Heating & Plumbing Engineers, Inc. v. H.J. Wilson Co.

698 P.2d 1364
CourtColorado Court of Appeals
DecidedApril 15, 1985
Docket82CA1209
StatusPublished
Cited by10 cases

This text of 698 P.2d 1364 (Heating & Plumbing Engineers, Inc. v. H.J. Wilson Co.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heating & Plumbing Engineers, Inc. v. H.J. Wilson Co., 698 P.2d 1364 (Colo. Ct. App. 1985).

Opinion

VAN CISE, Judge.

Plaintiff, Heating and Plumbing Engineers, Inc. (the subcontractor) brought this action to collect the amount due, and to foreclose a mechanic’s lien, for duct work manufactured by it for use in a building being constructed by defendant H.W. Houston Construction Company (the contractor) for defendant H.J. Wilson Co., Inc. (the owner). The contractor cross-claimed against the owner for a judgment for the value of the materials, labor, and other services and expenses furnished by it to the project and for a decree foreclosing its own mechanic’s lien therefor. The owner cross-claimed against the contractor for indemnification for any amount determined to be due to the subcontractor and for recovery of its attorneys’ fees and costs.

Following a trial without a jury, the court decreed foreclosure of the subcontractor’s lien against the owner’s property in the amount claimed and entered a money judgment against the contractor in favor of the subcontractor. These rulings have not been appealed.

Relative to the contractor, the court found that it was the contractor and not the owner who breached the contract, that the benefit conferred on the property was worth only $180, and that the contractor’s mechanic’s lien claim was, and was known to be, excessive at the time it was filed. Based on those findings, the trial court denied the contractor’s cross-claims except for the allowance of $180 on a quantum meruit basis, and entered a judgment against it for $65,754 in attorney’s fees and $354.60 in costs incurred by the owner. The contractor appeals the denial of its cross-claims and the judgment against it for the owner's costs and attorneys’ fees. We affirm.

The court denied the owner’s cross-claims for indemnity from the contractor and allowed only a portion of its attorneys’ out-of-pocket expenses. The owner appeals those orders, and we affirm the denial of indemnity and remand as to the attorneys’ expenses.

The owner proposed to build a show room at a Colorado Springs shopping mall. The contractor, who had done work for the owner on two previous projects, was the low bidder at approximately $1.7 million. On the earlier jobs, there had been disputes concerning change orders, and this past experience was a sore point between them. Following a meeting on March 12, 1981, at which the trial court found that the contractor agreed to perform change order work without any mark-up for overhead and profit, the owner gave the contractor notice to proceed immediately with the job. It was understood that formal contract documents embodying the terms agreed to would be prepared and executed shortly thereafter.

The contractor then moved equipment into the area and did some preliminary work. It also instructed the subcontractor to commence work. By March 27, the subcontractor had done the amount of work reflected in its later-filed lien statement.

On March 27, the contractor refused to sign formal contract documents incorporating the provision concerning no mark-up on change order work. Based on that refusal, the owner ordered the contractor to cease all work on the project. The owner then retained a different contractor who agreed to and did complete the project for less money.

On April 6, the contractor notified the owner of its intention to file a lien for the full amount of its contract, $1.7 million. On June 5, the lien statement was filed for that amount. On October 1, an amended lien was filed for $44,000. In the meantime, the subcontractor filed its lien statement and commenced this action.

I.

The contractor’s first contention is that its breach of contract, if any, was not a material one and, therefore, the owner was *1367 not justified in terminating the contract. We disagree.

The court found, and the evidence supports the finding, that the parties had agreed that there would be no mark-up on change orders. Therefore, when the contractor elected not to proceed under that arrangement, it breached the contract. This was a “present, positive, unequivocal refusal to perform the contract,” Gold Mining & Water Co. v. Swinerton, 23 Cal.2d 19, 142 P.2d 22 (1943), and, in view of the past history, was a material breach. Hence, the owner was justified in terminating the contract.

II.

The contractor admits that its lien claims were for more than the amount actually due. However, it contends that, under § 38-22-101(2), C.R.S. (1982 Repl.Vol. 16A), it was entitled to file a lien for the entire contract price and, therefore, it was error for the court to order a forfeiture of its lien rights. We agree with the owner that the contractor misinterprets the statute.

That statute provides:

“In case of a contract for the work, between the reputed owner and a contractor, the lien shall extend to the entire contract price, and such contract shall operate as a lien in favor of all persons performing labor or services or furnishing materials under contract, express or implied, with said contractor, to the extent of the whole contract price; and after all such liens are satisfied, then as a lien for any balance of such contract price in favor of the contractor.” (emphasis supplied)

This subsection on its face does not give a lien right to the contractor for the full contract price; at the most, all that the contractor is entitled to is the balance of the contract price remaining after all other liens have been satisfied.

Moreover, the quoted subsection must be viewed in conjunction with other subsections of § 38-22-101. Section 38-22-101(1) limits the lien of any person to the value of the materials, labor, or services provided. Thirteenth Street Corp. v. A-l Plumbing & Heating Co., 640 P.2d 1130 (Colo.1982). And, if the construction contract is not timely recorded, then under § 38-22-101(3) the owner is liable for the full value of labor or materials provided.

Construing the provisions of § 38-22-101 in their entirety, we conclude that subsection (2) does not enlarge the lien rights of the contractor beyond the reasonable value of the materials, labor, and services furnished by it. Rather, if, contrary to what happened here, the contract had been timely recorded, then the contract price would have represented the maximum value of all liens that could have been asserted.

The trial court found that the contractor’s lien claims “were for amounts greater than were due at the time without a reasonable possibility that those amounts claimed were due, and with knowledge that those amounts claimed were greater than the amount due.” Those findings are supported by the evidence and are, therefore, binding on us. Broncucia v. McGee, 173 Colo. 22, 475 P.2d 336 (1970). Based on those findings, the court correctly ruled that the contractor forfeited its lien rights and also is liable to the owner “in an amount equal to the costs and all attorney’s fees.” See § 38-22-128, C.R.S. (1982 Repl.Vol. 16A).

III.

Section 38-22-128, C.R.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byerly v. Bank of Colo.
411 P.3d 732 (Colorado Court of Appeals, 2013)
Roget v. Grand Pontiac, Inc.
5 P.3d 341 (Colorado Court of Appeals, 2000)
LSV, Inc. v. Pinnacle Creek, LLC
996 P.2d 188 (Colorado Court of Appeals, 1999)
People v. Bergen
883 P.2d 532 (Colorado Court of Appeals, 1994)
Independent Trust Corp. v. Stan Miller, Inc.
796 P.2d 483 (Supreme Court of Colorado, 1990)
Wigham Excavating Co. v. Colorado Federal Savings & Loan Ass'n
796 P.2d 23 (Colorado Court of Appeals, 1990)
Durango Transportation, Inc. v. City of Durango
786 P.2d 428 (Colorado Court of Appeals, 1990)
Stan Miller, Inc. v. Breckenridge Resort Associates, Inc.
779 P.2d 1365 (Colorado Court of Appeals, 1989)
Heating & Plumbing Engineers, Inc. v. H.J. Wilson Co.
708 P.2d 808 (Colorado Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
698 P.2d 1364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heating-plumbing-engineers-inc-v-hj-wilson-co-coloctapp-1985.