Morris v. Redak

234 P.2d 908, 124 Colo. 27, 1951 Colo. LEXIS 164
CourtSupreme Court of Colorado
DecidedJune 25, 1951
Docket16439
StatusPublished
Cited by32 cases

This text of 234 P.2d 908 (Morris v. Redak) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morris v. Redak, 234 P.2d 908, 124 Colo. 27, 1951 Colo. LEXIS 164 (Colo. 1951).

Opinion

Mr. Justice Moore

delivered the opinion of the court.

We will herein refer to the parties as they appeared in the trial court, where defendant in error was plaintiff and plaintiff in error was defendant.

*29 In plaintiff’s complaint, he alleged, in substance, that defendant, who is an architect, and one E. B. Jones, a contractor, desired to bid on a United States contract for certain construction work at Buckley Field. They needed financial backing and defendant solicited plaintiff to provide it. Plaintiff further alleged that an oral contract and agreement was entered into between himself and defendant, under which he was to receive one-third of the net profits realized upon the said construction contract in consideration for the financial backing provided by himself and those associated with him. It also was alleged in the complaint that the total profit realized upon performance of said contract was $183,359.73 plus equipment valued at $2,576.31.

Plaintiff further alleged that the sum of $27,033.39 was received by him, and that he is entitled to receive the difference between said sum and one-third of the total net profit resulting from performance of said contract. He also alleged that defendant breached the oral contract between himself and defendant in the following particulars: “(a) In not paying plaintiff the balance due him of $34,086.52. (b) In employing Robert M. Morris at a salary greater than $500.00 a month, without the consent of plaintiff, said amount so paid being $7,781.90, at the rate of $1,000 a month from June 26, 1942 to December 31; January 1 to March 5, 1943 at $150.00 per week, and May 31, $300.00, together with unauthorized extras of $5,010.00. (c) In not submitting to plaintiff a correct report of the operations of the project to show the share of plaintiff and his associates, (d) In not promptly delivering the books to Atler for audit in 1943 when the job was completed, (e) In not giving plaintiff a list of personal property acquired under the contract, and not delivering to plaintiff his 1/3 thereof, (f) Without the approval of plaintiff, paying himself unauthorized expenses for his personal car and alleged travel of at least $440.00, one-third of which should be paid to plaintiff.”

*30 Plaintiff prayed judgment for one-third of the profits, for interest, for one-half the sum charged by an auditor who audited the books relating to the construction job, and for costs.

In his answer defendant set forth two defenses, the first of which consisted partly of admissions and partly of denials of matters alleged in the complaint. In his second defense he alleged that plaintiff’s contract with him called for only a one-fourth interest in the net profits accruing from said construction contract, and that the balance due plaintiff upon this alleged one-fourth interest was the sum of $19,647.87.

In paragraph 3 of said second defense it is alleged: “Defendant hereby tenders to the plaintiff and is ready, able and willing to pay to the plaintiff at this or any time the full balance in said sum of $19,647.87, shown in said Exhibit A hereto attached.” Defendant prayed that plaintiff be required to accept and receive said tendered sum in full settlement and discharge of his claim and demand.

A pretrial conference was held at which the issue to be determined was stipulated and agreed to be as follows: Was the plaintiff entitled to one-third of the net profits plus the following items: “(a) One-third of the amount paid Robert M. Morris over $500 per month or an alleged total of $8,691.90 overpayment, (b) One-third of $440 charged as car expense on the project by Earl Morris. (c) One-third of alleged $500 attorney fee paid for services rendered the project and which it is stipulated the same was paid, (d) One-third of $1,298.00 office salaries paid, and that proof be required of such payment. (e) One-third of transportation charge of $285, and that proof be required of such payment”?

Plaintiff accepted the statement of defendant that, subject to the determination of the foregoing issues, the net profit derived from the project was $185,555.99 which was reflected by the books kept by the auditor Dolberg, *31 in which no recognition was given to the claims of plaintiff in those matters reserved for trial to the court.

By stipulation between the parties the case was divided into two parts for trial, the first of which involved the question as to whether the interest of plaintiff was one-third or one-fourth of the net profits. In connection with this issue the record discloses a further stipulation in the following words: “It is stipulated between counsel that the only issue in the case to be submitted to the Jury is whether the oral contract is a one-third interest or one-fourth interest of Redak, and that all the other issues will be passed upon by the Court.”

February 26, 1949, the jury returned a verdict in the following form: “We, the jury, find that the contract between the plaintiff, R. H. Redak, and the defendant, Earl Chester Morris, was that the plaintiff, Redak, was to receive one-third of the profits from the Buckley Field project.” The verdict was received and recorded and the trial court withheld any written decree or judgment based on said verdict, “until findings and Decree of Court on equity issues is entered.”

On various dates between April 1, and May 13, 1949, the trial court heard the evidence offered in connection with the second phase of the case, and on September 19, 1949, it entered its conclusions, findings and order, and each party was granted thirty days within which to file objections thereto. Each of the parties filed objections to said findings, and the court, after hearing said objections, entered its amended conclusions and findings on November 29, 1949, in which it found that one-third of the profit derived from the project was the sum of $61,902.79, and that $27,084.19 had been paid to Redak, leaving a balance of principal due and owing him, from defendant, of $34,818.60. We quote, inter alia, from the - court’s amended conclusions and findings:

“The evidence further shows from an audit on January 27, 1944, by one Edgar Dolberg, Registered Accountant,

*32 and which audit was submitted to the defendant, that as of that date the following distribution of profits of the project had been made by the defendant to himself and others of the following amounts, to-wit:

“Total Amount
“Date Distributed
February 4, 1943 $ 30,000.00
May 3, 1943 45.000. 00
November 29, 1943 26.000. 00

and plaintiff’s share of these distributions should have been $10,000.00, $15,000.00 and $8,666.67 respectively. Through a mistake in book-keeping, which was discovered through the audit there was distributed to Morris and Jones $8,246.45 as of January 1, 1944 through payment of the funds of the project to one of the defendant’s other operations, of which sum $2,748.81 was the property of plaintiff.

“On August 21, 1944, the balance in the Buckley Field checking account of $3,733.23 was distributed between defendant and Bob Morris and E. B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Levy v. Levitt
3 F. App'x 944 (Tenth Circuit, 2001)
Cherry Creek School District 5 v. Voelker Ex Rel. Voelker
859 P.2d 805 (Supreme Court of Colorado, 1993)
Frontier Exploration, Inc. v. American National Fire Insurance Co.
849 P.2d 887 (Colorado Court of Appeals, 1992)
Songer v. Bowman
804 P.2d 261 (Colorado Court of Appeals, 1991)
Kline Hotel Partners v. Aircoa Equity Interests, Inc.
729 F. Supp. 740 (D. Colorado, 1990)
Weber v. Wallace
789 P.2d 427 (Colorado Court of Appeals, 1989)
Neil v. Espinoza
747 P.2d 1257 (Supreme Court of Colorado, 1987)
Shultz v. Linden-Alimak, Inc.
734 P.2d 146 (Colorado Court of Appeals, 1986)
Heating & Plumbing Engineers, Inc. v. H.J. Wilson Co.
698 P.2d 1364 (Colorado Court of Appeals, 1985)
Graefe & Graefe, Inc. v. Beaver Mesa Exploration Co.
695 P.2d 767 (Colorado Court of Appeals, 1984)
Kading v. Kading
683 P.2d 373 (Colorado Court of Appeals, 1984)
People v. Graham
678 P.2d 1043 (Colorado Court of Appeals, 1983)
Galowich v. Beech Aircraft Corp.
441 N.E.2d 318 (Illinois Supreme Court, 1982)
Denver Urban Renewal Authority v. Hayutin
583 P.2d 296 (Colorado Court of Appeals, 1978)
Davis Cattle Co., Inc. v. Great Western Sugar Company
393 F. Supp. 1165 (D. Colorado, 1975)
McNeill v. Allen
534 P.2d 813 (Colorado Court of Appeals, 1975)
Goodfellow v. Kattnig
533 P.2d 58 (Colorado Court of Appeals, 1975)
Rosenthal v. Sandusky
533 P.2d 523 (Colorado Court of Appeals, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
234 P.2d 908, 124 Colo. 27, 1951 Colo. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morris-v-redak-colo-1951.