In re Scofield Co.

215 F. 45, 131 C.C.A. 353, 1914 U.S. App. LEXIS 1210
CourtCourt of Appeals for the Second Circuit
DecidedJune 27, 1914
DocketNo. 244
StatusPublished
Cited by27 cases

This text of 215 F. 45 (In re Scofield Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Scofield Co., 215 F. 45, 131 C.C.A. 353, 1914 U.S. App. LEXIS 1210 (2d Cir. 1914).

Opinion

ROGERS, Circuit Judge.

A contract was made by the United States and the Scofield Company, a New York corporation, for the erection at Hampton Roads, Va., ,of certain piers and for the dredging of the basin lying between the arms of the piers and for the deepening of the channel of approach to the basin from deep water. To secure the prompt and satisfactory performance of the contract, and in accordance with the act of Congress passed February 24, 1905, c. 778, 33 U. S. Statutes at Large, p. 811 (U. S. Comp. St. Supp. 1911, p. 1071) a bond was duly executed by the Scofield Company in the penal sum of $100,000 with the Fidelity & Deposit Company of Maryland as surety. In this bond the Scofield Company agreed and covenanted to perform the work called for under its contract and in addition agreed to “promptly make full payments to all persons supplying it labor or materials in'the prosecution of the work provided for in said contract.”

The government agreed to pay the contractor $385,000 for the work on the basis of estimates of work done, a percentage of 10 per centum to be reserved from each payment “until the, final completion and acceptance of the work.” The contract was entered into in November, 1906, and the work" was completed on September 20, 1907, and was accepted by the United States. The Scofield Company (the contractor) went into bankruptcy on September 23, 1907, and on March, [47]*471908, the United States paid over to the receivers of the bankrupt Scofield Company the sum of $45,453.66 and in September of the same year the additional sum of $985, which sums were the reserved percentages which the government had retained in its hands in accordance with the terms of the contract.

The Scofield Company • had left unpaid claims of persons who had supplied it with labor and materials in the prosecution of the work it performed for the government under the contract above mentioned, and the amount of these unpaid claims aggregated $139,781.60. The Fidelity Company, in discharge of its obligation as surety for the Scofield Company, satisfied these claims, and the total amount so expended was $85,625, the claimants having assigned their claims to the Fidelity Company on the payment to them of that amount. The Fidelity Company, therefore, insists that, as it was under legal obligations as surety on the bond to satisfy these unpaid claimants, and as it has satisfied them, it is now entitled to assert an equitable lien on the reserved fund of some $46,000, which the United States retained in its hands in paying the contractor, but which, as we have seen, it later turned over to the receivers of the bankrupt, and which is now in the hands of the trustee in bankruptcy. The question thus presented is whether, under the circumstances stated, the surety of the bankrupt contractor who has paid the claims of the laborers and materialmen has any equity in this so-called reserved fund which it can assert to the exclusion of the general creditors.

In 1894 Congress passed an act for the protection of persons furnishing materials and labor for the construction of public works. That act provided that any persons thereafter entering into a formal contract with the United States for the prosecution of any public work should be required to execute the usual penal bond, with the additional obligation that such contractor would promptly make payments to all persons supplying him with labor and materials in the prosecution of the work, and giving a right of action to such person or persons who had not been paid for their labor or materials and authorizing such person or persons to bring suit in the name of the United States for his or their own benefit against the contractor and his sureties; it being also provided that any such action should not involve the United States in any expense. Act Aug. 13, 1894, c. 280, 28 Stat. 278 (U. S. Comp. St. 1901, p. 2523).

In 1895 an additional act was passed which amended the previous act. This act provides that any person furnishing work or materials may intervene and be made a party to any action instituted by the United States on the bond of the contractor, and have his rights and claims adjudicated in such action, but subject to the priority of the claim of the United States, and if suit is not instituted by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials for which payment has not been made is authorized, subject to certain limitations, to bring suit on the bond in the name of the United States. U. S. Statutes at Targe, vol. 33, p. 811,

[48]*48These acts authorize suits upon the bond, the suits to be brought in the name of the United States and without expense to the United States. No suit was brought upon the bond given by the Scofield Company, and none was necessary, for the surety on the bond has satisfied the claimants. And in satisfying the claimants there is no doubt but that the surety, the Fidelity Company, has acted under a legal obligation and not as a volunteer.

There is nothing in this record to indicate that the United States withheld the reserved percentages for the' benefit of the, subcontractors, unless such intention can be inferred from the language of the bond, which made it the duty of the contractor to pay promptly the subcontractors. The contract itself, in providing for withholding the percentages, does not state or explain the reason, at least so far as this record shows. It simply states that they may be withheld “until the final completion and acceptance of the work.” This might seem to indicate that the purpose was simply to secure the government in case the work was not prosecuted promptly and faithfully, for the contract expressly provided that if for any of the reasons stated in the contract the United States found it necessary to terminate the contract, then it might deduct from the reserved percentages which it had withheld whatever sums it expended in completing the contract in excess of the stipulated price, and it allowed certain other deductions to be made. And there was no authority given to pay any subcontractors or deduct from the reserved fund any sums paid to any such persons. Nevertheless when the contract is construed in its entirety and in -connection with the obligations imposed by the bond, it will be found that an equity was created in favor of the surety in the reserved fund to which it is the duty of this court to give effect.

In Lawrence v. United States (C. C.) 71 Fed. 228 (1896) decided by Circuit Judge Simonton, the court considered the rights of persons supplying labor and materials to a contractor with the government of the United States, where the government had withheld from the contract price certain sums of money under conditions somewhat similar to those found in the 'contract made between the United States and the Scofield Company in the case at bar. In that case the court said:

“But these laborers and materialmen have no rights as against the government, rights which can be enforced. There is no privity between them and the government. They are recipients of its bounty, debtors to its good will, objects of its provident care, in whose favor, suo motu, it exercises its right and privilege to withhold the money until their claims are satisfied. Nor have they any specific interest in the money so withheld. It is not necessarily applicable to their claims.”

In that case the United States had concluded a contract for building a courthouse and post office for the sum of $76,290.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Commonwealth of Pa., Dept. of Highways
349 F. Supp. 1370 (E.D. Pennsylvania, 1972)
Logan Planing Mill Co. v. Fidelity & Casualty Co. of New York
212 F. Supp. 906 (S.D. West Virginia, 1962)
Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
In Re Dutcher Construction Corporation
197 F. Supp. 441 (W.D. New York, 1961)
Atlantic Refining Co. v. Continental Casualty Co.
183 F. Supp. 478 (W.D. Pennsylvania, 1960)
Philadelphia Industrial Corp. v. Upper Dublin Township
169 F. Supp. 725 (E.D. Pennsylvania, 1959)
In Re Massachusetts Bonding and Insurance Company
259 F.2d 33 (Second Circuit, 1958)
Massachusetts Bonding & Insurance v. New York
259 F.2d 33 (Second Circuit, 1958)
Munsey Trust Co. v. United States
67 F. Supp. 976 (Court of Claims, 1946)
In Re Flotation Systems, Inc.
65 F. Supp. 698 (S.D. California, 1946)
Maryland Casualty Co. v. City of Pittsburgh
51 F. Supp. 459 (W.D. Pennsylvania, 1943)
In Re L. H. Duncan & Sons
127 F.2d 640 (Third Circuit, 1942)
United States Fidelity & Guaranty Co. v. Sweeney
80 F.2d 235 (Eighth Circuit, 1935)
Sundheim v. Philadelphia School District
166 A. 365 (Supreme Court of Pennsylvania, 1933)
Maryland Casualty Co. v. Shafer
208 P. 192 (California Court of Appeal, 1922)
American Surety Co. of New York v. Finletter
274 F. 152 (Third Circuit, 1921)
Wasco Co. v. New England Equitable Ins.
172 P. 126 (Oregon Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
215 F. 45, 131 C.C.A. 353, 1914 U.S. App. LEXIS 1210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-scofield-co-ca2-1914.