Bushman Construction Company v. Air Force Academy Housing, Incorporated

327 F.2d 481
CourtCourt of Appeals for the Tenth Circuit
DecidedMarch 2, 1964
Docket7263_1
StatusPublished
Cited by25 cases

This text of 327 F.2d 481 (Bushman Construction Company v. Air Force Academy Housing, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bushman Construction Company v. Air Force Academy Housing, Incorporated, 327 F.2d 481 (10th Cir. 1964).

Opinion

SETH, Circuit Judge.

This is a companion case to Bushman Construction Co. v. Conner, 307 F.2d 888 (10th Cir.), and now pending in the United States District Court for the District of Colorado.

The trial' court granted motions to dismiss and motions for summary judgment on behalf of the various defendants. Bushman Construction Company, the plaintiff below, is appealing such orders.

The present diversity action is based primarily on the general lien statutes *483 of Colorado, Colo.Rev.Stat.1953 Ann., §§ 86-3-1 to -24, and also contains a separate in personam cause of action. Plaintiff-appellant asserts two liens: One for $720,819.95 by reason of the performance of a subcontract known as Subcontract 581, and the other by virtue of the assignment of a lien from The Harrison Engineering & Construction Corporation for $25,125.00. Both of the liens are claimed against certain property in the Armed Forces Housing (Capehart) project at the Air Force Academy in El Paso County, Colorado. Defendants, Del E. Webb Construction Co. (Webb) and Ru-benstein Construction Co. (Rubenstein), were prime contractors on this project, and The Maryland Casualty Company was the surety on the prime contractors’ bond. R.P.R. Construction Co. (R.P.R.), a first tier subcontractor under Webb and Rubenstein, in turn subcontracted a part of its work to the plaintiff-appellant and its alleged joint venturer, W. S. Conner, by the execution of Subcontract 581. The appellee housing corporations of Delaware are the owners of the leasehold estates and the improvements which were constructed. The State Treasurer of Colorado and The Colorado Public Employees’ Retirement Association are joined as defendants by reason of the fact that they are the present owners of the mortgages on the subject leaseholds.

The complaint alleges that the appellant and Conner, as joint venturers, undertook to perform Subcontract 581. Appellant claims that it furnished services, material and labor which contributed to the completion of the work and that appellant received $1,463,780.05 of the contract price of $2,184,600.00. Appellant seeks the difference, $720,819.95, by way of foreclosing a statutory lien. W. S. Conner is not named in the complaint as a party and was not initially joined or served.

As to the assigned lien, the complaint recites the assignment of a $25,125.00 lien claim to the appellant from The Harrison Engineering & Construction Corporation and prays for judgment in this amount, together with a decree foreclosing the lien. This lien arose from the performance of Subcontract 581, but was assigned to appellant individually.

The complaint also seeks a judgment against appellee, The Maryland Casualty Company, for each amount on bonds it executed as surety for the prime contractors.

On December 20, 1960, the motion of The Maryland Casualty Company to dismiss was granted on the ground that Conner, appellant’s joint venturer, was an indispensable party to the action and had not been served with process. This order of dismissal was later applied by a subsequent order to all matters contained in the complaint.

On December 20,1960, the housing corporations’ motion to dismiss was also granted on the ground that Conner was an indispensable party to the claim under Subcontract 581. The court on the same day denied the motion to dismiss as to the claim of the appellant as assignee of the Harrison claim.

Webb’s motion for summary judgment on the ground that payment had been made, that there was no privity between Webb and appellant, and that Conner was an indispensable party was granted on December 28, 1960.

Thereafter appellant moved for an order vacating or modifying the order of dismissal entered on December 20, 1960, to allow the appellant time to serve Conner. At the same time, approximately, appellant filed a motion seeking authority to serve Conner and other parties outside the District pursuant to 28 U.S.C. § 1655, and this motion was granted. On February 6, 1961, the court denied the appellant’s motion to modify the order of dismissal of December 20, 1960. On March 16, 1961, Conner filed his answer, pleading the merits of the case. He denied all the allegations of the complaint and expressly denied there was ever a joint venture.

On April 11, 1961, Webb, Maryland, and the housing corporations filed a joint motion for summary judgment as to the *484 assigned Harrison lien. This joint motion was granted on September 25, 1962, on the ground that under Colorado law, rental of equipment could not be the basis for a lien.

The motion for summary judgment filed by Rubenstein and R.P.R. relating to all of appellant’s claims was. granted September 25, 1962. As to Subcontract 581, the grounds for dismissal were payment and lack of privity of contract between the appellant and these appellees as noted in the December 28, 1960, order. As to the assigned claim, the ground for granting the summary judgments was that the work was not lienable and there was no privity.

Summary judgment in the September 25, 1962, order was also granted to the State Treasurer of Colorado and The Colorado Public Employees’ Retirement Association, the housing corporations, and Webb on the same grounds. An order for final judgment was entered on October 25, 1962.

I.

The Claim Under Subcontract 581.

Under this subcontract to W. E. Conner, which the complaint alleges was performed by a joint venture of appellant and Conner, the claim is made that there is an unpaid balance of $720,819.95. The complaint seeks personal judgments against the appellees and also asserts a lien against the property on which the improvements were constructed.

To dispose of the motions, the trial court properly considered the complaint, depositions, motions, exhibits, and admissions all together. In doing this, the allegations in the pleadings may be evaluated in the light of the depositions and the additional factual material before the court and a determination made whether material issues of fact actually exist. After this has been done, should no material fact “dispositive of right or duty remain in the case,” summary judgment is proper. See Bushman Construction Co. v. Conner, 307 F.2d 888 (10th Cir.), and cases therein cited.

The record before us contains nin® final payment and waiver of lien certificates signed by W. E. Conner. The record further shows that the entire amount due on Subcontract 581 was paid by R.P.R. to Conner or on his accounts. The complaint and the claim of lien assert there was a joint venture between appellant and Conner in the performance of Subcontract 581. Appellant in its complaint is asserting the joint venture did not receive the full payment. The record shows that W. E. Conner was in charge of the performance of the work under the subcontract. Appellant entered the picture primarily in the role of financier and to provide a performance bond. The record shows no dispute between the joint venture and R.P.R. as to the performance of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmidt Construction Co. v. Fast
776 P.2d 1175 (Colorado Court of Appeals, 1989)
In Re the Arbitration Between Lynch & Three Ponds Co.
656 P.2d 51 (Colorado Court of Appeals, 1982)
Jordan v. Elizabethan Manor
593 P.2d 1049 (Montana Supreme Court, 1979)
McNeill v. Allen
534 P.2d 813 (Colorado Court of Appeals, 1975)
W. F. Whitfield v. Nick Gangas
507 F.2d 880 (Tenth Circuit, 1974)
Technical Development Corp. v. United States
202 Ct. Cl. 237 (Court of Claims, 1973)
Chambers v. Nation
497 P.2d 5 (Supreme Court of Colorado, 1972)
Carlson v. Boryla
490 P.2d 700 (Colorado Court of Appeals, 1971)
R. A. Hanley v. Chrysler Motors Corporation
433 F.2d 708 (Tenth Circuit, 1970)
Hanley v. Chrysler Motors Corp.
433 F.2d 708 (Tenth Circuit, 1970)
State Ex Rel. Mayle v. Aetna Casualty & Surety Co.
166 S.E.2d 133 (West Virginia Supreme Court, 1969)
Ingalls Iron Works Co. v. Fehlhaber Corp.
275 F. Supp. 623 (N.D. New York, 1967)
Maryland Casualty Company v. W. S. Conner
382 F.2d 13 (Tenth Circuit, 1967)
Maryland Casualty Co. v. Conner
382 F.2d 13 (Tenth Circuit, 1967)
Bushman Construction Co. v. Conner
260 F. Supp. 779 (D. Colorado, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
327 F.2d 481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bushman-construction-company-v-air-force-academy-housing-incorporated-ca10-1964.