secure the same claims. The Statute of 1897 (as amended by Stats. 1911, p. 1422) provides that the claimants “shall, within ninety days from the time such contract is completed, file with the . . . board of supervisors ... a verified statement of such claim.” Concededly appellant failed to file such a claim and is therefore precluded from recovering on the bond given pursuant to the requirements of that statute. Such failure *583 affords no ground for relief under the faithful performance bond manifestly intended for a different purpose.

[2] Pursuant to the provisions of subdivision 11 of section 2643 of the Political Code, the contract provides that the county shall retain twenty-five per cent of the estimated value of the work for thirty-five days after the acceptance thereof. The contract further provides that the county “may at its option, retain out of any amounts' due the contractor, a sum sufficient to cover and pay any such unpaid bills and claims, provided that sworn statements of said bills and claims have been filed in the office of the board of supervisors on or before the date on which the final payment due the contractor under this contract, shall be made by the first party through its board of supervisors, as hereinafter set forth in article XIV of this contract, and not later than ninety days after the completion and acceptance of the work.” As stated, the county retained, under this provision, $12,919.81 due under the contract, that sum being less than twenty-five per cent of the value of the work. The court found that valid claims, duly verified, were filed in due time with the board, aggregating more than the amount retained by the county. Appellant did not so file a verified claim but filed an order, signed by the contractor, for the amount of such claim. It is now contended that appellant was entitled to payment out of the moneys retained by the county and deposited in court as stated; that Shafer’s order operated as an assignment of the sum retained by the county to the amount of the order; and that the plaintiff had no right or equity in the fund reserved in so far as it had been assigned by Shafer. In support of such contention appellant relies on the cases of Adamson v. Paonessa, 180 Cal. 157 [179 Pac. 880], and American Surety Co. v. Empire Securities Co., 185 Cal. 586 [197 Pac. 941]. The first case relates to a contract for street work under the Improvement Act of 1911 (Stats. 1911, p. 730), and the latter to similar work under the Vrooman Act (Stats. 1885, p. 147). In neither case did the contract provide for a reserve fund as in the ease at bar. In Adamson v. Paonessa, supra, this distinction is clearly pointed out by the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Maryland Casualty Co. v. Shafer, 208 P. 192, 57 Cal. App. 580 (Cal. Ct. App. 1922).

208 P. 192 (Maryland Casualty Co. v. Shafer) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States Fid. & Guar. Co. v. OAK GROVE UNION SCH. DIST. OF SONOMA CTY.
205 Cal. App. 2d 226 (California Court of Appeal, 1962)
Webb v. Crane Co.
80 P.2d 698 (Arizona Supreme Court, 1938)
Street v. Pacific Indemnity Co.
79 F.2d 68 (Ninth Circuit, 1935)
Lamson Co., Inc. v. Jones
24 P.2d 845 (California Court of Appeal, 1933)
Summerbell v. Weller
294 P. 414 (California Court of Appeal, 1930)
Los Angeles City School District v. Tucker
278 P. 507 (California Court of Appeal, 1929)
Castro v. Malcolm
226 P. 976 (California Court of Appeal, 1924)
Maryland Casualty Co. v. Shafer
208 P. 194 (California Court of Appeal, 1922)