Honolulu Iron Works Co. v. Bigelow

33 Haw. 607, 1935 Haw. LEXIS 10
CourtHawaii Supreme Court
DecidedOctober 31, 1935
DocketNo. 2194.
StatusPublished
Cited by1 cases

This text of 33 Haw. 607 (Honolulu Iron Works Co. v. Bigelow) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Honolulu Iron Works Co. v. Bigelow, 33 Haw. 607, 1935 Haw. LEXIS 10 (haw 1935).

Opinion

*608 OPINION OF THE COURT BY

PETERS, J.

This appeal presents for review the disposition by the trial judge sitting in equity of moneys remaining in the possession of the Territory subject to the terms of a contract for public work, after abandonment by the contractor and completion by the surety, adverse claims to which Avere on the one hand made by furnishers of labor and material and on the other by the surety upon the contractor’s bond.

The facts which are undisputed are in substance as follows : On June 4, 1932, the Territory by its board of har *609 bor commissioners entered into a contract with one K. Asakawa for the construction and completion, according to prescribed plans and amended specifications, of a certain public work, to-wit, a wharf and appurtenances at Honoapu, Hawaii county. The contract and specifications provided that the contractor furnish and pay for all labor, material, tools and equipment required to construct and complete the work for a sum certain; that he furnish satisfactory evidence that the persons, firms or corporations who had done work or supplied material had been paid or satisfactorily secured; that there be retained as a reserve twenty per cent of all progress payments due the contractor and that such retained percentages continue to be retained and should not become payable until full completion and acceptance of the work and until satisfactory evidence was furnished to the board that all claims had been settled as required; that final payment should only be made upon the full and faithful performance by the contractor of his covenants, undertakings and agreements and not until full completion of the work contracted for in accordance with the plans and specifications and its acceptance by the board and not until satisfactory evidence had been furnished that the furnishers of all labor and material had been paid or satisfactorily secured, but in case of the default of the contractor to furnish such evidence of payment or security of the claims of laborers or materialmen as required such amount as might be necessary to meet said claims might be retained from the moneys due the contractor under the contract until the liability should be fully discharged or notice of such liability withdrawn.

The contractor on June 6, 1932, pursuant to and in conformity with the provisions of R. L. H. 1925, s. 161 and s. 2679 as amended by L. 1931, c. 163, gave a bond with the respondent Columbia Casualty Company as surety. In addition to the statutory conditions the bond was also *610 conditioned upon the delivery of the work to the Territory completed, as in the contract specified, free from all liens and claims and without further cost, expense or charge to the Territory.

The application signed by the contractor for the bond contained the following: “That in further consideration of the execution of said bond, the undersigned hereby assigns, transfers and conveys to the surety all the deferred payments and retained percentages, and any and all moneys and properties that may be due and payable to the undersigned at the time of any breach or default in said contract, or that thereafter may become due and payable to the undersigned on account of such contract, or on account of extra work or materials supplied in connection therewith, hereby agreeing that such money, and the proceeds of such payments and properties shall be the sole property of the surety and to be by it credited upon any loss, cost, damage, charge and expense sustained or incurred by it under said bond.”

The contractor proceeded Avith the work but on January 26, 1933, became financially embarrassed and unable to finish the work and abandoned the contract, whereupon the surety, pursuant to arrangements with the board of harbor commissioners) of the facts of Avhich, hoAvever, we are not advised, undertook the completion of the Avork and finished the same. The amended specifications are not a part of the record and such references as are made thereto have their source in quoted excerpts contained in the bill of complaint and admitted as correct by the respondents’ answers.

At or about this same time, as alleged and admitted by the pleadings, the contractor executed another assignment to the surety company but the assignment was not offered in evidence and Ave are not advised of its contents or legal effect. We deem the same, however, immaterial *611 as it could not confer any greater rights upon the assignee than the equitable assignment of June 8, 1932, contained in the application for the bond.

On September 28, 1933, upon “final settlement” by the Territory, as that term is employed in R. L. H. 1925, s. 2679, as amended by L. 1931, c. 163, s. 3, the contracting officer of the Territory determined and certified that the amount deemed by him to be due to the contractor under the contract was the sum of $10,154.88. On August 6, 1934, the petitioners and others, as furnishers of material used in the prosecution of the work, all of whom appear herein either as petitioners or respondents, secured a judgment against the contractor and the surety company in a statutory action on the contractor’s bond, permitted by R. L. H. 1925, s. 2679, as amended by L. 1931, c. 163, s. 3, in the aggregate amount of $26,237.84. The bond being inadequate to pay the aggregate of the respective amounts adjudged to be due to the judgment creditors judgment was given to each creditor pro rata of the amount of recovery and the surety on the bond paid the full amount of its obligation into court for distribution pursuant to the judgment. The aggregate of the claims of the judgment creditors exceeds the net proceeds of the bond by $7199.84. Prom the amount found due the contractor upon final settlement there was paid to the surety by the Territory, as the latter’s estimated cost of the completion of the work, the sum of $4635, leaving a balance in the possession of the Territory of $5519.88.

In the trial court the surety claimed that it was entitled to the entire remaining balance due from the Territory (a) as assignee under the assignment included in its principal’s application for a bond, dated June 8, 1932, (b) as assignee under the alleged assignment of January 26, 1933, and (c) as subrogee of the Territory; or in the alternative it was entitled to be reimbursed in the sum of *612 $1767.95, necessarily incurred by it in completing the contract, in addition to the sum of $4635 previously received by it from the Territory. Said sum of $1767.95 included the sum of $750 paid by the surety to its attorney for services rendered by him “in connection with taking over the contract upon the contractor’s abandonment thereof, advice during time of completion and services re securing cost of completion after the work had been completed by the surety.” On the other hand, the petitioners and the other judgment creditors claimed that the sum of $1767.95 was not costs necessarily incurred in completing said contract in addition to the sum of $4635 previously paid the surety by the Territory, and that they had an equitable lien on the entire remaining balance prior and superior to the rights of the surety therein, considering the latter either as subrogee of the Territory or as assignee of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayer v. Alexander and Baldwin, Inc.
532 P.2d 1007 (Hawaii Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
33 Haw. 607, 1935 Haw. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/honolulu-iron-works-co-v-bigelow-haw-1935.