Allen v. Redward

10 Haw. 151, 1895 Haw. LEXIS 5
CourtHawaii Supreme Court
DecidedOctober 31, 1895
StatusPublished
Cited by11 cases

This text of 10 Haw. 151 (Allen v. Redward) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen v. Redward, 10 Haw. 151, 1895 Haw. LEXIS 5 (haw 1895).

Opinion

OPINION OP THE COURT BY

PREAR, J.

The defendant Redward contracted with, the defendant Hawaiian Lodge to do, for $7234, the carpenter work, wrought and cast iron work and plastering' upon the building known as the Masonic Temple situated on the easterly corner of Hotel and Alakea streets in Honolulu. The contractor abandoned the work before its completion and after $4700 had been paid under the, contract, this being more than was payable for the proportion of work then done. The Hawaiian Lodge thereupon completed the work at a cost exceeding the original contract price. The plaintiff, S. 0. Allen, doing business under the name of Allen & Robinson, claims to have advanced $2392 cash for labor and to have furnished materials of the value of $5194.45, including importation charges, to the contractor for this building. The $4700 paid under the contract was all paid to the plaintiff upon the order of the contractor. The plaintiff now sues for a balance of $2886.45 and interest thereon and claims a lien on the building and lot, under the “Act to Provide for Liens of Mechanics and Material-men,” Oh. 21, Laws of 1888.

The case was tried in the Circuit Court of the Pirst Circuit, jury waived, where judgment was rendered for the plaintiff for $2834.79, besides interest, this being the amount claimed [153]*153less $51.66, the value of materials shown not to have been delivered, and the lien was sustained for this amount npon the building and premises of the defendant Hawaiian Lodge.

The twenty-three exceptions enumerated in the bill of exceptions may be considered in substance under a few heads.

First, the exceptions to the following findings of fact made by the trial court, namely: that all the materials in question were delivered except certain items of the value of $51.66; that the plaintiff advanced cash to the contractor for labor; that there was an agreement between the contractor and the material-man that payments should be applied, first, on account of the cash advanced, and then on account of the materials furnished; that the payments were so applied; that the lien claimed was not for cash advanced; that there was not such confusion in the account that items for which the law gives no lien could not be separated by inspection; and that the materials were not furnished solely on the credit of the defendant Bedward.

These findings of fact, regarded, as they must be, as in the nature of a verdict of a jury, cannot be set aside, there being sufficient evidence to sustain them.

Secondly, evidence of the agreement relating to application of payments was properly admitted. In the absence of an agreement upon this subject with the owner, it was competent for the contractor and material-man to agree upon the application of payments made to the latter upon the order of the former. The rules relating to the application of payments in general apply to cases of this kind. Phill., Mec. Liens, Sec. 287; 2 Jones, Liens, Sec. 1307; 1 Am. Ld. Cas., 3rd Ed., 286, 299.

Thirdly, the Circuit Court correctly held that the amount for which the property may be charged with a lien in favor of a sub-contractor or material-man is not limited to the amount payable by the owner to the contractor.

In a few States, sub-contractors are given no lien at all upon the property, but a lien only on the debt payable by the owner [154]*154to the contractor. In many States a direct lien is given on the property, but with an express limitation to the amount of the original contract price. Under these two classes of statutes, the right of the material-man has generally been held to be controlled by the state of the account between the owner and contractor — the material-man or sub-contractor being merely subrogated to the rights of the contractor.

Under other statutes a direct lien is given upon the property, either without qualifying or limiting expressions as to amount, as in many States, or with expressions clearly showing that there is no limit, as in a few States. Under such statutes, courts have generally held that the material-man may have a lien for the reasonable value of the materials furnished by him, even though in excess of the amount payable to the principal contractor under the original contract.

Our statute is of this nature. It gives a direct lien upon the property to the sub-contractor without limit with reference to the original contract price. The statute provides:

“Section 1. Any person or association of persons furnishing labor or material to be used in the construction or repair of any building, structure, railroad or other undertaking, shall have a lien for the price agreed to be paid for such labor or material (if it shall not exceed the value thereof) upon such building, structure, railroad or other undertaking, as well as upon the interest of the owner of such building, structure, railroad or other undertaking in the land upon which the same is situated.”

This section of the statute gives a lien to “any person furnishing material” and makes no distinction between contractors and sub-contractors. Other sections, 5 and 6, show clearly that sub-contractors were intended to be included.

The lien is “for the price agreed to -be paid.” This may mean the price agreed either between the owner and contractor or between the contractor and material-man. It would naturally mean the price agreed to on one side at least by the “person furnishing the materials” and that would be the sub-contractor if the materials were furnished by him.

[155]*155There is not only no express or implied limit of the sub-contractor's lien to the price agreed between the owner and contractor, but the clause “if it shall not exceed the value thereof,” would seem to have been inserted chiefly for the purpose of preventing collusion between the contractor and sub-contractor whereby they might otherwise bind the owner beyond the real value of the materials or labor. This clause would hardly have been inserted to protect the owner against his own agreement. Indeed, he would ordinarily be estopped from saying that the price he agreed to pay exceeded the real value.

Again, as a rule the price agreed upon between the owner and the contractor is a lump sum for all labor and materials covered by the contract, and in such cases the only “price agreed to be paid for such labor or material” as may be furnished by the several material-men or sub-contractors is the price agreed between them and the contractor.

Section 6, which provides that when the work or material is furnished to a contractor, that is, by a sub-contractor, laborer or material-man, “the owner may retain from the amount payable to the contractor sufficient to cover the amount due or to become due to the person or persons who filed the lien,” may, at first glance, seem to indicate that the Legislature contemplated that there would be sufficient to satisfy all liens out of the original contract price, and that therefore there was no intention to give any further right. ■ But this inference by no means follows. The sub-contractor is given a lien directly on the property, not on the debt payable to the contractor, the owner is not obliged to retain the money; he is merely permitted to do so as one means of protection to himself against the wrong or mistake or inability of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Savings & Loan Ass'n v. Kauaian Development Co.
445 P.2d 109 (Hawaii Supreme Court, 1968)
Honolulu Iron Works Co. v. Bigelow
33 Haw. 607 (Hawaii Supreme Court, 1935)
Wong Wong v. Honolulu Skating Rink, Ltd.
24 Haw. 181 (Hawaii Supreme Court, 1918)
Lewers & Cooke, Ltd. v. Wong Wong
24 Haw. 39 (Hawaii Supreme Court, 1917)
Great Western Sugar Co. v. F. H. Gilcrest Lumber Co.
25 Colo. App. 1 (Colorado Court of Appeals, 1913)
Lucas v. Hustace
20 Haw. 693 (Hawaii Supreme Court, 1911)
H. Hackfeld & Co. v. Hilo Railroad
14 Haw. 448 (Hawaii Supreme Court, 1902)
Allen v. Lincoln
12 Haw. 356 (Hawaii Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
10 Haw. 151, 1895 Haw. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-v-redward-haw-1895.