Great Western Sugar Co. v. F. H. Gilcrest Lumber Co.

136 P. 553, 25 Colo. App. 1, 1913 Colo. App. LEXIS 1
Colorado Court of Appeals·Decided March 10, 1913·No. No. 3870·Published·Cited by 6 cases

Opinions

Morgan,-J.

On rehearing; former opinion withdrawn and the following substituted.

Writ of error to reverse a judgment of the Weld district court in an action against the Sugar Company, hereinafter called the owner, and its principal, contractor, Eggleston, to foreclose a mechanic’s, lien upon a building which the contractor agreed, orally, to construct for the owner, purchasing his material from the Lumber Company, hereinafter called the claimant,r and which filed its lien statement, and began this action, within the required time thereafter. The lien law of 1899 is involved’ No evidence was abstracted. There is some controversy over service by publication on . the principal- contractor, and default thereupon, but the principal- contention is'over the court’s ruling on two1 general demurrers — one to the complaint overruled, one to the answer sustained.

The owner contends that, in case of a contract between the owner and contractor, regardless.of the amount of the contract price,-sub-contractors and material men, [3] in order to maintain a lien for any more than may he owing to the contractor when the lien statement is filed for record, mnst serve on the owner a written notice that they have performed labor or furnished material, etc., independent of the service’ on the owner of a copy of the lien statement; and claims the right to pay the contractor, in the absence-of such notice, or until such notice is served, at such times as the contract may provide, and, in full, at the expiration of thirty-five days after the completion of the contract, if no such notice has been served prior-thereto. The claimant contends that no such notice is required, in any case, 'if the contract price is $500.00, or less, and, as a broader contention, not in any case, unless the contract or a memorandum thereof is filed with the county recorder. • ’

These contentions must be determined from the lien act of 1899, and particularly from sections one and two, being sec. 4025 and 4026, of the Eev. Stat., 1908.

See. 4025, after providing, generally, that mechanics, sub-contractors and material men, although dealing with the contractor alone, have a lien upon the property of the owner benefited, states:

“In case of a contract for the work, between the reputed owner and a contractor, the lien shall extend to the entire contract price and such contract shall operate as a lien in favor of all persons performing labor or services or furnishing materials as herein provided under contract, express or implied, with said contractor, to the extent of the whole contract price1; and after all such liens are satisfied^ then as a lien for any balance of such contract price in favor of the contractor. All such contracts- shall be in writing when the’ amount to be paid thereunder exceeds five hundred dollars, and shall be subscribed by the parties thereto, and the said contract, or a memorandum thereof, setting forth the names of all the parties to the contract, a description of the property [4] to be affected thereby, together.with a statement of the general character of the work to be done, the total amount to be paid thereunder, together with the times or stages of the work for making payments, shall, before the work is commenced, by the owner or reputed owner be filed in the office of the county recorder of the county where the property, or the principal portion thereof, is situated; and in case such contract is not filed, as above provided, the labor done and materials furnished by all persons aforesaid before such contract or memorandum is filed, shall be deemed to have been done and furnished at the personal instance of the owner, and they shall have a lien for the value thereof.”

Sec. 4026, after providing that the contract must provide for payments in installments after work is begun, that 15 per cent must be held for 35 days after the completion, that any payments made prior to dates set shall not affect liens of sub-contractors and material men, that as to them the amount of the contract shall be paid in money and shall not be affected by any indebtedness of the contractor to the owner, states:

“In case such contracts and alterations thereof do not conform substantially to the provisions of this section, the labor done and materials furnished by all persons other than the principal contractor shall be deemed to have been done and furnished at the personal instance and request of the person who contracted with the principal contractor, and they shall have a lien for the value thereof. Any of the 'persons mentioned in section 1," except a principal contractor, may at any time give to the owner or reputed owner or to his superintendent of construction, agent or architect, a written notice that they have performed labor or furnished materials or both to or for a principal contractor, or any person acting by authority of the owner or reputed owner, or that they have agreed to and will do so, stating in general terms [5] the kind of labor or materials and the name of the person to or for whom the same was or is to be done or performed, or both, and the estimated or agreed amount in value, as near as may be, of that already done or furnished or both, and also of the whole agreed to be done or furnished, or both. Such notice may be given by delivering the same to the owner or reputed owner personally, or by leaving at his residence or place of business with some person in'charge; or by delivering it either to his superintendent of-construction, agent or architect, or by leaving it either at his residence or place of business with some person in charge; no such notice shall be invalid or insufficient by reason of any defect of form,- provided it is sufficient to inform the owner or reputed owner of the substantial matters herein provided for, or to put him upon inquiry as to such matters. Upon such notice being given, it shall be the duty of the person who contracted with the principal contractor, to, and he shall withhold from such principal contractor, or from any other person acting under such owner or reputed owner, and to whom, by said notice, the said labor or materials, or both, have been furnished or agreed to be furnished, sufficient money due or that may become due, to said principal contractor, or other persons, to satisfy such claim, and any lien that may be filed therefor for record under this chapter, including reasonable costs provided for in this act; and the payment of any such lien, which shall have been acknowledged by such principal contractor, or other person acting under such owner or reputed owner, in writing to be correct, or which shall have been established by judicial determination, shall be taken and allowed as an offset against any moneys which may be due from the owner, or reputed owner to such principal contractor, or the person for whom such work and labor was performed.”

Sec. 4033 provides that a lien statement must be filed for record, and that sub-contractors and material men [6] must file such statement within two months after completion of the building, and serve a copy of the same upon the owner at or before the time of filing.

Free access — add to your briefcase to read the full text and ask questions with AI

Great Western Sugar Co. v. F. H. Gilcrest Lumber Co., 136 P. 553, 25 Colo. App. 1, 1913 Colo. App. LEXIS 1 (Colo. Ct. App. 1913).

136 P. 553 (Great Western Sugar Co. v. F. H. Gilcrest Lumber Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

HTC CORPORATION v. Olds
486 P.2d 463 (Colorado Court of Appeals, 1971)
Armour & Co. v. McPhee & McGinnity Co.
275 P. 12 (Supreme Court of Colorado, 1929)
Phoenix Title & Trust Co. v. Old Dominion Co.
253 P. 435 (Arizona Supreme Court, 1927)
Kennicott-Patterson Transfer Co. v. Modern Smelting & Refining Co.
26 Colo. App. 135 (Colorado Court of Appeals, 1914)