David C. Olson, Inc. v. Denver & Rio Grande Western Railroad

789 P.2d 492, 14 Brief Times Rptr. 210, 1990 Colo. App. LEXIS 47
CourtColorado Court of Appeals
DecidedFebruary 22, 1990
Docket87CA1851, 88CA0331
StatusPublished
Cited by2 cases

This text of 789 P.2d 492 (David C. Olson, Inc. v. Denver & Rio Grande Western Railroad) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David C. Olson, Inc. v. Denver & Rio Grande Western Railroad, 789 P.2d 492, 14 Brief Times Rptr. 210, 1990 Colo. App. LEXIS 47 (Colo. Ct. App. 1990).

Opinion

Opinion by

Judge CRISWELL.

Defendant, Denver & Rio Grande Western Railroad Co. (the railroad), appeals from that part of the trial court’s judgment which awarded David C. Olson, Inc. (the prime contractor), a judgment against the railroad for a portion of the attorney fees incurred by Howard Electrical & Mechanical, Inc., (the sub-contractor) in prosecuting a claim against the prime contractor. The railroad asserts that there is no legal basis for the award of any such fees. The prime contractor cross-appeals, claiming that the trial court erred in its allocation of the sub-contractor’s litigation expenses between the railroad and it. We affirm the judgment.

The railroad entered into a written agreement with the prime contractor to have substantial modifications and improvements made to the Moffat Tunnel. This agreement contained no provision for the recovery of attorney fees in the event of litigation.

A subsequent agreement was then executed by the prime contractor and the subcontractor under which the sub-contractor agreed to provide a portion of the labor and materials required by the railroad’s contract. Unlike the prime contract, however, the sub-contract provided that the prevailing party in any litigation concerning the *494 rights or obligations under the sub-contract would be entitled to recover reasonable attorney fees from the other party.

As construction on the project progressed, substantial problems arose and a 15-month delay in completion resulted. This delay caused both the prime contractor and the sub-contractor to suffer a substantial increase in costs.

The prime contractor asserted that the delay resulted, in part, from certain acts and omissions of the railroad and, in part, from the deficient work of the sub-contractor. Thus, it refused to pay the sub-contractor for a portion of the work that had been completed under the sub-contract, and it initiated legal action against the railroad seeking to recover additional costs and expenses caused by that portion of the delay allegedly attributable to the railroad. The damages requested in the prime contractor’s action against the railroad also included the additional costs and expenses of the sub-contractor, resulting from the delay, for which the prime contractor became liable under the sub-contract.

The trial court found that the sub-contractor’s work was not deficient and that the prime contractor’s refusal to pay the sub-contractor for a portion of its work was, therefore, improper. It further found, however, that the railroad was the party primarily responsible for the delay in the project and that both the prime contractor and the sub-contractor had incurred substantial additional expenses and liabilities as a result of the delay.

Based on these findings, the trial court entered a judgment in favor of the sub-contractor and against the prime contractor for a sum representing (1) the amount that was owed to the sub-contractor under the original sub-contract and approved change orders, (2) the additional costs and expenses resulting to the sub-contractor because of the delay, and (3) reasonable attorney fees pursuant to the terms of the subcontract.

In addition, a judgment was entered against the railroad and in favor of the prime contractor for a sum representing (1) the additional costs and expenses incurred directly by the prime contractor as a result of the delay and (2) the amount owed by the prime contractor to the sub-contractor, including 57.73% of the attorney fees included within the sub-contractor’s judgment against the prime contractor. The trial court’s allocation of the sub-contractor’s attorney fees was based on its finding that 42.27% of the sub-contractor’s damages resulted from the prime contractor’s refusal to pay a portion of the original sub-contract price (which the railroad had tendered, but the prime contractor had refused), while 57.73% of those damages resulted from the railroad’s delay.

I.

The railroad asserts that the prime contractor was not entitled to any reimbursement for the sub-contractor’s attorney fees as an item of damages because such recovery was not authorized either by the prime contract or by any statute. Under the unique circumstances presented here, we disagree.

The general “American rule” bars a litigant from recovering his attorney fees unless such an award is authorized either by contract or by statute. Publix Cab Co. v. Colorado National Bank, 139 Colo. 205, 338 P.2d 702 (1959). See Alyeska Pipeline Service Co. v. Wilderness Society, 421 U.S. 240, 95 S.Ct. 1612, 44 L.Ed.2d 141 (1975). Here, since the railroad was not a party to the contract between the prime contractor and the sub-contractor, we agree that the sub-contract’s provision for attorney fees could not, itself, justify an award of such fees against the railroad.

Nevertheless, we are convinced that the trial court’s award in this case was not an award of attorney fees, as such. The award was grounded upon the judgment that was entered by the court against the prime contractor; it was not based upon any fees incurred by the prime contractor.

Once a judgment enters, the nature of a party’s liability changes. The liability arising from a judgment is a new one, distinct from the liability upon which the judgment is based, and any prior liability merges into *495 that judgment. Akearn v. Goble, 90 Colo. 173, 7 P.2d 409 (1932) (liability under judgment survives death even though preceding liability might not have); Bassett v. Eagle Telecommunications, Inc., 750 P.2d 73 (Colo.App.1987) (once judgment enters, statutory provisions relating to interest on appeal applies to entire judgment irrespective of differing basis for portion of damages). See also Scognamillo v. Olsen, — P.2d - (Colo.App. No. 87CA1489, February 1, 1990) (client may collect from attorney full amount of judgment resulting from attorney’s negligence even though a portion of judgment was for punitive damages).

Circumstances similar to the facts disclosed by this record are to be found in Roach Aircraft, Inc. v. Sable, 513 P.2d 244 (Colo.App.1973) (not selected for official publication). There, a bank’s violation of an agreement to release the plaintiff from liability under a promissory note caused the original payee of the note to sue the plaintiff. In that litigation, the payee was awarded a judgment which included the attorney fees called for by the note. In a later suit by plaintiff against the bank, judgment was entered against the bank for the full amount of the payee’s recovery against the plaintiff, including that portion of the judgment representing attorney fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barrett v. Investment Management Consultants, Ltd.
190 P.3d 800 (Colorado Court of Appeals, 2008)
Printz Services Corp. v. Main Electric, Ltd.
949 P.2d 77 (Colorado Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
789 P.2d 492, 14 Brief Times Rptr. 210, 1990 Colo. App. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-c-olson-inc-v-denver-rio-grande-western-railroad-coloctapp-1990.