American Surety Co. of New York v. Finletter

274 F. 152, 1921 U.S. App. LEXIS 1324
CourtCourt of Appeals for the Third Circuit
DecidedJune 6, 1921
DocketNos. 2457, 2624
StatusPublished
Cited by21 cases

This text of 274 F. 152 (American Surety Co. of New York v. Finletter) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Surety Co. of New York v. Finletter, 274 F. 152, 1921 U.S. App. LEXIS 1324 (3d Cir. 1921).

Opinion

WOODLEY, Circuit Judge.

These cases, growing out of the same business failure, have as many angles as they have parties and subjects-matter. We shall endeavor to view them separately in so far as that is possible.

The questions concern the distribution of funds arising from a receivership in equity. Peoples Brothers, Inc., a Pennsylvania corporation, hereinafter called the Contractor, was under several contracts with the City of Philadelphia for the construction of public works. These contracts called for partial payments as construction progressed and for deferred payments pending completion.

[1] Before the works had been completed the Contractor defaulted and a receiver was appointed. With the receivership, the rights and [154]*154equities of all parties — contractors, claimants, creditors — became fixed, and a status was established from which all matters, past and prospective, are to be gauged. The court receiving the estate must regard this status as the chart to guide and govern its subsequent administration and final distribution. The rights of contract parties, of creditors of different classes, and of the receiver, are to be dealt with as they were found legally to exist when receivership brought the business to an end and at the same time brought into active operation laws applicable to everything that had gone before and to everything that was to follow. Regarding the appointment of a receiver as the fact, and the date of his appointment as the time, on which every phase of the instant controversies turns, we shall address ourselves to the questions brought here for revi&w.

Byberry Farms.

[2] Peoples Brothers, Inc., entered into a contract with the City of Philadelphia for the erection of a power house at Byberry Farms, a municipal property. Failing to complete the work, a receiver was appointed. From the status of the contractor’s affairs established by the receivership two things immediately developed: First, the receiver refused — as he had the right to do — to continue the contract and complete the work;- second, his refusal brought to light a fact, anterior to the receivership ; namely, that when the Contractor entered into this contract, he gave the City two bonds with the American Surety Company of New York as surety; one conditioned upon the completion of the work, and the other conditioned upon the payment of all claims for labor performed and material furnished under the contract. Resort to both bonds was had at once. The Surety Company completed the contract at a cost of $4,725.60 and paid in full all claims against the Contractor for labor and material amounting to $11,188.34.

During the progress of the work the City retained 15 per cent, of the amount due, of which 10 per cent, was to be paid on the completion of the contract and 5 per cent, one year thereafter. After completing the contract the City paid the Surety Company $7,231.60, being the final payment less the 5 per cent, of the contract price to be retained for one year. Of this sum the receiver demanded $3,150.40, representing 10 per cent, of the work claimed to have been -completed by 'the Contractor according to the last certificate by the architect prior to stopping work. Contesting the claim of the receiver the Surety Company turned over this sum to the receiver to await the outcome of this litigation.,

The special master and the District Court recognized the surety's right under one bond to be reimbursed in full out of funds retained, and later paid, by the City for its cost of completing the contract, but denied the surety the right under the other bond to apply the balance of the money, so obtained from the City, on account of the amount it had expended in paying claims of laborers and materialmen. By its decree the District Court awarded this disputed balance to the receiver for the benefit of general creditors, thereafter treating the surety as a [155]*155general creditor in the amount of its disbursements. From this de-cretal disposition of the fund the Surety Company took this appeal, presenting as the question involved the following:

Where a surety gives bond to a City for the payment of sub-contractors upon municipal work and pays their claims in full, is the surety not entitled to be reimbursed therefor out of retained percentages under the contract as against the receiver of the defaulting contractor?

This question was argued ou two theories, that of equitable sub-rogation and of assignment. The theory of equitable subrogation constituted the main contention and was argued by both parties with great vigor; and on that theory the case was decided. This issue had its rise in the written application made by the contractor to the Surety Company for the bond in question, which contained a paragraph of which the following is a part:

“VII. * * * And the Indemnitor (Contractor) further agrees in the event of any broach or default on his part in any of the provisions of the contract covered by said suretyship that the said surety, as surety, shall be subrogated to all the rights and properties of the Indemnitor in such contract. * * * ”

The receiver, the special master, and the District Court took the perfectly sound position that neither the subrogation contemplated by the quoted provision nor subrogation on any other theory is applicable to this case, because:

“As under the Pennsylvania decisions the laborers and materialmen did not have any right against the percentages retained by the City, but are merely in a position of general creditors of Peoples Brothers, Ine., the right of subrogation which the Surety Company has cannot arise any higher than that of the creditors whom it has paid.”

In this state of the law- — laborers and materialmen having no rights to reserved percentages — -there were, as to them, no rights to which the Surety Company could be subrogated. Likewise, Peoples Brothers, Inc., had no rights in the fund to which the Surety Company could he subrogated. Obviously, there was no right of subrogation anywhere.

The Surety Company recognized this, for it conceded throughout that sub-contractors had no lien on the fund reserved by the City and that this fund could not have been reached by the subcontractors through any process against the City. Indeed, both sides viewed in the same light the controlling decisions of the .Pennsylvania courts in this regard. Lesley v. Kite, 192 Pa. 268, 43 Atl. 959; Philadelphia v. McLinden, 205 Pa. 172, 54 Atl. 719; Sax v. School District, 237 Pa. 68, 85 Atl. 91.

But the Surety Company did not confine its argument to the question of subrogation, whether within or without the terms of the quoted provision in the Contractor’s application for bond, but maintained on authority of Prairie State Bank v. United States, 164 U. S. 227, 17 Sup. Ct. 142, 41 L. Ed. 412 and Henningsen v. United States Fidelity & Guaranty Co., 208 U. S. 404, 28 Sup. Ct. 389, 52 L. Ed. 547, that, as a surety — which had paid all laborers and materialmen and had thus released the contractor from his obligations to them and had also satis[156]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Modart, Inc. v. Penrose Industries Corporation
404 F.2d 72 (Third Circuit, 1968)
Modart, Inc. v. Penrose Industries Corp.
404 F.2d 72 (Third Circuit, 1968)
Modart, Inc. v. Penrose Industries Corp.
293 F. Supp. 1116 (E.D. Pennsylvania, 1967)
In Re Flotation Systems, Inc.
65 F. Supp. 698 (S.D. California, 1946)
Elgin v. Housing Authority
52 F. Supp. 250 (D. Maryland, 1943)
In re L. H. Duncan & Sons
46 F. Supp. 825 (W.D. Pennsylvania, 1941)
DuBois v. United States Fidelity & Guaranty Co.
341 Pa. 85 (Supreme Court of Pennsylvania, 1941)
Dubois v. U.S. Fid. Guar. Co.
18 A.2d 802 (Supreme Court of Pennsylvania, 1941)
Honolulu Iron Works Co. v. Bigelow
33 Haw. 607 (Hawaii Supreme Court, 1935)
Central Tractor & Equipment Co. v. Betz
260 N.W. 269 (South Dakota Supreme Court, 1935)
Walker v. Hartford Realization Co.
74 F.2d 56 (Second Circuit, 1934)
Lowe v. Columbian Nat. Life Ins.
2 F. Supp. 99 (W.D. Pennsylvania, 1932)
Agricultural Credit Corp. v. Scandia American Bank
237 N.W. 823 (Supreme Court of Minnesota, 1931)
Exchange State Bank v. Federal Surety Co.
28 F.2d 485 (Eighth Circuit, 1928)
Geddes v. Reeves Coal & Dock Co.
20 F.2d 48 (Eighth Circuit, 1927)
Mfg. Co. v. . Blaylock
135 S.E. 136 (Supreme Court of North Carolina, 1926)
Robinson Manufacturing Co. v. Blaylock
192 N.C. 407 (Supreme Court of North Carolina, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
274 F. 152, 1921 U.S. App. LEXIS 1324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-surety-co-of-new-york-v-finletter-ca3-1921.