McNeill v. Allen

534 P.2d 813, 35 Colo. App. 317
CourtColorado Court of Appeals
DecidedFebruary 11, 1975
Docket73-423
StatusPublished
Cited by48 cases

This text of 534 P.2d 813 (McNeill v. Allen) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McNeill v. Allen, 534 P.2d 813, 35 Colo. App. 317 (Colo. Ct. App. 1975).

Opinion

534 P.2d 813 (1975)

Rodney W. McNEILL and Pamela L. McNeill, Plaintiffs-Appellees,
v.
Roger L. ALLEN, an Individual, et al., Defendants-Appellees.
Gerald L. HAMMER, Defendant, Third-Party Plaintiff, and Appellant,
v.
A A ENGINEERS & ASSOCIATES, INC., a Colorado Corporation, Third-Party Defendant-Appellee.
The DENVER LUMBER CO., a Colorado Corporation, Plaintiff-Appellee,
v.
BRIARWOOD CORPORATION, a Colorado Corporation, et al., Defendants-Appellees,
and
Gerald L. Hammer, Defendant-Appellant.

No. 73-423.

Colorado Court of Appeals, Div. I.

February 11, 1975.
Rehearing Denied March 18, 1975.

*816 H. R. McCollister, Denver, for plaintiffs-appellees.

A. Daniel Rooney, Aurora, for defendant-appellant.

Selected for Official Publication.

ENOCH, Judge.

Defendant Gerald L. Hammer appeals from a judgment holding him liable on a house construction contract and for damages resulting from his fraudulent concealment of material information. We affirm the judgment as to the liability of defendant Hammer, but reverse as to certain elements of damages.

This case was tried to the court over several days and produced conflicting interpretations of the critical events and relationships between the parties. We accept the trial court's findings as to the facts, since there is evidence in the record to support those findings. Adler v. Adler, 167 Colo. 145, 445 P.2d 906.

Sometime in 1971 defendant Hammer, a licensed real estate broker, and defendant Roger L. Allen, a fledgling building contractor, made arrangements to work together in the business of constructing and selling houses. An entity known as The Briarwood Companies was formed to advance this business. During the summer of that year plaintiffs Rodney and Pamela McNeill, a young couple, met Allen and discussed the possibility of his constructing a house for them. At Allen's suggestions the McNeills met Hammer, who showed them certain building sites in Aurora. The McNeills chose one of these sites and Hammer appraised the house they then owned. On August 8, 1971, the McNeills and Allen signed a construction contract prepared by Hammer which set a price of $38,000 for the house and lot. When Allen obtained estimates of the cost of the house they proposed to build, it was discovered that the total cost would exceed the McNeills' budget. Ultimately plans were drawn up which appeared to fall within the budgetary limits of the McNeills and another draft of the contract was prepared and signed. Two principal issues at trial were whether there was a fixed price or a "cost-plus" contract, and which draft of the contract controlled. The court concluded that $38,000 was to be the maximum price under the contract, and that the contract prepared on August 8 was controlling.

Subsequently Hammer obtained title to the building lot chosen by the McNeills and conveyed title jointly to himself and Allen. A construction loan was obtained which was co-signed by both Allen and Hammer. Once construction got underway, Allen supervised the building, but Hammer had to approve all cost disbursements from the construction loan under his agreement with the lending institution.

The McNeills planned to sell their residence at 2838 East Euclid and use the proceeds from the sale as a down payment on the new house. Anticipating the completion of the new house in the spring they listed the East Euclid house for sale with a realtor in January of 1972. At the insistence of Hammer this listing was withdrawn and given to Hammer who found a buyer and scheduled a closing date for three days prior to the date on which the new house was expected to be ready for occupancy. On March 18, 1972, Hammer and the McNeills inspected the new house. On March 21 the closing was held on the East Euclid house. Then, on the afternoon of that same day, after completion of the closing, Allen informed the McNeills that cost overruns had driven the price of the new house up to about $43,000, a figure which he revised upward the next day to about $46,000. The trial court found that this was the first notice to the McNeills that they were expected to pay a price in excess of $38,000 for the new house.

The closing on the new house was never held. By giving $5,000 to Allen in exchange *817 for a promissory note they had previously given The Briarwood Companies, the McNeills obtained the keys to the house and moved in. At that time considerable work remained to be done to meet the specifications of the contract plans, including exterior painting and interior finishing. The house was mislocated on the lot, and acquisition of a strip of three feet from an adjoining lot, also owned by Hammer, was required to meet the city building code. Since that time Allen has filed a petition in bankruptcy and an order was issued by the referee in bankruptcy restraining any parties from proceeding against him. Several materialmen remained unpaid for materials provided for the house, and these claims were consolidated with the action brought by the McNeills to compel the closing at the contract price and for the recovery of damages.

The trial court found that Allen and Hammer had been engaged in a joint venture to construct and sell a house to the McNeills and that consequently Hammer was bound by the contract of August 8, 1971, to close at a price of $38,000. It further found that Hammer had believed at the time the contract was signed that the house could not be built for $38,000 but did not convey this information to the McNeills who reasonably believed the house could be built for that amount. It also found that the evidence was insufficient to show that in fact the house had cost more than $38,000 to build. Concluding that Hammer was liable for willful and wanton fraud, the court awarded damages for mental suffering to the McNeills, as well as exemplary damages in the amount of $10,000. The court found that the McNeills were entitled to the costs of bringing the house to contract specifications, the value lost to the McNeills by reason of loss of a favorable interest rate on their home loan resulting from the delay in closing, litigation expenses, and attorneys' fees. The court also found Hammer individually liable for the materialmens' liens that were proved.

I.

Hammer maintains that he was not engaged in a joint venture with Allen, but rather that he was the owner of the lot on which the McNeills' house was built and is entitled to compensation either as his profit on the sale of the land, or as a commission for services as a broker between the McNeills and Allen.

A joint venture will not arise by operation of law but only from the voluntary agreement of the parties, either express or implied. To establish a joint venture, all three of the following criteria must be demonstrated: (1) Joint interest in the appropriate property among those sought to be held as joint venturers, (2) an express or implied agreement to share in profits and losses of the venture, and (3) actions and conduct showing cooperation in the project. Realty Development Co. v. Feit, 154 Colo. 44, 387 P.2d 898.

From the record it appears that Hammer and Allen held joint title in the lot on which the house was built. There was extensive cooperation shown by the joint obligation on the construction loan, shared knowledge of the disbursements from that loan, and Hammer's role in preparing the contract for the McNeills.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. Muth
Colorado Court of Appeals, 2025
Stellar v. Saucon Mutual Ins.
25 Pa. D. & C.5th 373 (Lehigh County Court of Common Pleas, 2012)
ROCKY MOUNTAIN FESTIVALS v. Parsons Corp.
242 P.3d 1067 (Supreme Court of Colorado, 2010)
In Re the Marriage of McSoud
131 P.3d 1208 (Colorado Court of Appeals, 2006)
Hoffman v. Stamper
867 A.2d 276 (Court of Appeals of Maryland, 2005)
Zeigler v. Fisher-Price, Inc.
261 F. Supp. 2d 1047 (N.D. Iowa, 2003)
Anson v. Trujillo
56 P.3d 114 (Colorado Court of Appeals, 2002)
Vanderbeek v. Vernon Corp.
50 P.3d 866 (Supreme Court of Colorado, 2002)
Vanderbeek v. Vernon Corp.
25 P.3d 1242 (Colorado Court of Appeals, 2001)
Webster v. Boone
992 P.2d 1183 (Colorado Court of Appeals, 1999)
Diamond Back Services, Inc. v. Willowbrook Water & Sanitation District
961 P.2d 1134 (Colorado Court of Appeals, 1997)
Stallworth Timber Co. v. Triad Building Supply
968 F. Supp. 279 (Virgin Islands, 1997)
Stevens v. Moore and Co. Realtor
874 P.2d 495 (Colorado Court of Appeals, 1994)
Swartz v. Bianco Family Trust
874 P.2d 430 (Colorado Court of Appeals, 1993)
Feit v. Donahue
826 P.2d 407 (Colorado Court of Appeals, 1992)
T.A. Pelsue Co. v. Grand Enterprises, Inc.
782 F. Supp. 1476 (D. Colorado, 1991)
David C. Olson, Inc. v. Denver & Rio Grande Western Railroad
789 P.2d 492 (Colorado Court of Appeals, 1990)
Parker v. Stein
557 A.2d 1319 (District of Columbia Court of Appeals, 1989)
Calvaresi v. National Development Co.
772 P.2d 640 (Colorado Court of Appeals, 1988)
Cornell v. Wunschel
408 N.W.2d 369 (Supreme Court of Iowa, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
534 P.2d 813, 35 Colo. App. 317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcneill-v-allen-coloctapp-1975.